Office Engineer

Proposal Letting List
August 26, 2011 Transportation Letting

Welcome to the Proposal Letting List Page. You may view the approximate items of work for each proposal in the Letting by clicking on the View Items hyperlink to view the Project Item Pages. Please take a minute to review these pages and e-mail the Web Page Editor with your comments.


If you would like to order Plans, Proposals, Specification Standard Drawings, please use the ALDOT Order Form ; . THANKS !!!


The Bracket Ranges shown herein are to provide general financial information to Contractors and Bonding Companies concerning a Project's complexity and size only. THESE BRACKETS SHOULD NOT BE USED IN PREPARING A BID, NOR WILL THESE BRACKETS HAVE ANY BEARING ON THE DECISION TO AWARD ANY CONTRACT.


003 . IM-I085(335) , MACON 007 . ACSTPAA-1702(904) , BALDWIN
010 . BHP-0182(501) , BALDWIN 012 . BRZ-0800(217) , CALHOUN
013 . BRZ-6500(207) , WASHINGTON 015 . ER-8910(958) , WILCOX
017 . HSIP-0017(540) , LAMAR 018 . HSIP-0171(508) , TUSCALOOSA
020 . SRTS-SR09(916) , MARSHALL 022 . STPAA-0017(536) , MARION
*025 . STPNU-CN11(201) , LAUDERDALE 026 . EB-CN11(203) , PIKE
028 . STPOA-0417(200) , BIBB 029 . STPOA-0518(201) , BLOUNT
* 030. STPOA-1404(201) , CLAY 031 . STPOA-1910(200) , COOSA*
032 . STPOA-2603(204) , ELMORE 034 . EB-4020(201) , LAWRENCE*
035 . EB-4220(201) , LIMESTONE 036 . EB-5408(200) , PICKENS
037 . STPOA-6021(200) , SUMTER* 038 . STPOA-6721(201) , WINSTON*
042 . 99-304-416-169-101 , LEE, etc.

* - WITHDRAWN FROM LETTING


003 . IM-I085(335) MACON COUNTY

LENGTH: 0.08 MILES.

WORKING DAYS: 45
COST OF PLANS: $ 9.00

for constructing the Slide Repair along the I-85 northbound outside shoulder at MP 43.2 northeast of Tuskegee. Length 0.075 mi.

BRACKET ESTIMATE: $315,000 TO $385,000

VIEW ITEMS

Return To: Top of this Page


007 . ACSTPAA-1702(904) BALDWIN COUNTY

SHALL BE COMPLETED BY: June 22, 2014
DBE CONTRACT OBLIGATION: 10 % COST OF PLANS: $238

for constructing the Grade, Drainage, Pavement, Bridges and Bridge Culverts on CR-83 (Baldwin Beach Express) from CR-32 (Dixie Road) to SR-16 (US-90) east of Robertsdale. Length 6.734 mi.

BRACKET ESTIMATE: $34,700,000 TO $42,440,000

VIEW ITEMS

Return To: Top of this Page


010 . BHP-0182(501) BALDWIN COUNTY

LENGTH: 0.49 MILES.

WORKING DAYS: 110
COST OF PLANS: $23.00

for the Bridge Coating on SR-182 at Perdido Pass in Orange Beach. Length 0.491 mi.

BRACKET ESTIMATE: $2,940,000 TO $3,600,000

VIEW ITEMS

Return To: Top of this Page


012 . BRZ-0800(217) CALHOUN COUNTY

LENGTH: 0.15 MILES.

WORKING DAYS: 75
COST OF PLANS: $ 7.00

for constructing the Bridge Replacement (Bridge Culvert) and Approaches on Alexandria-Wellington Road at a tributary to Tallasseehatchee Creek south of Wellington. Length 0.150 mi.

BRACKET ESTIMATE: $345,000 TO $420,000

VIEW ITEMS

Return To: Top of this Page


013 . BRZ-6500(207) WASHINGTON COUNTY

LENGTH: 0.04 MILES.

WORKING DAYS: 70
COST OF PLANS: $ 6.00

for constructing the Bridge Replacement (Precast) on CR-5 at Taylors Creek south of Millry. Length 0.038 mi.

BRACKET ESTIMATE: $440,000 TO $540,000

VIEW ITEMS

Return To: Top of this Page


015 . ER-8910(958) WILCOX COUNTY

LENGTH: 0.09 MILES.

WORKING DAYS: 60
COST OF PLANS: $10.00

for constructing the Slide Correction on SR-41 from 2.697 miles south of the Dallas County line to 1.396 miles north of CR-49 northeast of Camden. Length 0.094 mi.

BRACKET ESTIMATE: $176,000 TO $215,000

VIEW ITEMS

Return To: Top of this Page


017 . HSIP-0017(540) & 99-305-381-017-102 LAMAR COUNTY

LENGTH: 4.10 MILES.

WORKING DAYS: 45
COST OF PLANS: $ 9.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-17 from the south city limits of Vernon to north of L Oakes Drive. Length 2.046 mi.

BRACKET ESTIMATE: $874,000 TO $1,070,000

VIEW ITEMS

Return To: Top of this Page


018 . HSIP-0171(508) ,HSIP-0171(511) & 99-305-632-171-101 TUSCALOOSA COUNTY

LENGTH: 13.72 MILES.

WORKING DAYS: 60
DBE CONTRACT OBLIGATION: 2 % COST OF PLANS: $11.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-171 from south of Mary Road (MP 4.680) north of Northport to Brownville Road (MP 13.600). Length 8.919 mi.

BRACKET ESTIMATE: $3,105,000 TO $3,850,000

VIEW ITEMS

Return To: Top of this Page


020 . SRTS-SR09(916) & SRTS-SR10(920) MARSHALL COUNTY

LENGTH: 0.67 MILES.

WORKING DAYS: 45
COST OF PLANS: $ 9.00

for constructing the Sidewalks and Lighting along Newt Parker Drive and the Sidewalks along Highland Street, Darnell Street, Collier Street, King Street and Mt. Vernon Road in Boaz. Length 0.889 mi.

BRACKET ESTIMATE: $225,000 TO $275,000

VIEW ITEMS

Return To: Top of this Page


022 . STPAA-0017(536) MARION COUNTY

WORKING DAYS: 60
DBE CONTRACT OBLIGATION: 4 % COST OF PLANS: $15.00

for constructing the Bridge Abutment Fill Replacement and Resurfacing on SR-17 at Bear Creek in and north of Hackleburg. Length 2.275 mi.

BRACKET ESTIMATE: $920,000 TO $1,125,000

VIEW ITEMS

Return To: Top of this Page


025 . STPNU-CN11(201) LAUDERDALE COUNTY

LENGTH: 6.30 MILES.

WORKING DAYS: 30
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 4.00

for constructing the Resurfacing and Traffic Stripe on CR-14 from CR-189 at Rhodesville to CR-81 and on CR-89 from CR-115 to SR-64 at Grassy. Length 6.300 mi.

BRACKET ESTIMATE: $610,000 TO $740,000

* *WITHDRAWN FROM THE LETTING**

Return To: Top of this Page


026 . EB-CN11(203) PIKE COUNTY

LENGTH: 3.32 MILES.

WORKING DAYS: 45
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 2.00

for constructing the Planing, Resurfacing and Traffic Stripe on CR-3304 from SR-87 at Mossy Grove to SR-53 (US-231). Length 5.999 mi.

BRACKET ESTIMATE: $455,000 TO $555,000

VIEW ITEMS

Return To: Top of this Page


028 . STPOA-0417(200) BIBB COUNTY

LENGTH: 4.21 MILES.

WORKING DAYS: 45
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 4.00

for constructing the Resurfacing and Traffic Stripe on CR-10 from CR-65 through Marvel to the Shelby County line. Length 4.214 mi.

BRACKET ESTIMATE: $775,000 TO $950,000

VIEW ITEMS

Return To: Top of this Page


029 . STPOA-0518(201) BLOUNT COUNTY

LENGTH: 7.12 MILES.

WORKING DAYS: 120
DBE CONTRACT OBLIGATION: 4 % COST OF PLANS: $25.00

for constructing the Resurfacing, Traffic Stripe and Drainage Improvements on CR-1 from SR-53 (US-231) in Cleveland to SR-75 in Allgood. Length 7.133 mi.

BRACKET ESTIMATE: $935,000 TO $1,140,000

VIEW ITEMS

Return To: Top of this Page


030 . STPOA-1404(201) CLAY COUNTY

LENGTH: 6.30 MILES.

WORKING DAYS: 40
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 4.00

for constructing the Resurfacing and Traffic Stripe on CR-5 from the Tallapoosa county line to Bluff Valley Road southwest of Bluff Springs. Length 6.299 mi.

BRACKET ESTIMATE: $660,000 TO $800,000

* *WITHDRAWN FROM THE LETTING**

Return To: Top of this Page


031 . STPOA-1910(200) COOSA COUNTY

LENGTH: 9.69 MILES.

WORKING DAYS: 30
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 4.00

for constructing the Resurfacing and Traffic Stripe on CR-49 from SR-21 (US-231) in Hanover to CR-511. Length 8.692 mi.

BRACKET ESTIMATE: $1,100,000 TO $1,280,000

* *WITHDRAWN FROM THE LETTING**

Return To: Top of this Page


032 . STPOA-2603(204) ELMORE COUNTY

LENGTH: 6.29 MILES.

WORKING DAYS: 30
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 4.00

for constructing the Resurfacing and Traffic Stripe on Redland Road from Marshell Road east of Wetumpka to Friendship Road. Length 6.291 mi.

BRACKET ESTIMATE: $730,000 TO $890,000

VIEW ITEMS

Return To: Top of this Page


034 . EB-4020(201) LAWRENCE COUNTY

LENGTH: 4.29 MILES.

WORKING DAYS: 30
COST OF PLANS: $ 4.00

for constructing the Resurfacing, Traffic Stripe and Signing on CR-81, CR-207 and CR-203 from SR-157 to CR-87 at Five Points. Length 4.285 mi.

BRACKET ESTIMATE: $340,000 TO $415,000

* *WITHDRAWN FROM THE LETTING**

Return To: Top of this Page


035 . EB-4220(201) LIMESTONE COUNTY

LENGTH: 3.04 MILES.

WORKING DAYS: 30
COST OF PLANS: $ 4.00

for constructing the Resurfacing and Traffic Stripe on Easter Ferry Road from Dupree Hollow Road to the Elk River bridge west of Elkmont. Length 2.914 mi.

BRACKET ESTIMATE: $385,000 TO $470,000

VIEW ITEMS

Return To: Top of this Page


036 . EB-5408(200) PICKENS COUNTY

LENGTH: 3.63 MILES.

WORKING DAYS: 45
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 6.00

for constructing the Resurfacing and Traffic Stripe on CR-35 from 0.217 miles south of CR-37 through McShan to CR-30. Length 3.627 mi.

BRACKET ESTIMATE: $623,000 TO $762,000

VIEW ITEMS

Return To: Top of this Page


037 . STPOA-6021(200) SUMTER COUNTY

LENGTH: 4.50 MILES.

WORKING DAYS: 60
DBE CONTRACT OBLIGATION: 2 % COST OF PLANS: $ 5.00

for constructing the Full Depth Reclamation, Resurfacing and Traffic Stripe on CR-85 from CR-35 to CR-34 at Warsaw. Length 4.500 mi.

BRACKET ESTIMATE: $985,000 TO $1,200,000

* *WITHDRAWN FROM THE LETTING**

Return To: Top of this Page


038 . STPOA-6721(201) WINSTON COUNTY

LENGTH: 1.36 MILES.

WORKING DAYS: 30
COST OF PLANS: $ 3.00

for constructing the Surface Treatment and Traffic Stripe on CR-14 (Sardis Airport Road) from CR-39 to the Cullman county line northwest of Addison. Length 1.360 mi.

BRACKET ESTIMATE: $130,000 TO $160,000

**  WITHDRAWN FROM LETTING **

Return To: Top of this Page


042 . 99-304-416-169-101 & 99-304-576-169-101 LEE & RUSSELL COUNTIES

LENGTH: 20.58 MILES.

WORKING DAYS: 30
COST OF PLANS: $ 3.00

for constructing the Resurfacing and Traffic Stripe on SR-169 from CR-175 (Meadows Mill Road) to SR-51 (Marvyn Parkway) in Opelika and from SR-1 (US-431) in Seale to SR-8 (US-80) in Crawford. Length 19.623 mi.

BRACKET ESTIMATE: $1,080,000 TO $1,325,000

VIEW ITEMS

Return To: Top of this Page