030 . STPOA-0318(200), BARBOUR 030 . STPOA-0318(200) , BARBOUR

COUNTY: BARBOUR

WORKING DAYS: 45

MBE/DBE CONTRACT OBLIGATION: 3 %
for constructing the Resurfacing and Traffic Stripe on CR-79 from SR-30 at Martin Pond to SR-6 (US-82) at Batesville. Length 11.244 mi.

The Bracket Ranges shown herein are to provide general financial information to Contractors and Bonding Companies concerning a Project's complexity and size only. THESE BRACKETS SHOULD NOT BE USED IN PREPARING A BID, NOR WILL THESE BRACKETS HAVE ANY BEARING ON THE DECISION TO AWARD ANY CONTRACT.

BRACKET ESTIMATE: $1,399,000 TO $1,700,000


THE PRINCIPAL ITEMS OF WORK ARE APPROXIMATELY AS FOLLOWS:

ITEM CODE QUANTITY UNIT ITEM DESCRIPTION
405A000 12155 GAL Tack Coat
410H000 1 EACH Material Remixing Device
429A216 5602 TON Imp Bit Wrg Surf 3/8" ESAL B
429A226 4727 TON Imp Bit Wrg Surf Level 1/2" ESAL B
429B220 11142 TON Imp Bit Binder 3/4" ESAL B
600A000 1 LS Mobilization
701A231 23 MILE Solid White Cl 2 Ty A Traf Str
701A235 16 MILE Solid Yellow Cl 2 Ty A Traf Str
701A245 8 MILE Broken Yellow Cl 2 Ty A Traf Str
701C000 16 MILE Broken Temporary Traffic Stripe
701C001 32 MILE Solid Temporary Traffic Stripe
703A002 372 SQFT Traffic Control Marking, Class 2, Type A
703B002 137 SQFT Traffic Control Legends, Class 2, Type A
703D002 120 SQFT Temporary Traffic Control Markings Paint
705A032 360 EACH Pavement Markers, Class A-H, Type 1-B
705A037 1056 EACH Pavement Markers, Class A-H, Type 2-D
740B000 300 SQFT Construction Signs
740O000 1 EACH Pilot Car
998A000 1 LS Construction Fuel (Max. Bid Limited to $ 74,000.00)