Office Engineer

Proposal Letting List
July 30, 2010 Transportation Letting

Welcome to the Proposal Letting List Page. You may view the approximate items of work for each proposal in the Letting by clicking on the View Items hyperlink to view the Project Item Pages. Please take a minute to review these pages and e-mail the Web Page Editor with your comments.


The Bracket Ranges shown herein are to provide general financial information to Contractors and Bonding Companies concerning a Project's complexity and size only. THESE BRACKETS SHOULD NOT BE USED IN PREPARING A BID, NOR WILL THESE BRACKETS HAVE ANY BEARING ON THE DECISION TO AWARD ANY CONTRACT.


001 . HPP-IM-STPOA-I085(311) , LEE 002 . IM-STPAAF-I020(335) , CLEBURNE
003 . STPAA-8570(601) , MADISON 004 . NHF-0006(530) , BIBB
005 . STMOA-CN10(922) , TUSCALOOSA 006 . STMOA-9628(600) , TUSCALOOSA
007 . STMOA-STPOA-0001(547) , ETOWAH 010 . BHP-0013(557) , MARENGO, etc.
019 . NH-HSIP-0002(539) , JACKSON 020 . HSIP-0027(508) , GENEVA
024 . NH-0004(524) , MARION 028 . STPAA-0003(559) , SHELBY
032 . STPAA-0075(520) , MARSHALL 033 . STPAA-0143(501) , MONTGOMERY, etc.
035 . STPAA-HSIP-0014(518) , ELMORE, etc. 036 . STPAA-HSIP-0136(500) , MONROE
038 . STPBH-CN10(927) , JEFFERSON 040 . STPMB-7500(602) , MOBILE
041 . STPNU-CN10(219) , LOWNDES 042 . STPNU-3017(201) , FRANKLIN
045 . STPOA-0275(502) , TALLADEGA 050 . SRTS-SR09(915) , JEFFERSON
051 . ST-044-888-003 , MACON 052 . 99-409-022-010-930 , BALDWIN
053 . 99-409-491-042-002 , MOBILE 054 . 99-501-003-495-901 , LIMESTONE
055 . 99-509-491-188-004 , MOBILE 056 . 99-309-022-059-008 , BALDWIN

001 . HPP-IM-STPOA-I085(311) LEE COUNTY

SHALL BE COMPLETED BY: July 1, 2012
DBE CONTRACT OBLIGATION: 10 % COST OF PLANS: $131

for constructing the Interchange (Grade, Drainage, Pavement, Signing and Bridge) on I-85 at CR-10 (Beehive Road) at the Auburn Technology Park. Length 1.604 mi.

BRACKET ESTIMATE: $19,200,000 TO $23,500,000

VIEW ITEMS

Return To: Top of this Page


002 . IM-STPAAF-I020(335) CLEBURNE COUNTY

SHALL BE COMPLETED BY: June 1, 2011
DBE CONTRACT OBLIGATION: 4 % COST OF PLANS: $32.00

for constructing the Pavement Rehabilitation on I-20 from east of SR-9 to east of SR-46 at Heflin including a portion of SR-46 at the I-20 interchange area. Length 5.668 mi.

BRACKET ESTIMATE: $7,770,000 TO $9,400,000

VIEW ITEMS

Return To: Top of this Page


003 . STPAA-8570(601) MADISON COUNTY

LENGTH: 1.61 MILES. WORKING DAYS: 360
DBE CONTRACT OBLIGATION: 8 % COST OF PLANS: $88.00

for constructing the Grade, Drainage, Pavement, Signing, Lighting, Signals and Bridges on SR-255 (Research Park Boulevard/Martin Luther King Jr. Boulevard) from south of SR-53 to north of SR-53 in Huntsville. Length 1.609 mi.

BRACKET ESTIMATE: $19,995,000 TO $24,400,000

VIEW ITEMS

Return To: Top of this Page


004 . NHF-0006(530) BIBB COUNTY

WORKING DAYS: 500
DBE CONTRACT OBLIGATION: 7 % COST OF PLANS: $171

for constructing the Grade, Drainage and Bridge Culvert on the new location of SR-6 (US-82) from east of SR-25 in Centreville to east of CR-20. Length 4.795 mi.

BRACKET ESTIMATE: $16,000,000 TO $20,000,000

VIEW ITEMS

Return To: Top of this Page


005 . STMOA-CN10(922) TUSCALOOSA COUNTY

WORKING DAYS: 180
DBE CONTRACT OBLIGATION: 5 % COST OF PLANS: $40.00

for constructing the Drainage, Sidewalk, Pavement, Lighting and Signals on SR-215 (Greensboro Avenue) from Hargrove Road to 15th Street in Tuscaloosa. Length 0.512 mi.

BRACKET ESTIMATE: $3,700,000 TO $4,550,000

VIEW ITEMS

Return To: Top of this Page


006 . STMOA-9628(600) & STMOA-9642(600) TUSCALOOSA COUNTY

WORKING DAYS: 30
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $14.00

for constructing the Planing, Resurfacing and Traffic Stripe on Charlie Shirley Road and Fifth Street in Northport at sites as indicated by the plans. Length 2.984 mi.

BRACKET ESTIMATE: $400,000 TO $500,000

VIEW ITEMS

Return To: Top of this Page


007 . STMOA-STPAA-0001(547) ETOWAH COUNTY

LENGTH: 1.00 MILES. WORKING DAYS: 80
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 6.00

for constructing the Micro-Milling, Resurfacing and Traffic Stripe on SR-1 (US-431) (Meighan Boulevard) from the Coosa River bridge to Terminal Street in Gadsden. Length 0.900 mi.

BRACKET ESTIMATE: $1,515,000 TO $1,850,000

VIEW ITEMS

Return To: Top of this Page


010 . BHP-0013(557) MARENGO & GREENE COUNTIES

LENGTH: 0.62 MILES. WORKING DAYS: 110
COST OF PLANS: $22.00

for constructing the Bridge Coating on SR-13 (US-43) at Warrior River north of Demopolis. Length 0.617 mi.

BRACKET ESTIMATE: $426,000 TO $520,000

VIEW ITEMS

Return To: Top of this Page


019 . NH-HSIP-0002(539) JACKSON COUNTY

LENGTH: 5.72 MILES. WORKING DAYS: 55
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 6.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-2 (US-72) (WBR Only) from CR-42 to Crow Creek at Stevenson. Length 5.715 mi.

BRACKET ESTIMATE: $1,850,000 TO $2,250,000

VIEW ITEMS

Return To: Top of this Page


020 . HSIP-0027(508) & 99-307-312-027-001 GENEVA COUNTY

LENGTH: 11.88 MILES. WORKING DAYS: 50
COST OF PLANS: $16.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-27 from the Florida state line to SR-52 in Geneva. Length 5.940 mi.

BRACKET ESTIMATE: $1,650,000 TO $2,000,000

VIEW ITEMS

Return To: Top of this Page


024 . NH-0004(524) MARION COUNTY

WORKING DAYS: 30
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 8.00

for constructing the Pavement Repair on SR-4 (Corridor X) at various sites as indicated by the plans.

BRACKET ESTIMATE: $665,000 TO $800,000

VIEW ITEMS

Return To: Top of this Page


028 . STPAA-0003(559) SHELBY COUNTY

LENGTH: 2.65 MILES. WORKING DAYS: 60
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 9.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-3 (US-31) from south of I-65 (MP 252.800) to CR-68 in Alabaster. Length 2.650 mi.

BRACKET ESTIMATE: $1,480,000 TO $1,800,000

VIEW ITEMS

Return To: Top of this Page


032 . STPAA-0075(520) MARSHALL COUNTY

LENGTH: 4.19 MILES. WORKING DAYS: 80
DBE CONTRACT OBLIGATION: 4 % COST OF PLANS: $ 9.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-75 from SR-1 (US-431) in Albertville to north of SR-68 (MP 62.99). Length 4.189 mi.

BRACKET ESTIMATE: $2,690,000 TO $3,290,000

VIEW ITEMS

Return To: Top of this Page


033 . STPAA-0143(501) & STPAA-0143(502) MONTGOMERY & ELMORE COUNTIES

LENGTH: 2.82 MILES. WORKING DAYS: 30
COST OF PLANS: $ 7.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-143 from I-65 to north of CR-23 (Coosada Road) in Millbrook. Length 4.439 mi.

BRACKET ESTIMATE: $1,250,000 TO $1,530,000

VIEW ITEMS

Return To: Top of this Page


035 . STPAA-HSIP-0014(518) & STPAA-0229(506) ELMORE & MACON COUNTIES

LENGTH: 4.41 MILES. WORKING DAYS: 75
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 8.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-14 and on SR-229 at various sites as indicated by the plans. Length 5.491 mi.

BRACKET ESTIMATE: $1,100,000 TO $1,360,000

VIEW ITEMS

Return To: Top of this Page


036 . STPAA-HSIP-0136(500) MONROE COUNTY

Return To: Top of this Page

LENGTH: 5.93 MILES. WORKING DAYS: 40
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 8.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-136 from SR-21 through Excel to SR-12 (US-84). Length 5.928 mi.

BRACKET ESTIMATE: $1,180,000 TO $1,300,000

VIEW ITEMS

Return To: Top of this Page


038 . STPBH-CN10(927) JEFFERSON COUNTY

WORKING DAYS: 30 COST OF PLANS: $ 6.00

for constructing the Pedestrian Improvements between Chalkville Road at North Mall intersection and North Mall at Parkway Drive in Trussville. Length 0.265 mi.

BRACKET ESTIMATE: $62,000 TO $77,000

VIEW ITEMS

Return To: Top of this Page


040 . STPMB-7500(602) MOBILE COUNTY

WORKING DAYS: 160 COST OF PLANS: $12.00

for constructing the Signal Interconnection on Airport Boulevard (CR-56) from Cody Road (CR-429) to Williams Street in Mobile.

BRACKET ESTIMATE: $315,000 TO $390,000

VIEW ITEMS

Return To: Top of this Page


041 . STPNU-CN10(219) LOWNDES COUNTY

LENGTH: 3.66 MILES. WORKING DAYS: 35
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 4.00

for constructing the Resurfacing and Traffic Stripe on CR-62 from the Butler county line to SR-3 (US-31) south of Sandy Ridge. Length 3.662 mi.

BRACKET ESTIMATE: $540,000 TO $660,000

VIEW ITEMS

Return To: Top of this Page


042 . STPNU-3017(201) FRANKLIN COUNTY

LENGTH: 1.29 MILES. WORKING DAYS: 30
COST OF PLANS: $ 3.00

for constructing the Resurfacing and Traffic Stripe on CR-20 from CR-22 to CR-63 north of Phil Campbell. Length 1.296 mi.

BRACKET ESTIMATE: $235,000 TO $290,000

VIEW ITEMS

Return To: Top of this Page


045 . STPOA-0275(502) TALLADEGA COUNTY

WORKING DAYS: 300
DBE CONTRACT OBLIGATION: 10 % COST OF PLANS: $85.00

for constructing the Partial Grade and Drain, Pavement and Landfill Removal on the extension of SR-275 from SR-77 to SR-21 in Talladega. Length 10.360 km

BRACKET ESTIMATE: $11,300,000 TO $13,800,000

VIEW ITEMS

Return To: Top of this Page


050 . SRTS-SR09(915) JEFFERSON COUNTY

WORKING DAYS: 75 COST OF PLANS: $ 5.00

for constructing the Concrete Sidewalks and Landscaping at various sites in Homewood as indicated by the plans.

BRACKET ESTIMATE: $155,000 TO $190,000

VIEW ITEMS

Return To: Top of this Page


051 . ST-044-888-003 MACON COUNTY

LENGTH: 1.43 MILES. WORKING DAYS: 30
COST OF PLANS: $ 3.00

for constructing the Planing, Resurfacing and Traffic Stripe on CR-61 (Hospital Road) from SR-81 to the Veterans Administration Hospital in Tuskegee. Length 1.429 mi.

BRACKET ESTIMATE: $224,000 TO $270,000

VIEW ITEMS

Return To: Top of this Page


052 . 99-409-022-010-930 BALDWIN COUNTY

WORKING DAYS: 45 COST OF PLANS: $ 2.00

for the Coating of the existing Water Tower on I-10 at the Welcome Center near the Florida State Line.

BRACKET ESTIMATE: $103,000 TO $126,000

VIEW ITEMS

Return To: Top of this Page


053 . 99-409-491-042-002 MOBILE COUNTY

WORKING DAYS: 35 COST OF PLANS: $10.00

for constructing the Intersection Improvements (Widening and Signalization) on SR-42 (US-98) at CR-31 Schillinger Road) west of Prichard. Length 0.094 mi.

BRACKET ESTIMATE: $180,000 TO $225,000

VIEW ITEMS

Return To: Top of this Page


054 . 99-501-003-495-901 LIMESTONE COUNTY

LENGTH: 0.20 MILES. CALENDAR DAYS: 30
COST OF PLANS: $10.00

for constructing the Hydroblasting and Bridge Deck Repair on SR-127 at the Elk River northwest of Elkmont. Length 0.204 mi.

BRACKET ESTIMATE: $410,000 TO $500,000

VIEW ITEMS

Return To: Top of this Page


055 . 99-509-491-188-004 MOBILE COUNTY

WORKING DAYS: 75 COST OF PLANS: $14.00

for the Bridge Coating on SR-188 at Bayou La Batre in Bayou La Batre.

BRACKET ESTIMATE: $285,000 TO $350,000

VIEW ITEMS

Return To: Top of this Page


056 . 99-309-022-059-008 BALDWIN COUNTY

LENGTH: 2.70 MILES. WORKING DAYS: 35
COST OF PLANS: $ 5.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-59 from the railroad bridge in Bay Minette to SR-287. Length 2.697 mi.

BRACKET ESTIMATE: $1,175,000 TO $1,430,000

VIEW ITEMS

Return To: Top of this Page