Office Engineer

036 . STPNU-2123(200) , CRENSHAW

COUNTY: CRENSHAW
WORKING DAYS: 30

for constructing the Resurfacing and Traffic Stripe on CR-57 from CR-6 west of Glenwood to SR-10 (US-29). Length 4.085 mi.

The Bracket Ranges shown herein are to provide general financial information to Contractors and Bonding Companies concerning a Project's complexity and size only. THESE BRACKETS SHOULD NOT BE USED IN PREPARING A BID, NOR WILL THESE BRACKETS HAVE ANY BEARING ON THE DECISION TO AWARD ANY CONTRACT.

BRACKET ESTIMATE: $402,000 TO $491,000


THE PRINCIPAL ITEMS OF WORK ARE APPROXIMATELY AS FOLLOWS:

ITEM CODE QUANTITY UNIT ITEM DESCRIPTION
210D001 500 CUYD Borrow Excavation (Loose Truckbed Meas)
212A000 432 STA Machine Grading Shoulders
401B100 47950 SQYD Bituminous Treatment E (W/Polymer)
405A000 2900 GAL Tack Coat
429A201 4050 TON Imp Bit Wrg Surf 3/4" ESAL A
429A206 1175 TON Imp Bit Wrg Surf Level 1/2" ESAL A
429B206 50 TON Imp Bit Bndr Patch 1 1/2" ESAL A
600A000 1 LS Mobilization
652A100 6 ACRE Seeding
656A010 6 ACRE Mulching
701A231 9 MILE Solid White Cl 2 Ty A Traf Str
701A235 5 MILE Solid Yellow Cl 2 Ty A Traf Str
701A245 4 MILE Broken Yellow Cl 2 Ty A Traf Str
701C000 11 MILE Broken Temporary Traffic Stripe
701C001 14 MILE Solid Temporary Traffic Stripe
703A002 40 SQFT Traffic Control Marking, Class 2, Type A
703D001 40 SQFT Temporary Traffic Control Markings
740B000 303 SQFT Construction Signs
740E000 25 EACH Cones (36" High)
740M001 25 EACH Ballast For Cone
740O000 1 EACH Pilot Car
998A000 1 LS Construction Fuel (Max. Bid Limited to $ 21,000.00)