Office Engineer

Proposal Letting List
May 29, 2009 Transportation Letting

Welcome to the Proposal Letting List Page. You may view the approximate items of work for each proposal in the Letting by clicking on the View Items hyperlink to view the Project Item Pages. Please take a minute to review these pages and e-mail the Web Page Editor with your comments.


The Bracket Ranges shown herein are to provide general financial information to Contractors and Bonding Companies concerning a Project's complexity and size only. THESE BRACKETS SHOULD NOT BE USED IN PREPARING A BID, NOR WILL THESE BRACKETS HAVE ANY BEARING ON THE DECISION TO AWARD ANY CONTRACT.


003. STMAA-0003(550) , BUTLER 005. STMAA-0017(525) , CHOCTAW
006. STMAA-0049(502) , CLAY 007. STMAA-0053(543) , ST. CLAIR
008. STMAA-0069(521) , MARENGO, etc. 009. STMAA-0069(523) , CULLMAN
010. STMAA-0079(510) , JEFFERSON 011. STMAA-0115(503) , COOSA
012. STMAA-0148(500) , TALLADEGA 013. STMAA-0213(502) , MOBILE
014. STMAA-0241(501) , FRANKLIN, etc. 015. STMAA-CN09(208) , BALDWIN, etc.
016. STMAA-CN09(908) , ELMORE 017. STMNU-BRZ-3500(214) , HOUSTON
018. STMNU-STPNU-0928(200) , CHAMBERS 019. STMNU-STPNU-5505(202) , PIKE
020. STMAA-0015(517) , LEE 021. STMAA-STPAA-7615(600) , MOBILE
034. EB-0038(524) , SHELBY 038. HSIP-0006(539) , PICKENS
039. HSIP-0021(526) , COOSA 040. HSIP-0063(501) , TALLAPOOSA
042. STPOA-HSIP-0001(541) , ETOWAH 043. NH-0038(525) , SHELBY
044. NH-0074(522) , BLOUNT 048. STPAA-HSIP-0025(519) , CHEROKEE
050. STPBH-CN09(903) , JEFFERSON 053. STPNU-0323(201) , BARBOUR
054. STPNU-2537(200) , DEKALB 057. STPOA-0014(513) , ELMORE
060. 99-405-632-659-911 , TUSCALOOSA 061. 99-308-663-162-905 , WILCOX
064. 99-301-363-035-911 , JACKSON 067. 99-302-473-129-912 , MARION
069. 99-406-062-110-801 , MONTGOMERY, etc. 070. 99-507-690-000-901 , BARBOUR, etc.
071. 99-508-690-000-918 , CHOCTAW, etc.

003. STMAA-0003(550) & STMAA-0055(505) BUTLER COUNTY
LENGTH: 6.39 MILES. WORKING DAYS: 65
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 3.00

for constructing the Resurfacing and Traffic Stripe on SR-3 (US-31) and on SR-55 at various sites as indicated by the plans. Length 6.384 mi.

BRACKET ESTIMATE: $2,200,000 TO $2,700,000

VIEW ITEMS

Return To: Top of this Page


005. STMAA-0017(525) & STMAA-0017(526) CHOCTAW COUNTY
LENGTH: 8.60 MILES. WORKING DAYS: 60
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $12.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-17 from 1.3 miles south of CR-18 (MP 98.820) to MP 107.932 in Butler. Length 8.667 mi.

BRACKET ESTIMATE: $1,835,000 TO $2,245,000

VIEW ITEMS

Return To: Top of this Page


006. STMAA-0049(502) CLAY COUNTY
LENGTH: 7.33 MILES. WORKING DAYS: 50
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 2.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-49 from the Tallapoosa County line to SR-77 south of Lineville. Length 7.334 mi.

BRACKET ESTIMATE: $1,800,000 TO $2,100,000

VIEW ITEMS

Return To: Top of this Page


007. STMAA-0053(543) ST. CLAIR COUNTY
LENGTH: 7.51 MILES. WORKING DAYS: 45
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 4.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-53 (US-231) from north of I-20 (MP 220.700) to MP 228.210 north of Wattsville. Length 7.510 mi.

BRACKET ESTIMATE: $1,420,000 TO $1,700,000

VIEW ITEMS

Return To: Top of this Page


008. STMAA-0069(521) ,STMAA-0069(525) & STMAA-0069(529) MARENGO & HALE COUNTIES
LENGTH: 27.66 MILES. WORKING DAYS: 90
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $17.00

for constructing the Planing, Resurfacing, Culvert Extensions and Traffic Stripe on SR-69 from SR-13 (US-43) to SR-8 (US-80) west of Prairieville. Length 13.637 mi.

BRACKET ESTIMATE: $3,440,000 TO $4,200,000

VIEW ITEMS

Return To: Top of this Page


009. STMAA-0069(523) CULLMAN COUNTY
LENGTH: 3.71 MILES. WORKING DAYS: 45
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 7.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-69 from I-65 in Good Hope to SR-3 (US-31) in Cullman. Length 3.710 mi.

BRACKET ESTIMATE: $1,190,000 TO $1,450,000

VIEW ITEMS

Return To: Top of this Page


010. STMAA-0079(510) JEFFERSON COUNTY
LENGTH: 5.29 MILES. WORKING DAYS: 60
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 5.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-79 from Winewood Road northeast of Tarrant City to SR-151. Length 5.288 mi.

BRACKET ESTIMATE: $2,000,000 TO $2,500,000

VIEW ITEMS

Return To: Top of this Page


011. STMAA-0115(503) COOSA COUNTY
WORKING DAYS: 30
COST OF PLANS: $ 2.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-115 from SR-9 to SR-38 (US-280) south of Goodwater. Length 3.190 mi.

BRACKET ESTIMATE: $850,000 TO $1,000,000

VIEW ITEMS

Return To: Top of this Page


012. STMAA-0148(500) TALLADEGA COUNTY
LENGTH: 1.75 MILES. WORKING DAYS: 30
COST OF PLANS: $ 3.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-148 from SR-21 in Sylacauga to MP 1.780. Length 1.753 mi.

BRACKET ESTIMATE: $520,000 TO $635,000

VIEW ITEMS

Return To: Top of this Page


013. STMAA-0213(502) MOBILE COUNTY
LENGTH: 2.32 MILES. WORKING DAYS: 60
COST OF PLANS: $ 5.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-213 from SR-158 to SR-13 (US-43) in Saraland. Length 2.288 mi.

BRACKET ESTIMATE: $525,000 TO $640,000

VIEW ITEMS

Return To: Top of this Page


014. STMAA-0241(501) FRANKLIN & MARION COUNTIES
WORKING DAYS: 30
COST OF PLANS: $ 2.00

for constructing the Resurfacing and Traffic Stripe on SR-241 from just south of the Marion County line (MP 13.558) to MP 14.559 east of Shady Grove. Length 1.024 mi.

BRACKET ESTIMATE: $235,000 TO $287,000

VIEW ITEMS

Return To: Top of this Page


015. STMAA-CN09(208) BALDWIN & MOBILE COUNTIES
WORKING DAYS: 75
COST OF PLANS: $21.00

for constructing the Pavement Repairs at various sites as indicated by the plans.

BRACKET ESTIMATE: $600,000 TO $730,000

VIEW ITEMS

Return To: Top of this Page


016. STMAA-CN09(908) ELMORE COUNTY
WORKING DAYS: 30
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 3.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-14 from SR-212 to SR-9 and on SR-212 from SR-14 to SR-111 in Wetumpka. Length 3.459 mi.

BRACKET ESTIMATE: $1,090,000 TO $1,330,000

VIEW ITEMS

Return To: Top of this Page


017. STMNU-BRZ-3500(214) HOUSTON COUNTY
LENGTH: 0.04 MILES. WORKING DAYS: 80
COST OF PLANS: $ 7.00

for constructing the Bridge Replacement on CR-83 at Cedar Creek northwest of Gordon. Length 0.037 mi.

BRACKET ESTIMATE: $615,000 TO $750,000

VIEW ITEMS

Return To: Top of this Page


018. STMNU-STPNU-0928(200) CHAMBERS COUNTY
LENGTH: 5.57 MILES. WORKING DAYS: 45
COST OF PLANS: $ 3.00

for constructing the Full Depth Reclamation on CR-267 from CR-222 in Fredonia to US-431. Length 5.571 mi.

BRACKET ESTIMATE: $700,000 TO $850,000

VIEW ITEMS

Return To: Top of this Page


019. STMNU-STPNU-5505(20 ,STPOA-5527(201) & STPNU-5502(200) PIKE COUNTY
LENGTH: 13.14 MILES. WORKING DAYS: 50
COST OF PLANS: $ 8.00

for constructing the Resurfacing and Traffic Stripe on CR-2276, CR-2290, CR-7755 and CR-3327 at sites as indicated on the plans. Length 13.138 mi.

BRACKET ESTIMATE: $830,000 TO $1,010,000

VIEW ITEMS

Return To: Top of this Page


020. STMAA-0015(517) LEE COUNTY
LENGTH: 1.93 MILES. WORKING DAYS: 30
COST OF PLANS: $ 2.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-15 (US-29) from the Macon County line to south of CR-010 (Sand Hill Road) (MP 178.23). Length 1.932 mi.

BRACKET ESTIMATE: $645,000 TO $785,000

VIEW ITEMS

Return To: Top of this Page


021. STMAA-STPAA-7615(600) MOBILE COUNTY
LENGTH: 1.83 MILES. WORKING DAYS: 65
COST OF PLANS: $12.00

for constructing the Resurfacing, Traffic Stripe and Drainage Improvements on Half-Mile Road from Beverly Road to approximately 900' west of Padgett Switch Road south of Irvington. Length 1.837 mi.

BRACKET ESTIMATE: $570,000 TO $700,000

VIEW ITEMS

Return To: Top of this Page


034. EB-0038(524) SHELBY COUNTY
LENGTH: 6.84 MILES. WORKING DAYS: 80
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 6.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-38 (US-280) from CR-62 west of Harpersville to the Talladega County line. Length 7.166 mi.

BRACKET ESTIMATE: $3,800,000 TO $4,700,000

VIEW ITEMS

Return To: Top of this Page


038. HSIP-0006(539) & 99-305-543-000-901 PICKENS COUNTY
LENGTH: 17.48 MILES. WORKING DAYS: 75
COST OF PLANS: $11.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-6 (US-82) from 0.3 mi west of Holley Creek to west of the Tuscaloosa County line and 0.4 miles of SR-159 in Gordo. Length 8.732 mi.

BRACKET ESTIMATE: $3,300,000 TO $4,000,000

VIEW ITEMS

Return To: Top of this Page


039. HSIP-0021(526) & 99-304-191-021-901 COOSA COUNTY
WORKING DAYS: 70
COST OF PLANS: $ 2.00

for constructing the Resurfacing and Traffic Stripe on SR-21 (US-231) from the Elmore County line to 0.7 mile south of SR-22 in Rockford. Length 9.127 mi.

BRACKET ESTIMATE: $2,700,000 TO $3,300,000

VIEW ITEMS

Return To: Top of this Page


040. HSIP-0063(501) & 99-304-621-063-901 TALLAPOOSA COUNTY
LENGTH: 25.50 MILES. WORKING DAYS: 100
COST OF PLANS: $ 3.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-63 from north of Hillabee Street west of Alexander City to the Clay County line. Length 12.800 mi.

BRACKET ESTIMATE: $3,300,000 TO $4,000,000

VIEW ITEMS

Return To: Top of this Page


042. STPOA-HSIP-0001(541) & STPOA-0001(550) ETOWAH COUNTY
LENGTH: 5.00 MILES. WORKING DAYS: 60
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 7.00

for constructing the Planing, Resurfacing, Traffic Stripe and Bridge Rail Retrofit on SR-1 (US-431) from MP 255.950 to SR-74 (US-278) in Glencoe. Length 2.500 mi.

BRACKET ESTIMATE: $1,500,000 TO $1,800,000

VIEW ITEMS

Return To: Top of this Page


043. NH-0038(525) SHELBY COUNTY
LENGTH: 5.25 MILES. WORKING DAYS: 50
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 5.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-38 (US-280) from the west Chelsea city limit (MP 15.100) to east of CR-55 (MP 20.350) in Westover. Length 5.250 mi.

BRACKET ESTIMATE: $2,985,000 TO $3,650,000

VIEW ITEMS

Return To: Top of this Page


044. NH-0074(522) BLOUNT COUNTY
LENGTH: 0.71 MILES. WORKING DAYS: 45
COST OF PLANS: $ 4.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-74 (US-278) from the Cullman County line to SR-53 (US-231) west of Brooksville. Length 2.600 mi.

BRACKET ESTIMATE: $760,000 TO $920,000

VIEW ITEMS

Return To: Top of this Page


048. STPAA-HSIP-0025(519) CHEROKEE COUNTY
LENGTH: 3.35 MILES. WORKING DAYS: 65
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 5.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-25 (US-411) from near SR-68 (MP 236.200) in Leesburg to near the SR-68 Bypass (MP 239.550) in Centre. Length 3.350 mi.

BRACKET ESTIMATE: $1,440,000 TO $1,760,000

VIEW ITEMS

Return To: Top of this Page


050. STPBH-CN09(903) JEFFERSON COUNTY
WORKING DAYS: 45
COST OF PLANS: $ 9.00

for constructing the Sidewalk Improvements on 20th Street North from Morris Avenue to Park Place and on 14th Street South at University Blvd. (SR-149) in Birmingham.

BRACKET ESTIMATE: $36,400 TO $44,500

VIEW ITEMS

Return To: Top of this Page


053. STPNU-0323(201) BARBOUR COUNTY
LENGTH: 12.04 MILES. WORKING DAYS: 100
COST OF PLANS: $ 3.00

for constructing the Full Depth Reclamation and Bituminous Treatment on CR-89 from SR-6 (US-82) to CR-49 at Spring Hill. Length 12.044 mi.

BRACKET ESTIMATE: $1,255,000 TO $1,530,000

VIEW ITEMS

Return To: Top of this Page


054. STPNU-2537(200) DEKALB COUNTY
LENGTH: 5.64 MILES. WORKING DAYS: 45
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 3.00

for constructing the Resurfacing and Traffic Stripe on CR-141 from SR-117 in Ider to SR-75. Length 5.635 mi.

BRACKET ESTIMATE: $800,000 TO $980,000

VIEW ITEMS

Return To: Top of this Page


057. STPOA-0014(513) ELMORE COUNTY
WORKING DAYS: 60
COST OF PLANS: $11.00

for constructing the Widening (Grade, Drainage and Pavement) on SR-14 from the east end of the Coosa River relief bridge #2 to the west end of the Coosa River relief bridge #1 in Wetumpka. Length 0.224 mi.

BRACKET ESTIMATE: $615,000 TO $750,000

VIEW ITEMS

Return To: Top of this Page


060. 99-405-632-659-911 TUSCALOOSA COUNTY
LENGTH: 45.55 MILES. WORKING DAYS: 80
COST OF PLANS: $ 3.00

for the Maintenance Roadside Mowing along I-59 from the Greene County line to the Jefferson County line. Length 45.515 mi.

BRACKET ESTIMATE: $170,000 TO $205,000

VIEW ITEMS

Return To: Top of this Page


061. 99-308-663-162-905 WILCOX COUNTY
LENGTH: 6.62 MILES. WORKING DAYS: 65
COST OF PLANS: $10.00

for constructing the Full Depth Reclamation on SR-162 from east of the Red Creek bridge to west of the Dixon Creek bridge east of Kimbrough. Length 6.622 mi.

BRACKET ESTIMATE: $780,000 TO $955,000

VIEW ITEMS

Return To: Top of this Page


064. 99-301-363-035-911 JACKSON COUNTY
LENGTH: 1.00 MILES. WORKING DAYS: 30
COST OF PLANS: $ 7.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-35 from SR-2 (US-72) to SR-279 in Scottsboro. Length 0.999 mi.

BRACKET ESTIMATE: $315,000 TO $385,000

VIEW ITEMS

Return To: Top of this Page


067. 99-302-473-129-912 & 99-302-473-233-913 MARION COUNTY
LENGTH: 1.69 MILES. WORKING DAYS: 30
COST OF PLANS: $ 4.00

for constructing the Resurfacing and Traffic Stripe on SR-129 from the Fayette County line to SR-118 (Alt US-78) and on SR-233 from SR-129 to SR-118 (Alt US-78). Length 4.247 mi.

BRACKET ESTIMATE: $1,030,000 TO $1,260,000

VIEW ITEMS

Return To: Top of this Page


069. 99-406-062-110-801 ,99-406-513-110-701 & 99-406-690-000-601 MONTGOMERY & BULLOCK COUNTIES
WORKING DAYS: 90
COST OF PLANS: $ 4.00

for constructing the Shoulder Paving, Drainage and Guardrail on SR-110 at various sites as indicated on the plans. Length 24.770 mi.

BRACKET ESTIMATE: $1,100,000 TO $1,400,000

VIEW ITEMS

Return To: Top of this Page


070. 99-507-690-000-901 BARBOUR , DALE & HOUSTON COUNTIES
WORKING DAYS: 50
COST OF PLANS: $ 5.00

for the Bridge Coatings (5) on SR-85, SR-1 (US-431) and SR-1 (US-231) at sites as indicated on the plans.

BRACKET ESTIMATE: $220,000 TO $265,000

VIEW ITEMS

Return To: Top of this Page


071. 99-508-690-000-918 CHOCTAW , MARENGO & SUMTER COUNTIES
WORKING DAYS: 30
COST OF PLANS: $ 7.00

for constructing the Bridge Coatings (5 bridges) at 4 sites as indicated on the plans.

BRACKET ESTIMATE: $30,250 TO $36,900

VIEW ITEMS

Return To: Top of this Page