Office Engineer

Proposal Letting List
September 30, 2016, Transportation Letting

Welcome to the Proposal Letting List Page. We now include the approximate items of work with each proposal. Please e-mail us with your comments.

1. HPPF-AL06(902), MOBILE 17. ACAA60987-ATRP(010), JEFFERSON
18. ACOA61059-ATRP(016), TALLAPOOSA 21. ACBRAA59499-ATRP(006), SHELBY
25. ACBRZ59783-ATRP(005), ETOWAH 26. ACBRZ60304-ATRP(012), CHILTON
27. ACBRZ60345-ATRP(011), HALE 28. ACBRZ60533-ATRP(009), GENEVA
29. ACBRZ62120-ATRP(010), LAUDERDALE 30. ACBRZ63504-ATRP(017), FAYETTE
33. ACNU61727-ATRP(009), FAYETTE 36. ACOA59485-ATRP(006), MARSHALL
37. ACOA60968-ATRP(008), WALKER 38. ACOA61200-ATRP(003), ETOWAH
41. BR-0007(513), ST. CLAIR *42. BR-0014(517), AUTAUGA
48. STPAA-HSIP-0003(571), JEFFERSON 51. ERPR-8960(918), CLARKE
56. ERPR-9010(934), MORGAN 57. ERPR-9010(940), MACON
58. ERPR-9010(941), MACON 59. ERPR-9010(943), DALLAS
65. IM-I022(303), WALKER 66. IM-I059(392), GREENE
68. IM-I085(351), ETC., MACON 71. ITS-AL01(901), COLBERT, ETC.
74. NH-0016(520), MOBILE 75. NH-0157(521), LAUDERDALE
77. NH-HSIP-0074(538), ETC., CULLMAN 82. STPAA-0022(523), CHILTON
84. STPAA-0225(501), BALDWIN 85. STPAA-5516(250), PIKE
87. STPAA-NR13(948), CALHOUN, ETC. 90. STPBH-STPAA-0119(507), ETC., SHELBY
91. ACAA59425-ATRP(005), JEFFERSON 95. STPOA-0042(529), BALDWIN
96. RECA-0021(555), ESCAMBIA 97. STPOA-0215(250), BALDWIN
98. STPOA-2314(252), DALE 99. STPOA-3516(252), ETC., HOUSTON
106. 99-607-234-027-601, DALE
*-WITHDRAWN FROM THE LETTING

The Bracket Ranges shown herein are to provide general financial information to Contractors and Bonding Companies concerning a Project's complexity and size. THESE BRACKETS SHOULD NOT BE USED IN PREPARING A BID, NOR WILL THESE BRACKETS HAVE ANY BEARING ON THE DECISION TO AWARD ANY CONTRACT.


1.HPPF-AL06(902) ,MOBILE COUNTY

Contract Time: 90 Working Days

DBE Goal Percent: 5.00

for constructing the I-10 Eastbound Water Street On-Ramp Closure and Roadway Improvements (Minor Widening) at the Canal Street, Claiborne Street, and Texas Street Interchanges in Mobile. Length 1.242 mi.

The Bracket Estimate on this project is from $1,121,759 to $1,371,039 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $41.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


17.ACAA60987-ATRP(010) ,JEFFERSON COUNTY

Contract Time: 100 Working Days

DBE Goal Percent: 10.00

for constructing the Planing, Resurfacing, and Traffic Stripe on 4th Avenue Southwest from the junction of McAdory School Road to the intersection of 18th Street North and on Dartmouth Avenue from the intersection of SR-150 (14th Street North) to the junction of 36th Street South in Bessemer. Length 6.218 mi.

The Bracket Estimate on this project is from $2,174,491 to $2,657,711 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $18.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


18.ACOA61059-ATRP(016) ,TALLAPOOSA COUNTY

Contract Time: 120 Working Days

DBE Goal Percent: 3.00

for constructing the Roadway Improvements on Lee Street from the intersection of SR-38 (US-280) to the intersection of 5th Way and Resurfacing and Traffic Stripe on Washington Street from the Alexander City Limits to the junction of 5th Way. Length 2.975 mi.

The Bracket Estimate on this project is from $1,761,062 to $2,152,409 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $17.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


21.ACBRAA59499-ATRP(006) ,SHELBY COUNTY

Contract Time: 240 Working Days

DBE Goal Percent: 8.00

for constructing the Bridge Replacement and Approaches on CR-264 over Buck Creek in Alabaster. Length 0.548 mi.

The Bracket Estimate on this project is from $3,221,826 to $3,937,788 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $32.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


25.ACBRZ59783-ATRP(005) ,ETOWAH COUNTY

Contract Time: 150 Working Days

DBE Goal Percent: 5.00

for constructing the Bridge Replacement on CR-2 (Jackson Trail Road) over Locust Fork south of Altoona. Length 0.365 mi.

The Bracket Estimate on this project is from $1,479,630 to $1,808,436 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $20.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


26.ACBRZ60304-ATRP(012) ,CHILTON COUNTY

Contract Time: 45 Working Days

for constructing the Bridge Replacement (Precast) on CR-214 (Kieser Morgan Road) over a Spur of Mulberry Creek north of Maplesville. Length 0.012 mi.

The Bracket Estimate on this project is from $323,474 to $395,357 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $5.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


27.ACBRZ60345-ATRP(011) ,HALE COUNTY

Contract Time: 60 Working Days

for constructing the Bridge Replacement on CR-226 (Cutoff Road) over Millians Creek Tributary northwest of Cypress. Length 0.066 mi.

The Bracket Estimate on this project is from $319,258 to $390,204 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $7.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


28.ACBRZ60533-ATRP(009) ,GENEVA COUNTY

Contract Time: 125 Working Days

DBE Goal Percent: 6.00

for constructing the Bridge Replacement on CR-79 over Tight Eye Creek northeast of Samson. Length 0.170 mi.

The Bracket Estimate on this project is from $1,341,801 to $1,639,979 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $17.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


29.ACBRZ62120-ATRP(010) ,LAUDERDALE COUNTY

Contract Time: 190 Working Days

DBE Goal Percent: 4.00

for constructing the Bridge Replacements (Grade, Drain, Base, Pave, and Bridge) on CR-10 over Cypress Creek and Cypress Creek Relief. Length 0.231 mi.

The Bracket Estimate on this project is from $1,577,547 to $1,928,113 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $17.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


30.ACBRZ63504-ATRP(017) ,FAYETTE COUNTY

Contract Time: 70 Working Days

for constructing the Bridge Culvert Replacement on CR-21 over a Tributary to Luxapallila Creek. Length 0.037 mi.

The Bracket Estimate on this project is from $336,276 to $411,004 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $6.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


33.ACNU61727-ATRP(009) ,FAYETTE COUNTY

Contract Time: 30 Working Days

DBE Goal Percent: 3.00

for constructing the Planing, Resurfacing, and Traffic Stripe on CR-30 and CR-46 from the junction of SR-18 in Berry to the intersection of CR-83. Length 5.981 mi.

The Bracket Estimate on this project is from $800,210 to $978,035 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $4.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


36.ACOA59485-ATRP(006) ,MARSHALL COUNTY

Contract Time: 65 Working Days

DBE Goal Percent: 5.00

for constructing the Planing, Resurfacing, and Traffic Stripe on Industrial Boulevard from the junction of Wagner Drive to the junction of 1st Street in Albertville (Site 1) and on Jackson Street from the junction of SR-75 (South Broad Street) to the intersection of SR-205 (Baltimore Avenue) in Albertville (Site 2). Length 1.490 mi.

The Bracket Estimate on this project is from $763,981 to $933,754 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $18.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


37.ACOA60968-ATRP(008) ,WALKER COUNTY

Contract Time: 175 Working Days

DBE Goal Percent: 7.00

for constructing the Widening, Planing, Resurfacing, and Traffic Stripe (Grade, Drain, Base, Pave, and Sidewalk) on Viking Drive from the intersection of Delaware Avenue to the intersection of 20th Avenue East in Jasper. Length 1.347 mi.

The Bracket Estimate on this project is from $2,396,725 to $2,929,331 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $35.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


38.ACOA61200-ATRP(003) ,ETOWAH COUNTY

Contract Time: 60 Working Days

DBE Goal Percent: 5.00

for constructing the Planing, Resurfacing, and Traffic Stripe on 3rd Street from north of the junction of SR-25 (US-411) to the intersection of Tuscaloosa Avenue (Site 1) and on Goodyear Avenue from north of the intersection of SR-1 (US-431) to west of the intersection of SR-74 (US-278) (Site 2) in Gadsden. Length 2.926 mi.

The Bracket Estimate on this project is from $586,900 to $717,323 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $12.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


41.BR-0007(513) ,ST. CLAIR COUNTY

Contract Time: 200 Working Days

DBE Goal Percent: 6.00

for constructing the Bridge Replacements (Grade, Drain, Base, Pave, and Bridge) on SR-7 (US-11) over Muckleroy and Gulf Creeks. Length 0.382 mi.

The Bracket Estimate on this project is from $5,242,366 to $6,407,337 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $42.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


42.BR-0014(517) ,AUTAUGA COUNTY

Contract Time: 305 Working Days

DBE Goal Percent: 6.00

for constructing the Bridge Replacements (Grade, Drain, Base, Pave, Bridge Removal, and Bridge) on SR-14 over Ivy and Beaver Creeks west of Autuagaville. Length 1.713 mi.

The Bracket Estimate on this project is from $7,362,457 to $8,998,559 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $68.00 per set.

***WITHDRAWN FROM THE LETTING***

Return To: Proposal Letting List (Top of web page)


48.STPAA-HSIP-0003(571) ,JEFFERSON COUNTY

Contract Time: 130 Working Days

DBE Goal Percent: 6.00

for constructing the Safety Widening, Planing, Resurfacing, Traffic Stripe, and Safety Improvements on SR-3 (US-31) from the Locust Fork of the Black Warrior River Bridge (MP 294.170) to the Blount County Line. Length 4.620 mi.

The Bracket Estimate on this project is from $2,517,291 to $3,076,689 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $27.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


51.ERPR-8960(918) ,CLARKE COUNTY

Contract Time: 60 Working Days

DBE Goal Percent: 3.00

for constructing the Slope and Culvert Wing Repair on SR-69 from 1.300 miles north of the junction of SR-154 to 1.700 miles north of SR-154. Length 0.094 mi.

The Bracket Estimate on this project is from $611,161 to $746,974 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $18.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


56.ERPR-9010(934) ,MORGAN COUNTY

Contract Time: 45 Working Days

DBE Goal Percent: 3.00

for constructing the Slope Repair on SR-67 (Northbound Lane) at the bridge over the CSX Railroad in Decatur. Length 0.410 mi.

The Bracket Estimate on this project is from $1,663,071 to $2,032,643 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $20.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


57.ERPR-9010(940) ,MACON COUNTY

Contract Time: 30 Working Days

for constructing the Slope and Culvert Wing Repair on I-85 at MP 33.500 east of Franklin.

The Bracket Estimate on this project is from $119,195 to $145,683 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $6.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


58.ERPR-9010(941) ,MACON COUNTY

Contract Time: 45 Working Days

DBE Goal Percent: 2.00

for constructing the Slope Repair on I-85 (Southbound Lane) at MP 41.000 northeast of Tuskegee. Length 0.058 mi.

The Bracket Estimate on this project is from $349,849 to $427,593 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $7.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


59.ERPR-9010(943) ,DALLAS COUNTY

Contract Time: 30 Working Days

for constructing the Slope Repair on SR-5 (Southbound Lane) at the intersection of SR-8 (US-80/MP 47.630) in Browns.

The Bracket Estimate on this project is from $107,247 to $131,079 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $5.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


65.IM-I022(303) ,WALKER COUNTY

Contract Time: 70 Working Days

DBE Goal Percent: 4.00

for constructing the Planing, Resurfacing, and Traffic Stripe on I-22 from the Marion County Line to east of the CR-1 Overpass north of Eldridge. Length 1.829 mi.

The Bracket Estimate on this project is from $2,892,776 to $3,535,616 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $17.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


66.IM-I059(392) ,GREENE COUNTY

Contract Time: 30 Working Days

DBE Goal Percent: 3.00

for constructing the Resurfacing and Traffic Stripe on I-59 at the North and Southbound Rest Areas west of Eutaw.

The Bracket Estimate on this project is from $711,363 to $869,444 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $7.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


68.IM-I085(351), IM-I085(352) & IM-I085(353) ,MACON COUNTY

Contract Time: 65 Working Days

DBE Goal Percent: 5.00

for constructing the Planing, Resurfacing, and Traffic Stripe on I-85 from south of Shorter (MP 21.502) to north of the CR-36 Overpass (MP 35.836) northwest of Tuskegee. Length 14.331 mi.

The Bracket Estimate on this project is from $5,329,264 to $6,513,545 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $8.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


71.ITS-AL01(901) ,COLBERT AND LAUDERDALE COUNTIES

Contract Time: 100 Working Days

for constructing the ITS Integration System on SR-2 (US-72) from the intersection of SR-2 (US-72) in Muscle Shoals to the junction of Indian Springs Road in Florence.

The Bracket Estimate on this project is from $943,440 to $1,153,093 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $22.00 per set.

A MANDATORY pre-bid conference is scheduled for 10:00 AM on Thursday, September 22, 2016, at the Alabama Department of Transportation, North Region-Tuscumbia Area Office, 295 Highway 20 East, Tuscumbia, AL 35674. Any qualified bidder wishing to bid this proposal is required to have a company representative present at this MANDATORY pre-bid conference. Proposals issued to bidders who fail to attend the MANDATORY pre-bid conference and/or register their attendance will be voided and their bids will not be received nor considered.

View Items

Return To: Proposal Letting List (Top of web page)


74.NH-0016(520) ,MOBILE COUNTY

Contract Time: 40 Working Days

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-16 (US-90) from west of the intersection of Pine Hill Drive (MP 25.250) to the intersection of SR-163 (MP 25.869) in Mobile. Length 0.619 mi.

The Bracket Estimate on this project is from $319,672 to $390,710 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $11.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


75.NH-0157(521) ,LAUDERDALE COUNTY

Contract Time: 30 Working Days

DBE Goal Percent: 3.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-157 from north of the Singing River Bridges (MP 71.097) to the intersection of Huntsville Road (MP 71.593) in Florence. Length 0.490 mi.

The Bracket Estimate on this project is from $488,323 to $596,839 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


77.STPAA-HSIP-0069(550) & NH-HSIP-0074(538) ,CULLMAN COUNTY

Contract Time: 70 Working Days

DBE Goal Percent: 6.00

for constructing the Safety Widening, Planing, Resurfacing, Traffic Stripe, and Safety Improvements on SR-74 (US-278) from west of the I-65 Interchange to the junction of SR-69 in Cullman. Length 5.560 mi.

The Bracket Estimate on this project is from $3,448,218 to $4,214,489 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $22.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


82.STPAA-0022(523) ,CHILTON COUNTY

Contract Time: 80 Working Days

DBE Goal Percent: 3.00

for constructing the Resurfacing and Traffic Stripe on SR-22 from east of the junction of CR-15 (MP 58.250) to west of the junction of CR-53 (MP 64.900) in Clanton. Length 6.723 mi.

The Bracket Estimate on this project is from $2,701,027 to $3,301,255 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $13.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


84.STPAA-0225(501) ,BALDWIN COUNTY

Contract Time: 100 Working Days

DBE Goal Percent: 2.00

for constructing the Planing, Resurfacing, Traffic Stripe, and Culvert Replacement on SR-225 from the junction of CR-138 (Hurricane Road) to the junction of SR-59 in Stockton. Length 11.546 mi.

The Bracket Estimate on this project is from $2,027,543 to $2,478,108 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $12.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


85.STPAA-5516(250) ,PIKE COUNTY

Contract Time: 30 Working Days

for constructing the Resurfacing and Traffic Stripe on CR-5516 from the junction of SR-10 (US-231) to the junction of CR-5513 in Troy. Length 2.211 mi.

The Bracket Estimate on this project is from $336,973 to $411,856 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


87.STPAA-NR13(948) ,CALHOUN, CLAY, CLEBURNE, RANDOLPH, AND TALLADEGA COUNTIES

Contract Time: 120 Working Days

for constructing the Curb Ramp Installations and Modifications on various State Routes at various locations as indicated by the plans.

The Bracket Estimate on this project is from $365,361 to $446,552 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $6.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


90.STPBH-STPAA-0119(507) & STPAA-HSIP-0155(503) ,SHELBY COUNTY

Contract Time: 200 Working Days

DBE Goal Percent: 9.00

for constructing the Roadway Improvements (Resurfacing, Signals, Sidewalks, Landscaping, Lighting, and Drainage)on SR-119 (Main Street) from Shoal Creek to the intersection of Bloch Street (Site 1) and the Safety Widening, Planing, Resurfacing, and Traffic Stripe on SR-155 from the intersection of SR-119 to 780 feet north of the junction of SR-25 (Site 2) in Montevallo. Length 0.805 mi.

The Bracket Estimate on this project is from $3,003,109 to $3,670,467 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $60.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


91.ACAA59425-ATRP(005) ,JEFFERSON COUNTY

Contract Time: 75 Working Days

DBE Goal Percent: 5.00

for constructing the Intersection Improvements (Grade, Drain, Base, Pave, and Traffic Stripe) on CR-2 (South Shades Crest Road) at the junction of Eden Ridge Drive and Shades Run Circle. Length 0.163 mi.

The Bracket Estimate on this project is from $821,498 to $1,004,053 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $13.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


95.STPOA-0042(529) ,BALDWIN COUNTY

Contract Time: 250 Working Days

for constructing the Adaptive Signal Installations along SR-42 (US-98) at various locations as indicated in the plans.

The Bracket Estimate on this project is from $2,269,431 to $2,773,749 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $18.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


96.RECA-0021(555) ,ESCAMBIA COUNTY

Contract Time: 30 Working Days

DBE Goal Percent: 1.00

for constructing the Resurfacing and Traffic Stripe on SR-21 from the Florida State Line to the pavement joint at MP 0.968 in Atmore. Length 0.968 mi.

The Bracket Estimate on this project is from $349,579 to $427,263 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $8.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


97.STPOA-0215(250) ,BALDWIN COUNTY

Contract Time: 40 Working Days

DBE Goal Percent: 3.00

for constructing the Resurfacing and Traffic Stripe on Scenic Route 98 from the junction of CR-1 to the junction of Nelson Drive in Fairhope. Length 6.581 mi.

The Bracket Estimate on this project is from $861,388 to $1,052,808 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $6.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


98.STPOA-2314(252) ,DALE COUNTY

Contract Time: 30 Working Days

for constructing the Resurfacing and Traffic Stripe on CR-87 from the junction of CR-112 in Grimes to the junction of SR-134. Length 1.576 mi.

The Bracket Estimate on this project is from $256,139 to $313,058 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $4.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


99.STPOA-3516(252) & STPOA-3516(253) ,HOUSTON COUNTY

Contract Time: 45 Working Days

DBE Goal Percent: 8.00

for constructing the Resurfacing and Traffic Stripe on Eddins Road from the intersection of Hodgesville Road to the intersection of SR-53 south of Dothan and on CR-93 (Malvern Road) from the Geneva County Line to the junction of CR-203 in Rehobeth. Length 4.785 mi.

The Bracket Estimate on this project is from $540,784 to $660,958 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $6.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


106.99-607-234-027-601 ,DALE COUNTY

Contract Time: 45 Working Days

for constructing the Relocation of Guardrail and End Anchors on SR-27 from the Coffee County Line to the junction of SR-53 (US-231) in Ozark. Length 7.631 mi.

The Bracket Estimate on this project is from $231,681 to $283,165 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $9.00 per set.

View Items