039 . 99-302-473-019-701, MARION 039 . 99-302-473-019-701 , MARION

COUNTY: MARION

WORKING DAYS: 30

for constructing the Resurfacing and Traffic Stripe on SR-19 from the Lamar county line to SR-74 on the SR-19 spur in Hamilton. Length 11.426 mi.

The Bracket Ranges shown herein are to provide general financial information to Contractors and Bonding Companies concerning a Project's complexity and size only. THESE BRACKETS SHOULD NOT BE USED IN PREPARING A BID, NOR WILL THESE BRACKETS HAVE ANY BEARING ON THE DECISION TO AWARD ANY CONTRACT.

BRACKET ESTIMATE: $927,000 TO $1,133,000


THE PRINCIPAL ITEMS OF WORK ARE APPROXIMATELY AS FOLLOWS:

ITEM CODE QUANTITY UNIT ITEM DESCRIPTION
405A000 6253 GAL Tack Coat
408A052 3178 SQYD Plane Pvmt Appr 1.10" - 2.0"
424A340 12956 TON Superpave Wrg Surf 1/2" ESAL A/B
424A349 100 TON Superpave Wrg Surf Widen 1/2" ESAL A/B
424B638 1000 TON Superpave Upr Bndr Patch 1/2" Esal A/B
600A000 1 LS Mobilization
701A228 27 MILE Solid White Cl 2 Ty A Traf Str 6" W
701A232 19 MILE Soild Yellow Cl 2 Ty A Traf Str 6" W
701A246 7 MILE Broken Yellow Cl 2 Ty A Traf Str 6" W
701C000 7 MILE Broken Temporary Traffic Stripe
701C001 45 MILE Solid Temporary Traffic Stripe
701G145 2062 LF Solid White Cl W Ty A Traf Str 6" Wide
701G149 296 LF Broken Yellow Cl W Ty A Traf Str 6" W
701G153 1470 LF Solid Yellow Cl W Ty A Traf Str 6" W
701H000 3532 LF Solid Traffic Stripe Removed Paint
701H005 296 LF Broken Traffic Stripe Removed Paint
705A032 422 EACH Pavement Markers, Class A-H, Type 1-B
705A037 1015 EACH Pavement Markers, Class A-H, Type 2-D
740B000 681 SQFT Construction Signs
740E000 200 EACH Cones (36" High)
740M001 200 EACH Ballast For Cone
740O000 1 EACH Pilot Car
998A000 1 LS Construction Fuel (Max. Bid Limited to $ 49,500.00)