1. ACAA60987-ATRP(010), JEFFERSON 4. ACBR58447-ATRP(002), TALLADEGA
7. ACBRZ59359-ATRP(005), CHILTON 8. ACBRZ59414-ATRP(010), CALHOUN
10. ACBRZ60915-ATRP(007), LAMAR **11. ACBRZ61377-ATRP(016), ETOWAH
12. ACBRZ62005-ATRP(016), GREENE 15. ACNU60466-ATRP(008), BULLOCK
19. ACOA61075-ATRP(016), PIKE 24. ERPR-9010(138), CONECUH
27. IM-I020(352), TALLADEGA 28. IM-I022(304), WALKER
29. IM-I059(401), SUMTER 30. IM-I065(466), MOBILE
33. IM-NH-I010(339), BALDWIN 36. NH-0006(568), TUSCALOOSA
37. NH-0021(558), CALHOUN *40. NH-HSIP-0001(596), BARBOUR
43. RP-IM-I065(473), BLOUNT 46. STPAA-0027(513), GENEVA
47. STPAA-0092(501), DALE 49. NH-0269(509), ETC., JEFFERSON
51. STPAA-HSIP-0015(527), LEE 52. STPAA-HSIP-0002(576), MADISON
53. STPAA-HSIP-0014(539), HALE 54. STPAA-HSIP-0015(529), CHAMBERS
55. STPAA-HSIP-0124(501), WALKER *56. STPAA-HSIP-0189(503), CRENSHAW
59. STPBH-3714(250), JEFFERSON 62. STPNU-0815(259), CALHOUN
63. STPNU-2417(250), DALLAS 64. STPNU-2916(251), FAYETTE
65. STPNU-4014(252), ETC., LAWRENCE 66. STPNU-4216(251), LIMESTONE
69. STPOA-2314(250), DALE 72. STPPC-4116(251), LEE
75. BP-049-042-011, MOBILE 200. BRZ-6314(252), TUSCALOOSA
  * - WITHDRAWN FROM THE LETTING
**_ALL BIDS REJECTED

The Bracket Ranges shown herein are to provide general financial information to Contractors and Bonding Companies concerning a Project's complexity and size. THESE BRACKETS SHOULD NOT BE USED IN PREPARING A BID, NOR WILL THESE BRACKETS HAVE ANY BEARING ON THE DECISION TO AWARD ANY CONTRACT.


1.ACAA60987-ATRP(010) ,JEFFERSON COUNTY

Contract Time: 95 Working Days

DBE Goal Percent:6.00

for constructing the Planing, Resurfacing, and Traffic Stripe on 4th Avenue Southwest from the junction of McAdory School Road to the intersection of 18th Street North and on Dartmouth Avenue from the intersection of SR-150 (14th Street North) to the junction of 36th Street South in Bessemer. Length 6.218 mi.

The Bracket Estimate on this project is from $1,654,234 to $2,021,842 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $18.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


4.ACBR58447-ATRP(002) ,TALLADEGA COUNTY

Contract Time: 250 Working Days

DBE Goal Percent:5.00

for constructing the Bridge Replacement and Approaches on CR-207 (Stemley Road) over Choccolocco Creek in Lincoln. Length 0.241 mi.

The Bracket Estimate on this project is from $4,916,848 to $6,009,480 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $22.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


7.ACBRZ59359-ATRP(005) ,CHILTON COUNTY

Contract Time: 45 Working Days

DBE Goal Percent:3.00

for constructing the Bridge Replacement (Precast) on CR-2 over Mahan Creek. Length 0.022 mi.

The Bracket Estimate on this project is from $456,713 to $558,205 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $6.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


8.ACBRZ59414-ATRP(010) ,CALHOUN COUNTY

Contract Time: 130 Working Days

DBE Goal Percent:6.00

for constructing the Bridge Replacement (Grade, Drain, Base, and Pave) on CR-567 (Verbon George Road) over Ohatchee Creek southeast of Glencoe. Length 0.212 mi.

The Bracket Estimate on this project is from $1,129,467 to $1,380,459 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $16.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


10.ACBRZ60915-ATRP(007) ,LAMAR COUNTY

Contract Time: 45 Working Days

DBE Goal Percent:5.00

for constructing the Bridge Replacement and Approaches on CR-412 (Sunset Road) over Little Hell's Creek. Length 0.105 mi.

The Bracket Estimate on this project is from $288,961 to $353,174 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $7.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


11.ACBRZ61377-ATRP(016) ,ETOWAH COUNTY

Contract Time: 45 Working Days

DBE Goal Percent:4.00

for constructing the Bridge Replacement (Precast) on Coats Bend Circle over an Unnamed Tributary to the Coosa River north of Hokes Bluff. Length 0.007 mi.

The Bracket Estimate on this project is from $213,810 to $261,323 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $6.00 per set.

***ALL BIDS REJECTED***

Return To: Proposal Letting List (Top of web page)


12.ACBRZ62005-ATRP(016) ,GREENE COUNTY

Contract Time: 60 Working Days

DBE Goal Percent:2.00

for constructing the Bridge Replacement (Precast) on CR-148 over Taylor Creek east of Boligee. Length 0.080 mi.

The Bracket Estimate on this project is from $613,699 to $750,077 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $11.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


15.ACNU60466-ATRP(008) ,BULLOCK COUNTY

Contract Time: 45 Working Days

DBE Goal Percent:3.00

for constructing the Widening, Resurfacing, and Traffic Stripe on CR-8 from the junction of SR-223 to the intersection of SR-15 (US-29) in Perote. Length 6.347 mi.

The Bracket Estimate on this project is from $1,576,891 to $1,927,311 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


19.ACOA61075-ATRP(016) ,PIKE COUNTY

Contract Time: 165 Working Days

DBE Goal Percent:7.00

for constructing the Realignment (Grade, Drain, Base, Pave, and Signals) on McKinley Drive from the junction of College Drive to the junction of George Wallace Drive in Troy. Length 0.614 mi.

The Bracket Estimate on this project is from $2,395,861 to $2,928,275 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $25.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


24.ERPR-9010(138) ,CONECUH COUNTY

Contract Time: 30 Working Days

DBE Goal Percent:10.00

for constructing the Slope Repair (Front Slope Failure) on I-65 at MP 77.600 (Northbound Lane) southeast of Range. Length 0.189 mi.

The Bracket Estimate on this project is from $106,473 to $130,134 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $6.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


27.IM-I020(352) ,TALLADEGA COUNTY

Contract Time: 60 Working Days

DBE Goal Percent:4.00

for constructing the Planing, Resurfacing, and Traffic Stripe on I-20 from east of the CR-97 Overpass (Airport Road) at MP 173.218 in Lincoln to west of the H. J. Bentley Jr. Parkway Overpass at MP 181.747 near Oxford. Length 8.529 mi.

The Bracket Estimate on this project is from $4,172,999 to $5,100,332 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $5.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


28.IM-I022(304) ,WALKER COUNTY

Contract Time: 120 Working Days

DBE Goal Percent:3.00

for constructing the Planing, Resurfacing, and Traffic Stripe on I-22 from MP 65.273 (Exit 65) to the Jefferson County Line. Length 15.086 mi.

The Bracket Estimate on this project is from $8,920,448 to $10,902,770 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $10.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


29.IM-I059(401) ,SUMTER COUNTY

Contract Time: 50 Working Days

DBE Goal Percent:3.00

for constructing the Planing, Resurfacing, and Traffic Stripe on I-59 from south of the McCainville Road Overpass southwest of Epps to the Tombigbee River Bridge. Length 7.698 mi.

The Bracket Estimate on this project is from $3,023,746 to $3,695,689 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $8.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


30.IM-I065(466) ,MOBILE COUNTY

Contract Time: 175 Working Days

DBE Goal Percent:6.00

for constructing the Planing, Resurfacing, and Traffic Stripe on I-65 from the Main Street Overpass in Prichard to just north of the SR-158 Interchange in Saraland. Length 4.580 mi.

The Bracket Estimate on this project is from $6,734,934 to $8,231,586 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $33.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


33.IM-NH-I010(339) ,BALDWIN COUNTY

Contract Time: 65 Working Days

DBE Goal Percent:3.00

for constructing the Planing, Resurfacing, and Traffic Stripe on I-10 from east of the CR-64 (Wilcox Road) Interchange to the Florida State Line. Length 12.374 mi.

The Bracket Estimate on this project is from $3,631,652 to $4,438,685 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $8.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


36.NH-0006(568) ,TUSCALOOSA COUNTY

Contract Time: 35 Working Days

DBE Goal Percent:3.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-6 (US-82) from just east of the Woolsey Finnel Bridge to just east of the Campus Drive Overpass in Tuscaloosa. Length 0.819 mi.

The Bracket Estimate on this project is from $667,069 to $815,307 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $7.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


37.NH-0021(558) ,CALHOUN COUNTY

Contract Time: 65 Working Days

DBE Goal Percent:3.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-21 from 0.100 mile north of the intersection of George Douthit Drive Southwest to 0.250 mile north of the junction of Pine Island Road in Jacksonville. Length 4.477 mi.

The Bracket Estimate on this project is from $1,481,690 to $1,810,954 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $4.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


40.NH-HSIP-0001(596) ,BARBOUR COUNTY

Contract Time: 70 Working Days

DBE Goal Percent:5.00

for constructing the Safety Widening, Resurfacing, and Traffic Stripe on SR-1 (US-431) from 0.250 mile south of the junction of Lindsey Drive to the Russell County Line. Length 7.646 mi.

The Bracket Estimate on this project is from $2,878,213 to $3,517,816 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $11.00 per set.

****WITHDRAWN FROM THE LETTING****

Return To: Proposal Letting List (Top of web page)


43.RP-IM-I065(473) ,BLOUNT COUNTY

Contract Time: 50 Working Days

DBE Goal Percent:3.00

for constructing the Resurfacing and Traffic Stripe on I-65 from 1.000 mile north of the Jefferson County Line to the Cullman County Line. Length 5.955 mi.

The Bracket Estimate on this project is from $2,818,674 to $3,445,045 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $6.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


46.STPAA-0027(513) ,GENEVA COUNTY

Contract Time: 65 Working Days

DBE Goal Percent:6.00

for constructing the Resurfacing and Traffic Stripe on SR-27 from the junction of CR-8 (Goose Hollow Road) to the Coffee County Line. Length 9.331 mi.

The Bracket Estimate on this project is from $2,870,596 to $3,508,506 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $12.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


47.STPAA-0092(501) ,DALE COUNTY

Contract Time: 30 Working Days

DBE Goal Percent:3.00

for constructing the Resurfacing and Traffic Stripe on SR-85/SR-92 from the east end of the bridge over Claybank Creek to the west end of the bridge over Choctawhatchee Creek in Clayhatchee. Length 2.885 mi.

The Bracket Estimate on this project is from $660,328 to $807,067 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $8.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


49.NH-0269(509) & STPAA-0269(510) ,JEFFERSON COUNTY

Contract Time: 90 Working Days

DBE Goal Percent:4.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-269 from the junction of Pike Road/Avenue V to the Birmingham City Limits and from south of the junction of Little River Trail (MP 15.000) to the Walker County Line. Length 7.623 mi.

The Bracket Estimate on this project is from $3,187,680 to $3,896,054 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $8.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


51.STPAA-HSIP-0015(527) ,LEE COUNTY

Contract Time: 60 Working Days

DBE Goal Percent:6.00

for constructing the Safety Widening, Planing, Resurfacing, Bridge Guardrail Retrofit, and Traffic Stripe on SR-15 (US-29) from west of the I-85 Interchange (MP 192.670) in Opelika to the Chambers County Line. Length 8.629 mi.

The Bracket Estimate on this project is from $2,259,068 to $2,761,083 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


52.STPAA-HSIP-0002(576) ,MADISON COUNTY

Contract Time: 30 Working Days

DBE Goal Percent:3.00

for constructing the Safety Widening, Planing, Resurfacing, and Traffic Stripe on SR-2 (US-72) from the intersection of North Memorial Parkway to just west of the I-565 Interchange in Huntsville. Length 1.249 mi.

The Bracket Estimate on this project is from $593,136 to $724,944 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $7.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


53.STPAA-HSIP-0014(539) ,HALE COUNTY

Contract Time: 50 Working Days

DBE Goal Percent:3.00

for constructing the Safety Widening, Planing, Resurfacing, and Traffic Stripe on SR-14 from the East City Limits of Greensboro to the Perry County Line. Length 6.504 mi.

The Bracket Estimate on this project is from $2,671,823 to $3,265,562 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $7.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


54.STPAA-HSIP-0015(529) ,CHAMBERS COUNTY

Contract Time: 30 Working Days

DBE Goal Percent:4.00

for constructing the Safety Widening, Resurfacing, and Traffic Stripe on SR-15 (US-29) from the Lee County Line to just south of the junction of Judge Brown Road (MP 204.558). Length 3.312 mi.

The Bracket Estimate on this project is from $728,081 to $889,877 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


55.STPAA-HSIP-0124(501) ,WALKER COUNTY

Contract Time: 30 Working Days

DBE Goal Percent:3.00

for constructing the Safety Widening, Resurfacing, and Traffic Stripe on SR-124 from the junction of SR-118 to the junction of SR-69 east of Jasper. Length 10.896 mi.

The Bracket Estimate on this project is from $951,870 to $1,163,397 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $6.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


56.STPAA-HSIP-0189(503) ,CRENSHAW COUNTY

Contract Time: 30 Working Days

DBE Goal Percent:5.00

for constructing the Safety Widening, Planing, Resurfacing, and Traffic Stripe on SR-189 from the Coffee County Line to the junction of SR-9 (US-331) southeast of Brantley. Length 4.341 mi.

The Bracket Estimate on this project is from $1,194,021 to $1,459,359 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $12.00 per set.

****WITHDRAWN FROM THE LETTING****

Return To: Proposal Letting List (Top of web page)


59.STPBH-3714(250) ,JEFFERSON COUNTY

Contract Time: 130 Working Days

DBE Goal Percent:10.00

for constructing the Sidewalk Installation (Drainage, Sidewalks, Lighting, and Landscaping) along 12th Street West from the junction of Lomb Avenue to the junction of 3rd Avenue West and along 2nd Avenue West from the junction of 12th Street West to the junction of 11th Street West in Birmingham. Length 0.336 mi.

The Bracket Estimate on this project is from $959,025 to $1,172,142 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $22.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


62.STPNU-0815(259) ,CALHOUN COUNTY

Contract Time: 30 Working Days

DBE Goal Percent:3.00

for constructing the Resurfacing and Traffic Stripe on CR-55 (Rabbittown Road) from a point near the junction of Red Road 55 to the Cleburne County Line. Length 5.978 mi.

The Bracket Estimate on this project is from $696,956 to $851,835 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


63.STPNU-2417(250) ,DALLAS COUNTY

Contract Time: 30 Working Days

DBE Goal Percent:3.00

for constructing the Resurfacing and Traffic Stripe on CR-43 from 0.400 mile south of the junction of CR-420 to the junction of SR-8 (US-80). Length 1.862 mi.

The Bracket Estimate on this project is from $347,297 to $424,474 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


64.STPNU-2916(251) ,FAYETTE COUNTY

Contract Time: 30 Working Days

DBE Goal Percent:10.00

for constructing the Resurfacing, Guardrail, and Traffic Stripe on CR-35 from the junction of Oak Grove Road to the South City Limits of Fayette. Length 3.257 mi.

The Bracket Estimate on this project is from $674,057 to $823,847 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $7.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


65.STPNU-4014(252) & STPNU-4014(251) ,LAWRENCE COUNTY

Contract Time: 30 Working Days

DBE Goal Percent:10.00

for constructing the Resurfacing and Traffic Stripe on CR-21, CR-20, CR-17, and CR-28 from the junction of CR-23 to the junction of CR-460 and on CR-214 from the junction of SR-33 to the junction of CR-217 east of Langtown. Length 9.518 mi.

The Bracket Estimate on this project is from $690,404 to $843,827 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $2.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


66.STPNU-4216(251) ,LIMESTONE COUNTY

Contract Time: 30 Working Days

DBE Goal Percent:6.00

for constructing the Resurfacing (Triple Layer Bituminous Surface Treatment) and Traffic Stripe on Parker Road from the junction of SR-2 (US-72) to the junction of New Cut Road (Site 1); on Baker Hill Road from the junction of New Cut Road to the junction of Elk River Mills Road (Site 2); and on Elk River Mills Road from the junction of Baker Hill Road to the Elk River Bridge (Site 3) west of Athens. Length 4.301 mi.

The Bracket Estimate on this project is from $484,006 to $591,563 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


69.STPOA-2314(250) ,DALE COUNTY

Contract Time: 30 Working Days

DBE Goal Percent:8.00

for constructing the Resurfacing and Traffic Stripe on CR-10 from the intersection of SR-53 (US-231) in Grimes to the Houston County Line. Length 3.493 mi.

The Bracket Estimate on this project is from $546,517 to $667,965 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


72.STPPC-4116(251) ,LEE COUNTY

Contract Time: 30 Working Days

for constructing the Full Depth Reclamation, Resurfacing, and Traffic Stripe on CR-248 from the intersection of CR-243 in Smiths Station to the junction of SR-38 (US-280). Length 0.634 mi.

The Bracket Estimate on this project is from $247,264 to $302,212 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $4.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


75.BP-049-042-011 ,MOBILE COUNTY

Contract Time: 240 Working Days

for constructing the Bridge Extension on SR-42 (US-98) Eastbound Lane over Big Creek east of Wilmer. Length 0.325 mi.

The Bracket Estimate on this project is from $5,200,812 to $6,356,548 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $15.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


200.BRZ-6314(252) ,TUSCALOOSA COUNTY

Contract Time: 75 Working Days

for constructing the Bridge Replacement on Hosmer Road over Rockcastle Creek northwest of Lakeview. Length 0.009 mi.

The Bracket Estimate on this project is from $294,908 to $360,443 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $7.00 per set.

THIS PROJECT HAS BEEN DESIGNATED AS AN SBE PROJECT, AND CAN ONLY BE BID ON BY QUALIFIED SBE CONTRACTORS THAT HAVE BEEN PRE-APPROVED BY THE ALDOT DBE UNIT AND ALDOT OFFICE ENGINEER.

View Items