Office Engineer

Proposal Letting List
March 26, 2010 Transportation Letting

Welcome to the Proposal Letting List Page. You may view the approximate items of work for each proposal in the Letting by clicking on the View Items hyperlink to view the Project Item Pages. Please take a minute to review these pages and e-mail the Web Page Editor with your comments.


The Bracket Ranges shown herein are to provide general financial information to Contractors and Bonding Companies concerning a Project's complexity and size only. THESE BRACKETS SHOULD NOT BE USED IN PREPARING A BID, NOR WILL THESE BRACKETS HAVE ANY BEARING ON THE DECISION TO AWARD ANY CONTRACT.


001 . STMAA-STPAA-7273(600) , JEFFERSON 003 . STMBH-CN07(908) , JEFFERSON
004 . STMBH-CMAQ-9802(918) , JEFFERSON 006 . STPNU-0271(907) , CLAY
008 . STMHV-CN10(215) , MADISON 009 . STMHV-4500(215) , MADISON
011 . STMLL-STPLL-0042(518) , BALDWIN 013 . HRRR-CN10(203) , LEE
014 . STMOA-BRZ-0800(216) , CALHOUN 015 . STPOA-BRZ-3000(209) , FRANKLIN
017 . STMOA-BRZ-6500(206) , WASHINGTON 019 . STMOA-2331(200) , DALE
021 . STMNU-STPNU-CN10(213) , BIBB 022 . STMNU-STPNU-CN10(216) , MONTGOMERY
023 . STMOA-STPOA-CN10(217) , CLEBURNE 024 . STMOA-STPOA-2F07(600) , DEKALB
025 . STMOA-STPOA-0210(200) , BALDWIN 026 . STMNU-STPNU-0325(201) , BARBOUR
027 . STMNU-STPNU-0707(200) , BUTLER 028 . STMOA-STPOA-1205(201) , CHOCTAW
029 . STMNU-STPNU-1907(200) , COOSA 030 . STMOA-STPOA-2111(202) , CRENSHAW
031 . STMNU-STPNU-2446(200) , DALLAS 032 . STMOA-STPOA-3621(201) , JACKSON
033 . STMNU-STPOA-4606(201) , MARENGO 034 . STMNU-STMOA-STPNU-4738(200) , MARION
035 . STMNU-STPNU-6111(200) , TALLADEGA 036 . STMNU-STPOA-6617(200) , WILCOX
037 . STMNU-STPNU-6721(200) , WINSTON *038 . STMOA-STPOA-0271(501) , MONTGOMERY
*039 . STMOA-STPOA-0007(514) , TUSCALOOSA 040 . STMOA-CN10(923) , MORGAN
041 . STMOA-0800(214) , CALHOUN* 042 . STMOA-6303(200) , TUSCALOOSA
043 . STMOA-9628(600) , TUSCALOOSA 044 . STMOA-STPOA-CN10(214) , MARSHALL
045 . STMOA-STPOA-5A20(600) , LIMESTONE 046 . STMNU-STPNU-2215(200) , CULLMAN
*047 . STMOA-NH-0133(503) , COLBERT *048 . STMOA-6312(200) , TUSCALOOSA, etc.
050 . STMPC-8018(601) , RUSSELL 051 . STMPC-STMAA-NH-0001(555) , RUSSELL
054 . BRF-0074(505) , MARION 056 . ERF-8910(910) , BALDWIN*
058 . NH-0002(520) , JACKSON 061 . ER-8910(929) , MONTGOMERY
062 . HRRR-2100(202) , CRENSHAW 063 . HRRR-6305(200) , TUSCALOOSA
064 . TCSP-06AL(002) , WINSTON 066 . ST-037-038-002 , JEFFERSON*
067 . ST-061-999-010 , TALLADEGA 068 . 99-409-491-000-003 , MOBILE
069 . 99-504-690-000-901 , CLEBURNE
  * - WITHDRAWN FROM THE LETTING
** - STIMULUS PROJECTS

001 . STMAA-STPAA-7273(600) JEFFERSON COUNTY

LENGTH: 1.59 MILES. WORKING DAYS: 40
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 8.00

for constructing the Planing, Resurfacing and Traffic Stripe on Deerfoot Parkway from SR-7 (US-11) to I-59 in Trussville. Length 1.584 mi.

BRACKET ESTIMATE: $350,000 TO $430,000

VIEW ITEMS

Return To: Top of this Page


003 . STMBH-CN07(908) & STMBH-CN07(909) JEFFERSON COUNTY

WORKING DAYS: 120
DBE CONTRACT OBLIGATION: 5 % COST OF PLANS: $ 8.00

for constructing the Sidewalk and Landscaping along Rockview Lane and Park Avenue in Hoover at sites as indicated by the plans.

BRACKET ESTIMATE: $505,000 TO $620,000

VIEW ITEMS

Return To: Top of this Page


004 . STMBH-CMAQ-9802(918) JEFFERSON COUNTY

WORKING DAYS: 120
DBE CONTRACT OBLIGATION: 5 % COST OF PLANS: $39.00

for constructing the Intersection Improvements on Lorna Road in Hoover at four sites as indicated by the plans.

BRACKET ESTIMATE: $1,535,000 TO $1,875,000

VIEW ITEMS

Return To: Top of this Page


006 . STPNU-0271(907) & STMFH-27-1(907) CLAY COUNTY

LENGTH: 4.18 MILES. WORKING DAYS: 40
COST OF PLANS: $ 4.00

for constructing the Resurfacing and Traffic Stripe on CR-7from CR-18 to the Talladega County line in the Talladega National Forest. Length 2.052 mi.

BRACKET ESTIMATE: $275,000 TO $340,000

VIEW ITEMS

Return To: Top of this Page


008 . STMHV-CN10(215) MADISON COUNTY

LENGTH: 0.22 MILES. WORKING DAYS: 60
COST OF PLANS: $ 8.00

for constructing the Bridge Replacement (Bridge Culvert) and Approaches on Love Branch Road at Leslie Branch west of Huntsville. Length 0.216 mi.

BRACKET ESTIMATE: $302,000 TO $369,000

VIEW ITEMS

Return To: Top of this Page


009 . STMHV-4500(215) MADISON COUNTY

LENGTH: 0.13 MILES. WORKING DAYS: 45
COST OF PLANS: $ 7.00

for constructing the Bridge Replacement (Bridge Culvert) and Approaches on Douglass Road at Douglass Creek in Monrovia. Length 0.129 mi.

BRACKET ESTIMATE: $285,000 TO $350,000

VIEW ITEMS

Return To: Top of this Page


011 . STMLL-STPLL-0042(518) BALDWIN COUNTY

LENGTH: 0.04 MILES. WORKING DAYS: 30
COST OF PLANS: $ 6.00

for constructing the Traffic Signal on SR-42 (US-98) at CR-99 in Lillian. Length 0.036 mi.

BRACKET ESTIMATE: $115,000 TO $140,000

VIEW ITEMS

Return To: Top of this Page


013 . HRRR-CN10(203) & STMNU-4107(200)LEE COUNTY

LENGTH: 3.55 MILES. WORKING DAYS: 35
COST OF PLANS: $ 6.00

for constructing the Resurfacing, Traffic Stripe and Pavement Markers at various sites as indicated by the plans. Length 3.549 mi.

BRACKET ESTIMATE: $200,000 TO $250,000

VIEW ITEMS

Return To: Top of this Page


014 . STMOA-BRZ-0800(216) CALHOUN COUNTY

LENGTH: 0.26 MILES. WORKING DAYS: 150
DBE CONTRACT OBLIGATION: 5 % COST OF PLANS: $11.00

for constructing the Bridge Replacement and Approaches on Prickett Trail at Tallasseehatchee Creek west of Jacksonville. Length 0.255 mi.

BRACKET ESTIMATE: $1,120,000 TO $1,370,000

VIEW ITEMS

Return To: Top of this Page


015 . STMOA-BRZ-3000(209) FRANKLIN COUNTY

LENGTH: 0.02 MILES. WORKING DAYS: 60
COST OF PLANS: $ 5.00

for constructing the Bridge Replacement on CR-93 at Bear Creek south of Oak Grove. Length 0.021 mi.

BRACKET ESTIMATE: $359,000 TO $439,000

VIEW ITEMS

Return To: Top of this Page


017 . STMOA-BRZ-6500(206) WASHINGTON COUNTY

LENGTH: 0.10 MILES. WORKING DAYS: 120
COST OF PLANS: $ 4.00

for constructing the Bridge Replacement (Precast) on CR-1 at the Escatawpa River at Vinegar Bend. Length 0.098 mi.

BRACKET ESTIMATE: $1,000,000 TO $1,220,000

VIEW ITEMS

Return To: Top of this Page


019 . STMOA-2331(200) , STMOA-2311(202), STMOA-2311(201) , STMOA-2304(200) , STMOA-2315(201) & STMOA-9440(600) DALE COUNTY

LENGTH: 16.74 MILES. WORKING DAYS: 60
COST OF PLANS: $15.00

for constructing the Resurfacing and Traffic Stripe on various county roads at sites as indicated by the plans. Length 16.721 mi.

BRACKET ESTIMATE: $375,000 TO $460,000

VIEW ITEMS

Return To: Top of this Page


021 . STMNU-STPNU-CN10(213) BIBB COUNTY

LENGTH: 71.64 MILES. WORKING DAYS: 45
COST OF PLANS: $ 2.00

for constructing the Traffic Stripe, Markings, Legends and Signing on various county roads at sites as indicated by the plans. Length 71.641 mi.

BRACKET ESTIMATE: $341,000 TO $417,000

VIEW ITEMS

Return To: Top of this Page


022 . STMNU-STPNU-CN10(216) MONTGOMERY COUNTY

LENGTH: 8.02 MILES. WORKING DAYS: 45
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 5.00

for constructing the Planing, Resurfacing and Traffic Stripe on CR-24 from the Lowndes County line to SR-3 (US-31) and on CR-39 from Mt. Zion Road to the Montgomery city limit. Length 8.020 mi.

BRACKET ESTIMATE: $950,000 TO $1,160,000

VIEW ITEMS

Return To: Top of this Page


023 . STMOA-STPOA-CN10(217) CLEBURNE COUNTY

LENGTH: 3.21 MILES. WORKING DAYS: 45
COST OF PLANS: $ 4.00

for constructing the Resurfacing and Traffic Stripe on CR-36 from SR-1 (US-431) to CR-13 southwest of Heflin and on CR-23 from the Georgia state line east of Ranburne to the Georgia state line. Length 3.209 mi.

BRACKET ESTIMATE: $535,000 TO $655,000

VIEW ITEMS

Return To: Top of this Page


024 . STMOA-STPOA-2F07(600) DEKALB COUNTY

LENGTH: 2.90 MILES. WORKING DAYS: 45
COST OF PLANS: $ 3.00

for constructing the Resurfacing and Traffic Stripe on CR-89 from the Fort Payne city limit to CR-78 in Fort Payne. Length 2.900 mi.

BRACKET ESTIMATE: $390,000 TO $480,000

VIEW ITEMS

Return To: Top of this Page


025 . STMOA-STPOA-0210(200) BALDWIN COUNTY

LENGTH: 7.22 MILES. WORKING DAYS: 45
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 3.00

for constructing the Resurfacing and Traffic Stripe on CR-32 from SR-59 in Summerdale to CR-87. Length 7.215 mi.

BRACKET ESTIMATE: $1,640,000 TO $2,005,000

VIEW ITEMS

Return To: Top of this Page


026 . STMNU-STPNU-0325(201) BARBOUR COUNTY

LENGTH: 4.20 MILES. WORKING DAYS: 30
COST OF PLANS: $ 3.00

for constructing the Resurfacing on CR-49 from SR-6 (US-82) to CR-89 at Springhill. Length 4.203 mi.

BRACKET ESTIMATE: $260,000 TO $315,000

VIEW ITEMS

Return To: Top of this Page


027 . STMNU-STPNU-0707(200) BUTLER COUNTY

LENGTH: 7.90 MILES. WORKING DAYS: 45
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 3.00

for constructing the Resurfacing and Traffic Stripe on CR-15 from SR-106 at Starlington to CR-38. Length 7.902 mi.

BRACKET ESTIMATE: $715,000 TO $875,000

VIEW ITEMS

Return To: Top of this Page


028 . STMOA-STPOA-1205(201) CHOCTAW COUNTY

LENGTH: 6.13 MILES. WORKING DAYS: 30
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 3.00

for constructing the Resurfacing and Traffic Stripe on CR-32 from CR-9 to SR-17 northeast of Lisman. Length 6.129 mi.

BRACKET ESTIMATE: $1,100,000 TO $1,300,000

VIEW ITEMS

Return To: Top of this Page


029 . STMNU-STPNU-1907(200) COOSA COUNTY

LENGTH: 6.19 MILES. WORKING DAYS: 30
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 3.00

for constructing the Resurfacing and Traffic Stripe on CR-85 from CR-50 at Kellyton to CR-86 at Goodwater. Length 6.194 mi.

BRACKET ESTIMATE: $660,000 TO $800,000

VIEW ITEMS

Return To: Top of this Page


030 . STMOA-STPOA-2111(202) CRENSHAW COUNTY

LENGTH: 3.99 MILES. WORKING DAYS: 30
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 2.00

for constructing the Planing, Resurfacing and Traffic Stripe on CR-6 from the Luverne city limits to the Glenwood city limits. Length 3.998 mi.

BRACKET ESTIMATE: $580,000 TO $710,000

VIEW ITEMS

Return To: Top of this Page


031 . STMNU-STPNU-2446(200) DALLAS COUNTY

LENGTH: 3.63 MILES. WORKING DAYS: 30
DBE CONTRACT OBLIGATION: 4 % COST OF PLANS: $ 3.00

for constructing the Resurfacing and Traffic Stripe on CR-81 from SR-22 to SR-22 north of Selma. Length 3.627 mi.

BRACKET ESTIMATE: $565,000 TO $690,000

VIEW ITEMS

Return To: Top of this Page


032 . STMOA-STPOA-3621(201) JACKSON COUNTY

LENGTH: 4.15 MILES. WORKING DAYS: 35
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 4.00

for constructing the Resurfacing and Traffic Stripe on CR-88 from SR-71 east of Pisgah to the Dekalb County line. Length 4.149 mi.

BRACKET ESTIMATE: $570,000 TO $700,000

VIEW ITEMS

Return To: Top of this Page


033 . STMNU-STPOA-4606(201) MARENGO COUNTY

LENGTH: 4.10 MILES. WORKING DAYS: 30
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 3.00

for constructing the Resurfacing and Traffic Stripe on CR-33 from SR-13 (US-43) south of Linden to CR-47. Length 4.100 mi.

BRACKET ESTIMATE: $530,000 TO $640,000

VIEW ITEMS

Return To: Top of this Page


034 . STMNU-STMOA-STPNU-4738(200) MARION COUNTY

LENGTH: 1.59 MILES. WORKING DAYS: 30
COST OF PLANS: $ 3.00

for constructing the Resurfacing and Traffic Stripe on CR-51 from CR-42 to SR-74 (US-278) east of Hamilton. Length 1.590 mi.

BRACKET ESTIMATE: $290,000 TO $355,000

VIEW ITEMS

Return To: Top of this Page


035 . STMNU-STPNU-6111(200) TALLADEGA COUNTY

LENGTH: 2.70 MILES. WORKING DAYS: 30
COST OF PLANS: $ 4.00

for constructing the Resurfacing, Guardrail and Traffic Stripe on CR-209 from SR-77 south of Waldo to the Clay County line. Length 2.699 mi.

BRACKET ESTIMATE: $365,000 TO $445,000

VIEW ITEMS

Return To: Top of this Page


036 . STMNU-STPOA-6617(200) WILCOX COUNTY

LENGTH: 7.15 MILES. WORKING DAYS: 30
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 3.00

for constructing the Resurfacing and Traffic Stripe on CR-29 from the Gees Bend Farm Road in Gees Bend to 0.473 miles north of Chilatchee Park Road. Length 7.149 mi.

BRACKET ESTIMATE: $1,200,000 TO $1,360,000

VIEW ITEMS

Return To: Top of this Page


037 . STMNU-STPNU-6721(200) WINSTON COUNTY

LENGTH: 3.04 MILES. WORKING DAYS: 30
COST OF PLANS: $ 3.00

for constructing the Resurfacing and Traffic Stripe on CR-14 (Sardis Airport Road) from CR-41 in Addison to CR-39. Length 3.043 mi.

BRACKET ESTIMATE: $295,000 TO $361,000

VIEW ITEMS

Return To: Top of this Page


038 . STMOA-STPOA-0271(501) MONTGOMERY COUNTY

WORKING DAYS: 60
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 3.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-271 from US-231 to Vaughn Road in Montgomery. Length 3.148 mi.

BRACKET ESTIMATE: $1,900,000 TO $2,300,000

****WITHDRAWN FROM THE LETTING****

Return To: Top of this Page


039 . STMOA-STPOA-0007(514) TUSCALOOSA COUNTY

LENGTH: 2.13 MILES. WORKING DAYS: 50
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $12.00

for constructing the Planing, Resurfacing, Traffic Stripe and Turn Lanes on SR-7 (US-11) from east of CR-37 (Hargrove Road) in Tuscaloosa to 61st Avenue. Length 2.154 mi.

BRACKET ESTIMATE: $1,375,000 TO $1,690,000

****WITHDRAWN FROM THE LETTING****

Return To: Top of this Page


040 . STMOA-CN10(923) MORGAN COUNTY

LENGTH: 2.32 MILES. WORKING DAYS: 30
COST OF PLANS: $ 4.00

for constructing the Planing, Resurfacing and Traffic Stripe on CR-103 (Hayes Street) from SR-3 (US-31) to Karl Prince Drive and on Sparkman Street from Karl Prince Drive to SR-3 (US-31) in Hartselle. Length 2.321 mi.

BRACKET ESTIMATE: $300,000 TO $370,000

VIEW ITEMS

Return To: Top of this Page


041 . STMOA-0800(214) & STMOA-STPOA-0800(215) CALHOUN COUNTY

WORKING DAYS: 125
DBE CONTRACT OBLIGATION: 4 % COST OF PLANS: $30.00

for constructing the Resurfacing, Traffic Stripe and Drainage on Hillyer Robinson Industrial Parkway and on Frank Akers Road in Anniston at various sites as indicated by the plans. Length 1.163 mi.

BRACKET ESTIMATE: $1,380,000 TO $1,690,000

****WITHDRAWN FROM LETTING****

Return To: Top of this Page


042 . STMOA-6303(200) TUSCALOOSA COUNTY

LENGTH: 5.46 MILES. WORKING DAYS: 50
DBE CONTRACT OBLIGATION: 2 % COST OF PLANS: $ 5.00

for constructing the Full Depth Reclamation, Resurfacing and Traffic Stripe on CR-239 (Hagler Coaling Road) from CR-240 (Serty Boyd Road) to CR-566 (Clements Road) north of Hagler. Length 5.500 mi.

BRACKET ESTIMATE: $924,000 TO $1,140,000

VIEW ITEMS

Return To: Top of this Page


043 . STMOA-9628(600) ,STMOA-9642(600) & STMOA-9673(600) TUSCALOOSA COUNTY

WORKING DAYS: 45
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $18.00

for constructing the Planing, Resurfacing and Traffic Stripe on Charley Shirley Road, Fifth Street and Bridge Avenue in Northport at sites as indicated by the plans. Length 4.316 mi.

BRACKET ESTIMATE: $690,000 TO $860,000

VIEW ITEMS

Return To: Top of this Page


044 . STMOA-STPOA-CN10(214) MARSHALL COUNTY

LENGTH: 3.61 MILES. WORKING DAYS: 45
COST OF PLANS: $ 4.00

for constructing the Resurfacing and Traffic Stripe on Hustleville Road from Short Creek to SR-75 northeast of Albertville. Length 3.609 mi.

BRACKET ESTIMATE: $690,000 TO $840,000

VIEW ITEMS

Return To: Top of this Page


045 . STMOA-STPOA-5A20(600) LIMESTONE COUNTY

LENGTH: 2.06 MILES. WORKING DAYS: 30
COST OF PLANS: $ 3.00

for constructing the Resurfacing and Traffic Stripe on Lucas Ferry Road from Harris Station Road to Nuclear Plant Road south of Athens. Length 2.059 mi.

BRACKET ESTIMATE: $290,000 TO $360,000

VIEW ITEMS

Return To: Top of this Page


046 . STMNU-STPNU-2215(200) CULLMAN COUNTY

LENGTH: 6.33 MILES. WORKING DAYS: 45
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 3.00

for constructing the Resurfacing and Traffic Stripe on CR-1069 from CR-1043 to CR-1101 northwest of Jones Chapel. Length 6.329 mi.

BRACKET ESTIMATE: $1,100,000 TO $1,300,000

VIEW ITEMS

Return To: Top of this Page


047 . STMOA-NH-0133(503) COLBERT COUNTY

LENGTH: 2.55 MILES. WORKING DAYS: 30
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 4.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-133 from CR-22 (Old Highway 20) to Lincoln Avenue in Muscle Shoals. Length 2.545 mi.

BRACKET ESTIMATE: $511,000 TO $625,000

****WITHDRAWN FROM THE LETTING****

Return To: Top of this Page


048 . STMOA-6312(200) TUSCALOOSA & JEFFERSON COUNTIES

LENGTH: 0.16 MILES. WORKING DAYS: 120
DBE CONTRACT OBLIGATION: 5 % COST OF PLANS: $ 8.00

for constructing the Bridge Replacement (Bridge Culvert) and Approaches on Eastern Valley Road at Cooley Creek southeast of Bucksville. Length 0.160 mi.

BRACKET ESTIMATE: $582,000 TO $716,000

****WITHDRAWN FROM THE LETTING****

Return To: Top of this Page


050 . STMPC-8018(601) RUSSELL COUNTY

LENGTH: 0.97 MILES. WORKING DAYS: 30
COST OF PLANS: $ 3.00

for constructing the Planing, Resurfacing and Traffic Stripe on CR-427(Opelika Road) from 0.027 miles northwest of the Phenix City limits to 0.197 miles south of Stafford Road. Length 0.946 mi.

BRACKET ESTIMATE: $223,000 TO $272,000

VIEW ITEMS

Return To: Top of this Page


051 . STMPC-STMAA-NH-0001(555) RUSSELL COUNTY

LENGTH: 1.79 MILES. WORKING DAYS: 70
DBE CONTRACT OBLIGATION: 4 % COST OF PLANS: $ 4.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-1 (US-431) from MP 113.942 to MP 115.730 in Phenix City. Length 1.788 mi.

BRACKET ESTIMATE: $1,715,000 TO $2,095,000

VIEW ITEMS

Return To: Top of this Page


054 . BRF-0074(505) MARION COUNTY

SHALL BE COMPLETED BY: October 8, 2010
DBE CONTRACT OBLIGATION: 6 % COST OF PLANS: $24.00

for constructing the Bridge Replacement and Approaches on SR-74 (US-278) at Barn Creek northeast of Pearces Mill. Length 0.763 mi.

BRACKET ESTIMATE: $3,370,000 TO $4,100,000

VIEW ITEMS

Return To: Top of this Page


056 . ERF-8910(910) BALDWIN COUNTY

LENGTH: 1.01 MILES. WORKING DAYS: 150
DBE CONTRACT OBLIGATION: 5 % COST OF PLANS: $31.00

for constructing the Slide Corrections on I-10 at three sites between 0.14 mile east of CR-87 (MP 57.429) to one mile west of the Styx River (MP 59.5) Length 1.013 mi.

BRACKET ESTIMATE: $1,690,000 TO $2,060,000

****WITHDRAWN FROM THE LETTING****

Return To: Top of this Page


058 . NH-0002(520) JACKSON COUNTY

LENGTH: 9.28 MILES. WORKING DAYS: 110
COST OF PLANS: $ 8.00

for constructing the Interchange Lighting on SR-2 (US-72) at SR-277 north of Stevenson.

BRACKET ESTIMATE: $2,000,000 TO $2,300,000

VIEW ITEMS

Return To: Top of this Page


061 . ER-8910(929) MONTGOMERY COUNTY

WORKING DAYS: 60
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 4.00

for constructing the Bridge Scour Repair on I-85, SR-126 and SR-8 (US-80) at Millie Creek and Jenkins Creek east of Montgomery.

BRACKET ESTIMATE: $860,000 TO $1,000,000

VIEW ITEMS

Return To: Top of this Page


062 . HRRR-2100(202) CRENSHAW COUNTY

LENGTH: 1.59 MILES. WORKING DAYS: 30
COST OF PLANS: $ 2.00

for constructing the Resurfacing and Traffic Stripe on CR-35 from the end of pavement to the Rutledge town limits. Length 3.594 mi.

BRACKET ESTIMATE: $271,000 TO $331,000

VIEW ITEMS

Return To: Top of this Page


063 . HRRR-6305(200) TUSCALOOSA COUNTY

LENGTH: 2.71 MILES. WORKING DAYS: 30
COST OF PLANS: $ 2.00

for constructing the Leveling, Traffic Stripe, Traffic Control Markings, Pavement Markers and Signs on Romulus Road from Foxfire Road to Sipsey Valley Road northwest of Fosters. Length 2.708 mi.

BRACKET ESTIMATE: $90,000 TO $115,000

VIEW ITEMS

Return To: Top of this Page


064 . TCSP-06AL(002) WINSTON COUNTY

LENGTH: 0.28 MILES. WORKING DAYS: 60
COST OF PLANS: $10.00

for constructing the Grade, Drainage and Pavement on Joint Armed Forces Access Road in Haleyville. Length 0.276 mi.

BRACKET ESTIMATE: $250,000 TO $305,000

VIEW ITEMS

Return To: Top of this Page


066 . ST-037-038-002 JEFFERSON COUNTY

WORKING DAYS: 30 COST OF PLANS: $ 4.00

for the Crossover Removal on SR-38 (US-280) at MP 1.1 in Homewood. Length 0.115 mi.

BRACKET ESTIMATE: $57,000 TO $70,000

****WITHDRAWN FOR THE LETTING****

Return To: Top of this Page


067 . ST-061-999-010 TALLADEGA COUNTY

WORKING DAYS: 75 COST OF PLANS: $22.00

for constructing the New City Street (Grade, Drainage and Pavement) from Lomar Drive to Campground Drive in Lincoln. Length 0.511 mi.

BRACKET ESTIMATE: $620,000 TO $759,000

VIEW ITEMS

Return To: Top of this Page


068 . 99-409-491-000-003 MOBILE COUNTY

WORKING DAYS: 100 COST OF PLANS: $ 3.00

for the Roadside Mowing, Litter Collection and Selective Clearing along I-10, I-65 and I-165 at sites as indicated by the plans.

BRACKET ESTIMATE: $200,000 TO $240,000

VIEW ITEMS

Return To: Top of this Page


069 . 99-504-690-000-901 CLEBURNE COUNTY

WORKING DAYS: 65 COST OF PLANS: $ 2.00

for constructing the Bridge Coating on CR-18 at I-20 and on SR-46 at I-20 east of Heflin.

BRACKET ESTIMATE: $380,000 TO $460,000

VIEW ITEMS

Return To: Top of this Page