Welcome to the Proposal Letting List Page. We now include the approximate items of work with each proposal. Please e-mail us with your comments.


1. BR-0001(565), ETOWAH 3. HSIPF-I059(375), SUMTER
5. IMF-I085(349), ETC., MONTGOMERY 7. NHF-MR15(900), TUSCALOOSA
26. ACNU59357-ATRP(004), BIBB 28. ACNU61857-ATRP(004), LIMESTONE
34. ACOA59748-ATRP(009), COLBERT 35. ACOA61158-ATRP(002), BALDWIN
38. BR-0008(562), LOWNDES, ETC. 42. CMAQ-3715(250), JEFFERSON
48. HSIP-I065(443), LIMESTONE 49. HSIP-I565(311), LIMESTONE, ETC.
52. IM-I065(450), MONTGOMERY 55. NH-0003(594), ESCAMBIA
56. NH-0013(598), FAYETTE 57. NH-0020(524), COLBERT
58. NH-0035(529), DEKALB 61. NH-HSIP-0005(548), WILCOX
65. SRTS-SR13(907), JEFFERSON 68. STPOA-0004(541), ST. CLAIR
69. STPAA-0025(544), CHEROKEE 70. STPOA-0027(511), COFFEE
* 71. STPAA-0091(505), CULLMAN 72. STPAA-0172(503), FRANKLIN
74. STPAA-0247(503), COLBERT 76. STPAA-7804(604), AUTAUGA
78. STPAA-HSIP-0007(540), ST. CLAIR 79. STPAA-HSIP-0008(580), MACON
80. STPAA-HSIP-0010(540), PIKE 81. STPAA-HSIP-0046(506), CLEBURNE
82. STPAA-HSIP-0052(511), ETC., GENEVA 85. STPAA-NR13(953), SUMTER
93. STPOA-STPNU-4415(251), MACON 94. STPNU-6415(250), WALKER
96. STPOA-0815(251), CALHOUN 98. STPOA-7425(601), CALHOUN

* - WITHDRAWN FROM THE LETTING

The Bracket Ranges shown herein are to provide general financial information to Contractors and Bonding Companies concerning a Project's complexity and size. THESE BRACKETS SHOULD NOT BE USED IN PREPARING A BID, NOR WILL THESE BRACKETS HAVE ANY BEARING ON THE DECISION TO AWARD ANY CONTRACT.


1.BR-0001(565) ,ETOWAH COUNTY

Contract Time: 310 Working Days

DBE Goal Percent:5.00

for constructing the Replacement of Dual Bridges and Widening (Grade, Drain Base, Pave, Signals, and Pedestrian Bridge) on SR-1 (US-431) over Black Creek to include the removal of a Pedestrian Bridge and Retaining Wall in Gadsden. Length 0.681 mi.

The Bracket Estimate on this project is from $7,042,429 to $8,607,414 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $61.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


3.HSIPF-I059(375) ,SUMTER COUNTY

Contract Time: 150 Working Days

for constructing the Median Barrier Protection (Cable Guiderail Installation) on I-59 from the Mississippi State Line (MP 0.000) to the Tombigbee River Dual Bridges (MP 27.000). Length 26.999 mi.

The Bracket Estimate on this project is from $1,492,055 to $1,823,622 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $6.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


5.HSIP-I085(348) & IMF-I085(349) ,MONTGOMERY COUNTY

Contract Time: 105 Working Days

DBE Goal Percent:5.00

for constructing the Pavement Rehabilitation (Planing, Resurfacing, Guardrail, and the Installation of Intelligence Transportation Systems Devices) on I-85 from just east of the Ann Street Exit to just west of the SR-8 (US-80/Eastern Boulevard) Interchange in Montgomery. Length 3.100 mi.

The Bracket Estimate on this project is from $8,852,380 to $10,819,575 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $7.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


7.NHF-MR15(900) ,TUSCALOOSA COUNTY

Contract Time: 90 Working Days

DBE Goal Percent:8.00

for constructing the Installation and Removal of Signals (Grade, Drain, Base, Pave, and Signals) on SR-6 (US-82/McFarland Boulevard) from 0.100 mile east of the junction of 26th Avenue (MP 46.130) to the intersection of SR-7 (US-11/Skyland Boulevard). Length 3.016 mi.

The Bracket Estimate on this project is from $4,542,478 to $5,551,918 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $66.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


26.ACNU59357-ATRP(004) ,BIBB COUNTY

Contract Time: 45 Working Days

DBE Goal Percent:3.00

for constructing the Resurfacing and Traffic Stripe on CR-20 from the junction of SR-6 (US-82) east of Centreville to the junction of SR-139 in Randolph. Length 10.379 mi.

The Bracket Estimate on this project is from $1,551,103 to $1,895,792 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


28.ACNU61857-ATRP(004) ,LIMESTONE COUNTY

Contract Time: 30 Working Days

DBE Goal Percent:6.00

for constructing the Resurfacing and Traffic Stripe on Thach Road from the junction of the I-65 Interchange east of Elkmont to the intersection of SR-251. Length 4.896 mi.

The Bracket Estimate on this project is from $1,094,139 to $1,337,281 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


34.ACOA59748-ATRP(009) ,COLBERT COUNTY

Contract Time: 200 Working Days

DBE Goal Percent:10.00

for constructing the Additional Lanes (Grade, Drain, Base, and Pave) on Avalon Avenue from the junction of South Montgomery Avenue in Tuscumbia to the junction of Cox Boulevard in Muscle Shoals. Length 1.159 mi.

The Bracket Estimate on this project is from $3,940,503 to $4,816,170 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $31.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


35.ACOA61158-ATRP(002) ,BALDWIN COUNTY

Contract Time: 110 Calendar Days

DBE Goal Percent:8.00

for constructing the Intersection Improvements (Roundabout Installation) on CR-48 (Fairhope Avenue) at the intersection of CR-13 in Fairhope. Length 0.135 mi.

The Bracket Estimate on this project is from $1,245,603 to $1,522,404 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $29.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


38.BR-0008(562) ,LOWNDES AND MONTGOMERY COUNTIES

Contract Time: 190 Working Days

DBE Goal Percent:8.00

for constructing the Bridge Replacement (Grade, Drain, Base, and Pave) on SR-8 (US-80) over Pintlala Creek (Westbound Lanes) west of Mt. Sinai. Length 0.972 mi.

The Bracket Estimate on this project is from $4,437,043 to $5,423,052 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $40.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


42.CMAQ-3715(250) ,JEFFERSON COUNTY

Contract Time: 70 Working Days

for constructing the Sidewalks along Ross Bridge Parkway from the intersection of Deer Trail to a point near Deer Valley Elementary School in Hoover. Length 0.987 mi.

The Bracket Estimate on this project is from $787,835 to $962,910 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $17.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


48.HSIP-I065(443) ,LIMESTONE COUNTY

Contract Time: 65 Working Days

DBE Goal Percent:3.00

for constructing the Median Crossover Protection (Cable Guiderail Installation) on I-65 from a point near the Norfolk Southern Railroad Overpass (MP 341.400) north of Mooresville to 0.100 mile south of the SR-3 (US-31) Overpass in Athens and from 1.300 miles north of the SR-53 Underpass (MP 366.200) to the Tennessee State Line. Length 12.799 mi.

The Bracket Estimate on this project is from $1,108,784 to $1,355,181 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $6.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


49.HSIP-I565(311) ,LIMESTONE AND MADISON COUNTIES

Contract Time: 50 Working Days

for constructing the Median Crossover Protection (Cable Guiderail Installation) on I-565 from a point near Spring Branch (MP 0.100) to CR-1036 (Madison Boulevard Overpass/MP 13.300) in Huntsville. Length 8.934 mi.

The Bracket Estimate on this project is from $809,004 to $988,783 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $7.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


52.IM-I065(450) ,MONTGOMERY COUNTY

Contract Time: 40 Working Days

DBE Goal Percent:3.00

for constructing the Planing, Resurfacing, and Traffic Stripe on I-65 from north of Pintlala Creek (MP 161.500) to Catoma Creek (MP 167.103) in Montgomery. Length 5.602 mi.

The Bracket Estimate on this project is from $1,757,919 to $2,148,568 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


55.NH-0003(594) ,ESCAMBIA COUNTY

Contract Time: 60 Working Days

DBE Goal Percent:3.00

for constructing the Resurfacing and Traffic Stripe on SR-3 (US-31) from north of the intersection of Tiger Drive/Douglas Lane (MP 71.961) to just south of the Conecuh County Line (MP 81.196) in Brewton. Length 9.235 mi.

The Bracket Estimate on this project is from $1,761,504 to $2,152,950 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $7.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


56.NH-0013(598) ,FAYETTE COUNTY

Contract Time: 30 Working Days

DBE Goal Percent:3.00

for constructing the Resurfacing and Traffic Stripe on SR-13 from the Tuscaloosa County Line (MP 223.040) to the junction of SR-18 (The Berry "Y"/MP 226.550) southwest of Berry. Length 3.510 mi.

The Bracket Estimate on this project is from $1,396,781 to $1,707,177 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $5.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


57.NH-0020(524) ,COLBERT COUNTY

Contract Time: 45 Working Days

DBE Goal Percent:4.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-20 from the junction of SR-157 (MP 32.190) to a point near CR-48 (MP 36.220) south of Leighton. Length 3.990 mi.

The Bracket Estimate on this project is from $1,926,630 to $2,354,771 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


58.NH-0035(529) ,DEKALB COUNTY

Contract Time: 45 Working Days

DBE Goal Percent:3.00

for constructing the Resurfacing and Traffic Stripe on SR-35 from north of the Cherokee County Line (MP 14.590) to the intersection of CR-89 (Desoto Parkway) in Fort Payne. Length 5.020 mi.

The Bracket Estimate on this project is from $2,101,185 to $2,568,115 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $6.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


61.NH-HSIP-0005(548) ,WILCOX COUNTY

Contract Time: 30 Working Days

DBE Goal Percent:3.00

for constructing the Safety Widening, Planing, Resurfacing, and Traffic Stripe on SR-5 from Moccasin Creek (MP 9.359) to 0.320 mile north of the intersection of SR-10 in Pine Hill. Length 1.987 mi.

The Bracket Estimate on this project is from $819,840 to $1,002,027 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $6.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


65.SRTS-SR13(907) ,JEFFERSON COUNTY

Contract Time: 45 Working Days

DBE Goal Percent:5.00

for constructing the Sidewalks and Improvements along 7th Avenue at Pleasant Grove Elementary School in Pleasant Grove. Length 0.227

The Bracket Estimate on this project is from $107,107 to $130,909 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $9.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


68.STPOA-0004(541) ,ST. CLAIR COUNTY

Contract Time: 45 Working Days

DBE Goal Percent:3.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-4 (US-78) from the I-20 Interchange to the intersection of SR-53 (US-231) in Pell City. Length 3.220 mi.

The Bracket Estimate on this project is from $901,532 to $1,101,872 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


69.STPAA-0025(544) ,CHEROKEE COUNTY

Contract Time: 45 Working Days

DBE Goal Percent:3.00

for constructing the Resurfacing and Traffic Stripe on SR-25 (US-411) from just south of the intersection of SR-283 (US-411 Bypass/MP 243.800) to just east of the junction of CR-161 (MP 249.000). Length 5.200 mi.

The Bracket Estimate on this project is from $1,469,398 to $1,795,930 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $5.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


70.STPOA-0027(511) ,COFFEE COUNTY

Contract Time: 30 Working Days

DBE Goal Percent:3.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-27 from south of the junction of CR-636 to the intersection of SR-192 (Boll Weevil Circle) in Enterprise. Length 3.071 mi.

The Bracket Estimate on this project is from $1,545,345 to $1,888,755 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $8.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


71.STPAA-0091(505) ,CULLMAN COUNTY

Contract Time: 75 Working Days

DBE Goal Percent:8.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-91 from south of the junction of CR-38 (MP 14.330) northeast of Colony to the intersection of SR-3 (US-31/MP 25.170) in Hanceville. Length 10.839 mi.

The Bracket Estimate on this project is from $2,206,283 to $2,696,568 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $6.00 per set.

*** WITHDRAWN FROM THE LETTING ***

Return To: Proposal Letting List (Top of web page)


72.STPAA-0172(503) ,FRANKLIN COUNTY

Contract Time: 40 Working Days

DBE Goal Percent:6.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-172 from the junction of SR-19 (MP 0.000) east of Vina to a point near the junction of Wilson West Road (MP 5.600) northwest of Hodges. Length 5.371 mi.

The Bracket Estimate on this project is from $1,499,278 to $1,832,451 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


74.STPAA-0247(503) ,COLBERT COUNTY

Contract Time: 30 Working Days

DBE Goal Percent:5.00

for constructing the Resurfacing and Traffic Stripe on SR-247 from the intersection of CR-49 (MP 20.820) to the junction of SR-2 (US-72/MP 24.850) east of Barton. Length 4.010 mi.

The Bracket Estimate on this project is from $757,683 to $926,057 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


76.STPAA-7804(604) ,AUTAUGA COUNTY

Contract Time: 45 Working Days

DBE Goal Percent:5.00

for constructing the Planing, Widening, Resurfacing, and Traffic Stripe on CR-2 (East Main Street) from the intersection of SR-3 (US-31/South Memorial Drive) to the junction of Shady Oak Drive in Prattville. Length 0.861 mi.

The Bracket Estimate on this project is from $725,713 to $886,983 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $9.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


78.STPAA-HSIP-0007(540) ,ST. CLAIR COUNTY

Contract Time: 45 Working Days

DBE Goal Percent:4.00

for constructing the Safety Widening, Planing, Resurfacing, and Traffic Stripe on SR-7 (US-11) from the intersection of SR-53 (US-231) to the South Town Limits of Steele (MP 181.341). Length 4.967 mi.

The Bracket Estimate on this project is from $1,253,224 to $1,531,718 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


79.STPAA-HSIP-0008(580) ,MACON COUNTY

Contract Time: 60 Working Days

DBE Goal Percent:4.00

for constructing the Safety Widening, Planing, Resurfacing, and Traffic Stripe on SR-8 (US-80) from the junction of CR-40 (MP 157.530) in Shorter to the beginning of the divided 4-lane section (MP 167.290) west of Tuskegee. Length 9.759 mi.

The Bracket Estimate on this project is from $2,512,928 to $3,071,357 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


80.STPAA-HSIP-0010(540) ,PIKE COUNTY

Contract Time: 40 Working Days

DBE Goal Percent:5.00

for constructing the Safety Widening, Planing, Resurfacing, and Traffic Stripe on SR-10 from the end of the curb section east of Brundidge (MP 181.063) to the Barbour County Line. Length 6.303 mi.

The Bracket Estimate on this project is from $1,367,708 to $1,674,643 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $11.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


81.STPAA-HSIP-0046(506) ,CLEBURNE COUNTY

Contract Time: 75 Working Days

DBE Goal Percent:10.00

for constructing the Safety Widening, Planing, Resurfacing, and Traffic Stripe on SR-46 from a point (MP 5.005) south of the I-20 overpass in Heflin to a point (MP 10.954) near the junction of CR-620. Length 5.949 mi.

The Bracket Estimate on this project is from $3,044,010 to $3,720,457 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $4.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


82.STPAA-HSIP-0027(512) & STPAA-HSIP-0052(511) ,GENEVA COUNTY

Contract Time: 60 Working Days

DBE Goal Percent:4.00

for constructing the Safety Widening, Planing, Resurfacing, and Traffic Stripe on SR-52 from the junction of SR-196 to the East City Limits of Geneva and on SR-27 from the junction of SR-52 to the junction of CR-8. Length 6.252 mi.

The Bracket Estimate on this project is from $2,530,426 to $3,092,742 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $15.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


85.STPAA-NR13(953) ,SUMTER COUNTY

Contract Time: 35 Working Days

for constructing the Curb Ramp Installations and Modifications on various routes at various locations in Livingston and York as indicated by the plans.

The Bracket Estimate on this project is from $114,469 to $139,907 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $9.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


93.STPOA-STPNU-4415(251) ,MACON COUNTY

Contract Time: 45 Working Days

DBE Goal Percent:3.00

for constructing the Resurfacing and Traffic Stripe on CR-69 from the junction of CR-22 to the intersection of SR-8 (US-80) (Site 1); on CR-57 from the junction of CR-59 to the junction of CR-54 (Site 2); and on CR-21 from the Tuskegee City Limits to the junction of SR-199 (Site 3). Length 7.662 mi.

The Bracket Estimate on this project is from $752,905 to $920,217 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $4.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


94.STPNU-6415(250) ,WALKER COUNTY

Contract Time: 45 Working Days

DBE Goal Percent:8.00

for constructing the Resurfacing, Guardrail Replacement, and Traffic Stripe on New Oakman Highway from the junction of Market Street in Oakman to the Right-of-Way of SR-269 in Parrish. Length 7.270 mi.

The Bracket Estimate on this project is from $1,384,785 to $1,692,515 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $5.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


96.STPOA-0815(251) ,CALHOUN COUNTY

Contract Time: 30 Working Days

for constructing the Bicycle and Pedestrian Improvements (Signing, Traffic Stipe, and Signals) at 14th Street, 11th Street, 18th Street, and Cobb Avenue in Anniston. Length 3.186 mi.

The Bracket Estimate on this project is from $99,607 to $121,742 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $15.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


98.STPOA-7425(601) ,CALHOUN COUNTY

Contract Time: 100 Working Days

DBE Goal Percent:5.00

for constructing the Intersection Improvements (Grade, Drain, Base, Pave, and Signals) on CR-389 (Lenlock Lane) at CR-324 (Saks Road) in Saks. Length 0.227 mi.

The Bracket Estimate on this project is from $626,014 to $765,128 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $16.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)