Office Engineer

039 . STPNU-5415(200) , PICKENS

COUNTY: PICKENS
WORKING DAYS: 30

for constructing the Resurfacing and Traffic Stripe on CR-59 from SR-17 north of Palmetto to the Fayette county line. Length 4.986 mi.

The Bracket Ranges shown herein are to provide general financial information to Contractors and Bonding Companies concerning a Project's complexity and size only. THESE BRACKETS SHOULD NOT BE USED IN PREPARING A BID, NOR WILL THESE BRACKETS HAVE ANY BEARING ON THE DECISION TO AWARD ANY CONTRACT.

BRACKET ESTIMATE: $502,000 TO $614,000


THE PRINCIPAL ITEMS OF WORK ARE APPROXIMATELY AS FOLLOWS:

ITEM CODE QUANTITY UNIT ITEM DESCRIPTION
210D021 2600 CUYD Borrow Excav (Lse Trb Meas)(A-4 Better)
405A000 1756 GAL Tack Coat
424A340 3957 TON Superpave Wrg Surf 1/2" ESAL A/B
424A343 500 TON Superpave Wrg Surf Patch 1/2" ESAL A/B
424A346 2926 TON Superpave Wrg Surf Level 1/2" ESAL A/B
600A000 1 LS Mobilization
652A100 5 ACRE Seeding
656A010 5 ACRE Mulching
701A004 10 MILE Solid White Class 1 Type A Traf Stripe
701A008 3 MILE Broken Yellow Cl 1 Ty A Traf Stripe
701A012 7 MILE Solid Yellow Class 1 Type A Traffic St
701C000 3 MILE Broken Temporary Traffic Stripe
701C001 7 MILE Solid Temporary Traffic Stripe
703A000 20 SQFT Traffic Control Marking, Class 1, Type A
740B000 245 SQFT Construction Signs
740E000 50 EACH Cones (36" High)
740M001 50 EACH Ballast For Cone
740O000 1 EACH Pilot Car
998A000 1 LS Construction Fuel (Max. Bid Limited to $ 26,000.00)