Alabama Department of Transportation
Proposal Letting List
June 27, 2008 Transportation Letting

Welcome to the Proposal Letting List Page. You may view the approximate items of work for each proposal in the Letting by clicking on the View Items hyperlink to view the Project Item Pages. Please take a minute to review these pages and e-mail the Web Page Editor with your comments.


If you would like to order Plans, Proposals, Diskettes, Specification Standard Drawings, please use the ALDOT Order Form ; . THANKS !!!


The Bracket Ranges shown herein are to provide general financial information to Contractors and Bonding Companies concerning a Project's complexity and size only. THESE BRACKETS SHOULD NOT BE USED IN PREPARING A BID, NOR WILL THESE BRACKETS HAVE ANY BEARING ON THE DECISION TO AWARD ANY CONTRACT.


001 . IM-I065(382) , LIMESTONE 002 . STPAAF-0006(531) , MONTGOMERY
010 . BRF-0013(517) , WASHINGTON 017 . HRRR-6400(211) , WALKER
020 . HSIP-0205(504) , MARSHALL 021 . HSIP-0021(520) , TALLADEGA
025 . STPAA-0008(532) , MONTGOMERY 026 . STPAA-0193(503) , MOBILE
027 . STPAA-0229(504) , ELMORE 029 . STPAA-HSIP-0003(540) , MORGAN
030 . STPAA-HSIP-0003(541) , AUTAUGA 032 . STPOA-0823(201) , CALHOUN
034 . STPOA-9059(600) , LEE 037 . STPOA-CN08(263) , LAWRENCE
038 . STPOA-2015(200) , COVINGTON 044 . 99-302-673-005-805 , WINSTON, etc.
046 . 99-506-245-005-802 , DALLAS

001 . IM-I065(382) LIMESTONE COUNTY

LENGTH: 0.36 MILES.

SHALL BE COMPLETED BY: October 15, 2008
COST OF PLANS: $10.00

for constructing the Safety Improvements (Resurfacing, Traffic Stripe and Guardrail) on I-65 at approximately MP 365.655 north of Athens. Length 0.341 mi.

BRACKET ESTIMATE: $720,000 TO $880,000

VIEW ITEMS


002 . STPAAF-0006(531) & STPAA-HSIP-0006(532) MONTGOMERY COUNTY

LENGTH: 2.40 MILES.

WORKING DAYS: 110
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 7.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-6 (US-82) (South Boulevard) from east of Davenport Drive to SR-53 (US-231) (Troy Highway) in Montgomery and on SR-6 (US-231) (Troy Highway) from just south of SR-271 (Taylor Road) in Montgomery to the Little Catoma Creek bridge. Length 7.138 mi.

BRACKET ESTIMATE: $4,200,000 TO $5,000,000

VIEW ITEMS


010 . BRF-0013(517) WASHINGTON COUNTY

LENGTH: 0.91 MILES.

SHALL BE COMPLETED BY: September 1, 2009
DBE CONTRACT OBLIGATION: 5 % COST OF PLANS: $31.00

for constructing the Bridge Replacement and Approaches on SR-13 (US-43) Northbound at Lewis Creek south of Sunflower. Length 0.710 mi.

BRACKET ESTIMATE: $3,500,000 TO $4,250,000

VIEW ITEMS


017 . HRRR-6400(211) WALKER COUNTY

LENGTH: 0.20 MILES.

WORKING DAYS: 30
COST OF PLANS: $ 2.00

for constructing the Resurfacing, Traffic Stripe and Guardrail on Boldo Cut-off Road at Poley Creek north of Cordova. Length 0.200 mi.

BRACKET ESTIMATE: $43,500 TO $53,100

VIEW ITEMS


020 . HSIP-0205(504) & 99-301-484-205-805 MARSHALL COUNTY

LENGTH: 6.38 MILES.

WORKING DAYS: 45
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 7.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-205 from the Etowah county line to Guinivere Drive in Boaz. Length 4.390 mi.

BRACKET ESTIMATE: $1,300,000 TO $1,600,000

VIEW ITEMS


021 . HSIP-0021(520) & 99-304-615-021-801 TALLADEGA COUNTY
WORKING DAYS: 60
COST OF PLANS: $ 3.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-21 (US-231) from the Coosa county line to CR-511 south of Sylacauga. Length 3.687 mi.

BRACKET ESTIMATE: $1,400,000 TO $1,700,000

VIEW ITEMS


025 . STPAA-0008(532) & BR-7771(600) MONTGOMERY COUNTY

LENGTH: 1.02 MILES.

WORKING DAYS: 150
DBE CONTRACT OBLIGATION: 2 % COST OF PLANS: $23.00

for constructing the Bridge Replacement (Precast) and Approaches (EBR) on SR-8 (US-80) at Oliver Creek in Montgomery. Length 0.506 mi.

BRACKET ESTIMATE: $2,155,000 TO $2,630,000

VIEW ITEMS


026 . STPAA-0193(503) MOBILE COUNTY

LENGTH: 7.44 MILES.

WORKING DAYS: 75
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 4.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-193 from Laurendine Road (MP 18.417) at Belle Fontaine to north of I-10 (MP 25.873). Length 7.361 mi.

BRACKET ESTIMATE: $2,835,000 TO $3,460,000

VIEW ITEMS


027 . STPAA-0229(504) ELMORE COUNTY

LENGTH: 4.01 MILES.

WORKING DAYS: 35
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 3.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-229 from near CR-143 to SR-14 in Tallassee. Length 4.007 mi.

BRACKET ESTIMATE: $950,000 TO $1,160,000

VIEW ITEMS


029 . STPAA-HSIP-0003(540) MORGAN COUNTY

LENGTH: 1.83 MILES.

WORKING DAYS: 35
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 5.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-3 (US-31) from north of Atkinson Drive at Flint City to SR-67. Length 1.830 mi.

BRACKET ESTIMATE: $895,000 TO $1,090,000

VIEW ITEMS


030 . STPAA-HSIP-0003(541) AUTAUGA COUNTY

LENGTH: 11.47 MILES.

WORKING DAYS: 105
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 4.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-3 (US-31) from I-65 to the Chilton county line. Length 11.120 mi.

BRACKET ESTIMATE: $3,000,000 TO $3,700,000

VIEW ITEMS


032 . STPOA-0823(201) CALHOUN COUNTY

LENGTH: 2.84 MILES.

WORKING DAYS: 45
COST OF PLANS: $ 3.00

for constructing the Resurfacing and Traffic Stripe on Nesbit Lake Road from SR-204 in Jacksonville to Hulsey Road. Length 2.840 mi.

BRACKET ESTIMATE: $600,000 TO $733,000

VIEW ITEMS


034 . STPOA-9059(600) LEE COUNTY
WORKING DAYS: 110
DBE CONTRACT OBLIGATION: 5 % COST OF PLANS: $20.00

for constructing the Additional Lanes on Donahue Drive from west of Glenn Avenue to 50m north of Bragg Avenue and Relocation of SR-14 in Auburn. Length 0.320 km.

BRACKET ESTIMATE: $970,000 TO $1,180,000

VIEW ITEMS


037 . STPOA-CN08(263) LAWRENCE COUNTY
WORKING DAYS: 30
COST OF PLANS: $ 2.00

for constructing the Resurfacing and Traffic Stripe on CR-195, CR-196 and CR-4 from the Winston county line to the Morgan county line. Length 3.314 mi.

BRACKET ESTIMATE: $451,000 TO $551,000

VIEW ITEMS


038 . STPOA-2015(200) COVINGTON COUNTY

LENGTH: 4.48 MILES.

WORKING DAYS: 30
COST OF PLANS: $ 3.00

for constructing the Resurfacing and Traffic Stripe on CR-70 from SR-9 (US-331) to the Coffee county line northeast of Opp. Length 4.477 mi.

BRACKET ESTIMATE: $573,000 TO $700,000

VIEW ITEMS


044 . 99-302-673-005-805 WINSTON & WALKER COUNTIES
WORKING DAYS: 55
COST OF PLANS: $ 3.00

for constructing the Resurfacing and Traffic Stripe on SR-5 from just south of the Walker county line to SR-74 (US-278) at Natural Bridge. Length 10.301 mi.

BRACKET ESTIMATE: $2,130,000 TO $2,600,000

VIEW ITEMS


046 . 99-506-245-005-802 & 99-506-245-041-804 DALLAS COUNTY
WORKING DAYS: 45
COST OF PLANS: $ 2.00

for constructing the Bridge Scour Repair on SR-5 at Chilatchee Creek and on SR-41 at Mush Creek.

BRACKET ESTIMATE: $83,000 TO $102,000

VIEW ITEMS



Return To: Top of this Page

ALDOT Home Page