Proposal Letting List
December 07, 2012 Transportation Letting

Welcome to the Proposal Letting List Page. You may view the approximate items of work for each proposal in the Letting by clicking on the View Items hyperlink to view the Project Item Pages. Please take a minute to review these pages and e-mail us with your comments.


The Bracket Ranges shown herein are to provide general financial information to Contractors and Bonding Companies concerning a Project's complexity and size only. THESE BRACKETS SHOULD NOT BE USED IN PREPARING A BID, NOR WILL THESE BRACKETS HAVE ANY BEARING ON THE DECISION TO AWARD ANY CONTRACT.


001 . IM-I065(412) , CONECUH 002 . IM-NHF-I020(339) , CLEBURNE *
006 . BRF-0020(509) , LAWRENCE 007 . BRF-0008(528) , MARENGO
010 . NHF-I085(327) , MONTGOMERY 014 . ACBRZ55194-ATRP(001) , CHAMBERS
015 . ACNU58562-ATRP(001) , PIKE 016 . ACBRZ58393-ATRP(001) , LAUDERDALE
017 . ACNU58306-ATRP(001) , MOBILE 018 . ACNU58392-ATRP(001) , CLAY
019 . ACNU58416-ATRP(001) , LEE 020 . ACNU58471-ATRP(001) , MONROE
021 . ACNU58477-ATRP(001) , GREENE 022 . ACNU58624-ATRP(001) , CULLMAN
023 . ACNU58625-ATRP(001) , CULLMAN 024 . ACOA58387-ATRP(001) , COLBERT
025 . ACOA58683-ATRP(001) , HOUSTON 026 . ACNU58506-ATRP(001) , BARBOUR
030 . BR-0004(505) , ST. CLAIR 032 . BR-7004(601) , JEFFERSON
033 . BR-0026(501) , RUSSELL 043 . NH-0003(575) , ESCAMBIA
045 . NH-0009(549) , CHEROKEE 046 . NH-0013(575) , FAYETTE
047 . NH-HSIP-0006(544) , CHILTON 060 . STPAA-0016(512) , BALDWIN
061 . STPAA-0117(509) , JACKSON 062 . STPAA-HSIP-0188(502) , MOBILE
063 . STPAA-HSIP-0193(504) , MOBILE 065 . STPAA-HSIP-0015(520) , PIKE
070 . STPNU-2649(200) , ELMORE 071 . STPNU-6717(200) , WINSTON
075 . STPOA-4114(200) , LEE 076 . STPOA-5012(200) , MONROE
081 . TCSP-11AL(001) , LEE 090 . ST-002-181-010 , BALDWIN *
091 . ST-047-013-001 , MARION

**WITHDRAWN FROM THE LETTING**


001 . IM-I065(412) CONECUH COUNTY

LENGTH: 10.27 MILES.

SHALL BE COMPLETED BY: September 1, 2014
DBE CONTRACT OBLIGATION: 5 % COST OF PLANS: $72.00

for constructing the Planing, Resurfacing, Traffic Stripe, Drainage and Guardrail on I-65 from near CR-6 to Murder Creek in Evergreen. Length 10.268 mi.

BRACKET ESTIMATE: $15,400,000 TO $18,800,000

VIEW ITEMS


002 . IM-NHF-I020(339) CLEBURNE COUNTY

LENGTH: 4.29 MILES.

SHALL BE COMPLETED BY: May 1, 2015
DBE CONTRACT OBLIGATION: 8 % COST OF PLANS: $110

for constructing the Additional Lanes (Grade, Drainage, Pavement, Lighting and Signing) on I-20 from SR-46 in Heflin to west of the Tallapoosa River. Length 4.290 mi.

BRACKET ESTIMATE: $26,775,000 TO $32,725,000

**WITHDRAWN FROM THE LETTING**


006 . BRF-0020(509) LAWRENCE COUNTY

LENGTH: 1.07 MILES.

WORKING DAYS: 285
DBE CONTRACT OBLIGATION: 8 % COST OF PLANS: $47.00

for constructing the Bridge Replacements (Dual) and Approaches on SR-20 (Alt. US-72) at Fox Creek east of Hillsboro. Length 1.065 mi.

BRACKET ESTIMATE: $4,920,000 TO $6,000,000

VIEW ITEMS


007 . BRF-0008(528) MARENGO COUNTY

LENGTH: 1.00 MILES.

WORKING DAYS: 180
DBE CONTRACT OBLIGATION: 8 % COST OF PLANS: $44.00

for constructing the Bridge Replacement (WBR) and Approaches on SR-8 (US-80) at French Creek east of Demopolis. Length 1.003 mi.

BRACKET ESTIMATE: $3,720,000 TO $4,540,000

VIEW ITEMS


010 . NHF-I085(327) MONTGOMERY COUNTY
SHALL BE COMPLETED BY: April 15, 2015
DBE CONTRACT OBLIGATION: 7 % COST OF PLANS: $96.00

for constructing the Interchange Improvements (Bridge Widening, Additional Lanes and Traffic Signals) on I-85 at Perry Hill Road (Exit 4) in Montgomery. Length 0.814 mi.

BRACKET ESTIMATE: $5,800,000 TO $7,000,000

VIEW ITEMS


014 . ACBRZ55194-ATRP(001) CHAMBERS COUNTY

LENGTH: 0.21 MILES.

WORKING DAYS: 90
COST OF PLANS: $ 5.00

for constructing the Bridge Replacement (Precast) and Approaches on CR-11 at Sandy Creek north of Waverly. Length 0.236 mi.

BRACKET ESTIMATE: $590,000 TO $724,000

VIEW ITEMS


015 . ACNU58562-ATRP(001) & ACBR58557-ATRP(001) PIKE COUNTY

LENGTH: 7.46 MILES.

WORKING DAYS: 120
DBE CONTRACT OBLIGATION: 4 % COST OF PLANS: $13.00

for constructing the Planing, Resurfacing, Traffic Stripe and Bridge Replacement on CR-2201 and on CR-2214 at sites as indicated by the plans. Length 7.453 mi.

BRACKET ESTIMATE: $1,500,000 TO $1,800,000

VIEW ITEMS


016 . ACBRZ58393-ATRP(001) LAUDERDALE COUNTY

LENGTH: 0.08 MILES.

WORKING DAYS: 120
COST OF PLANS: $ 4.00

for constructing the Bridge Rehabilitation (Pile Encasement) on CR-70 at Anderson Creek east of Rogersville. Length 0.076 mi.

BRACKET ESTIMATE: $363,000 TO $444,000

VIEW ITEMS


017 . ACNU58306-ATRP(001) MOBILE COUNTY

LENGTH: 12.25 MILES.

WORKING DAYS: 130
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 4.00

for constructing the Planing, Resurfacing and Traffic Stripe on CR-96 (Beverly Jefferies Hwy and Prine Road) at sites as indicated by the plans. Length 12.250 mi.

BRACKET ESTIMATE: $2,300,000 TO $2,830,000

VIEW ITEMS


018 . ACNU58392-ATRP(001) CLAY COUNTY

LENGTH: 4.96 MILES.

WORKING DAYS: 40
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 3.00

for constructing the Resurfacing and Traffic Stripe on CR-66 from SR-49 at Union to SR-9 at Needmore. Length 4.955 mi.

BRACKET ESTIMATE: $510,000 TO $620,000

VIEW ITEMS


019 . ACNU58416-ATRP(001) LEE COUNTY

LENGTH: 7.18 MILES.

WORKING DAYS: 45
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 4.00

for constructing the Planing, Resurfacing and Traffic Stripe on CR-240 from SR-169 to CR-592 south of Smiths Station. Length 7.177 mi.

BRACKET ESTIMATE: $1,685,000 TO $2,000,000

VIEW ITEMS


020 . ACNU58471-ATRP(001) MONROE COUNTY

LENGTH: 7.36 MILES.

WORKING DAYS: 30
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 3.00

for constructing the Resurfacing and Traffic Stripe on CR-20 from the Monroeville city limits to CR-5. Length 7.363 mi.

BRACKET ESTIMATE: $1,080,000 TO $1,320,000

VIEW ITEMS


021 . ACNU58477-ATRP(001) & STPNU-3201(201) GREENE COUNTY

LENGTH: 15.46 MILES.

WORKING DAYS: 50
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 6.00

for constructing the Resurfacing and Traffic Stripe on CR-20 from CR-72 through Boligee to CR-117. Length 15.454 mi.

BRACKET ESTIMATE: $2,590,000 TO $3,170,000

VIEW ITEMS


022 . ACNU58624-ATRP(001) CULLMAN COUNTY

LENGTH: 1.56 MILES.

WORKING DAYS: 45
COST OF PLANS: $ 3.00

for constructing the Resurfacing and Traffic Stripe on CR-222 from SR-69S north of Bremen to CR-109. Length 1.555 mi.

BRACKET ESTIMATE: $240,000 TO $290,000

VIEW ITEMS


023 . ACNU58625-ATRP(001) CULLMAN COUNTY

LENGTH: 0.98 MILES.

WORKING DAYS: 45
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 3.00

for constructing the Resurfacing and Traffic Stripe on CR-222 from east of CR-310 to CR-410 east of Good Hope. Length 0.980 mi.

BRACKET ESTIMATE: $440,000 TO $535,000

VIEW ITEMS


024 . ACOA58387-ATRP(001) COLBERT COUNTY
WORKING DAYS: 45
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 4.00

for constructing the Planing, Resurfacing and Traffic Stripe on Avalon Avenue from US-43 (Woodward Avenue) to SR-133 (Wilson Dam Road) in Muscle Shoals. Length 1.739 mi.

BRACKET ESTIMATE: $555,000 TO $675,000

VIEW ITEMS


025 . ACOA58683-ATRP(001) HOUSTON COUNTY

LENGTH: 0.81 MILES.

WORKING DAYS: 45
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 6.00

for constructing the Resurfacing and Traffic Stripe on Range Street from Spring Street to Ross Clark Circle (US-84) in Dothan. Length 0.805 mi.

BRACKET ESTIMATE: $532,000 TO $650,000

VIEW ITEMS


026 . ACNU58506-ATRP(001) & ACNU58505-ATRP(001) BARBOUR COUNTY

LENGTH: 15.32 MILES.

WORKING DAYS: 40
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 3.00

for constructing the Resurfacing and Traffic Stripe on CR-33 and on Clio Short Road (CR-9) at sites as indicated by the plans. Length 15.328 mi.

BRACKET ESTIMATE: $1,605,000 TO $1,960,000

VIEW ITEMS


030 . BR-0004(505) ST. CLAIR COUNTY

LENGTH: 0.09 MILES.

WORKING DAYS: 70
DBE CONTRACT OBLIGATION: 5 % COST OF PLANS: $11.00

for constructing the Bridge Replacement (Bridge Culvert) and Approaches on SR-4 (US-78) at Cane Creek southeast of Cooks Springs. Length 0.087 mi.

BRACKET ESTIMATE: $970,000 TO $1,190,000

VIEW ITEMS


032 . BR-7004(601) JEFFERSON COUNTY

LENGTH: 0.07 MILES.

WORKING DAYS: 160
DBE CONTRACT OBLIGATION: 5 % COST OF PLANS: $12.00

for constructing the Bridge Replacement on CR-55 (Dickey Springs Road) at Shades Creek near Greenwood. Length 0.067 mi.

BRACKET ESTIMATE: $1,315,000 TO $1,600,000

VIEW ITEMS


033 . BR-0026(501) RUSSELL COUNTY
WORKING DAYS: 250
DBE CONTRACT OBLIGATION: 6 % COST OF PLANS: $39.00

for constructing the Bridge Replacement (Bridge Culvert) and Approaches on SR-29 at Hatchechubbee Creek and at High Log Creek in Hatchechubbee. Length 0.519 mi.

BRACKET ESTIMATE: $3,000,000 TO $4,000,000

VIEW ITEMS


043 . NH-0003(575) ESCAMBIA COUNTY

LENGTH: 2.23 MILES.

WORKING DAYS: 30
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 4.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-3 (US-31) from west of SR-113 (US-29) (MP 55.300) in Flomaton to south of the railroad overpass (57.535). Length 2.234 mi.

BRACKET ESTIMATE: $670,000 TO $820,000

VIEW ITEMS


045 . NH-0009(549) CHEROKEE COUNTY

LENGTH: 4.90 MILES.

WORKING DAYS: 30
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 5.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-9 from north of SR-35 (MP 268.200) to the Georgia state line. Length 4.900 mi.

BRACKET ESTIMATE: $675,000 TO $825,000

VIEW ITEMS


046 . NH-0013(575) FAYETTE COUNTY

LENGTH: 5.92 MILES.

WORKING DAYS: 35
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 5.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-13 from SR-102 at Fowlers Crossroads to the Walker county line. Length 5.916 mi.

BRACKET ESTIMATE: $930,000 TO $1,140,000

VIEW ITEMS


047 . NH-HSIP-0006(544) CHILTON COUNTY

LENGTH: 8.32 MILES.

WORKING DAYS: 55
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 5.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-6 (US-82) from the Bibb county line through Maplesville to east of Mulberry Creek (MP 106.885). Length 8.011 mi.

BRACKET ESTIMATE: $1,550,000 TO $1,900,000

VIEW ITEMS


060 . STPAA-0016(512) BALDWIN COUNTY

LENGTH: 6.21 MILES.

WORKING DAYS: 45
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 3.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-16 (US-90) from SR-181 (MP 48.091) to SR-59 in Loxley. Length 6.210 mi.

BRACKET ESTIMATE: $1,110,000 TO $1,350,000

VIEW ITEMS


061 . STPAA-0117(509) JACKSON COUNTY

LENGTH: 6.02 MILES.

WORKING DAYS: 35
DBE CONTRACT OBLIGATION: 4 % COST OF PLANS: $ 6.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-117 from near CR-114 (MP 30.912) to SR-2 (US-72) at Stevenson. Length 6.018 mi.

BRACKET ESTIMATE: $1,235,000 TO $1,505,000

VIEW ITEMS


062 . STPAA-HSIP-0188(502) MOBILE COUNTY

LENGTH: 11.08 MILES.

WORKING DAYS: 65
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 4.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-188 from CR-19 to SR-193 at Alabama Port. Length 11.077 mi.

BRACKET ESTIMATE: $1,680,000 TO $2,000,000

VIEW ITEMS


063 . STPAA-HSIP-0193(504) MOBILE COUNTY

LENGTH: 14.48 MILES.

WORKING DAYS: 70
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 4.00

for constructing the Resurfacing and Traffic Stripe on SR-193 from the north end of the Dauphin Island bridge to CR-24 (Laurendine Road) south of Mobile. Length 14.477 mi.

BRACKET ESTIMATE: $2,100,000 TO $2,500,000

VIEW ITEMS


065 . STPAA-HSIP-0015(520) PIKE COUNTY

LENGTH: 7.47 MILES.

WORKING DAYS: 85
DBE CONTRACT OBLIGATION: 4 % COST OF PLANS: $19.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-15 from east of CR-7 (Needmore Road) to SR-93 in Banks. Length 7.469 mi.

BRACKET ESTIMATE: $2,060,000 TO $2,520,000

VIEW ITEMS


070 . STPNU-2649(200) ELMORE COUNTY

LENGTH: 2.72 MILES.

WORKING DAYS: 30
COST OF PLANS: $ 3.00

for constructing the Resurfacing and Traffic Stripe on CR-161 (Little Road) from the Tallassee city limits to SR-229. Length 2.715 mi.

BRACKET ESTIMATE: $320,000 TO $390,000

VIEW ITEMS


071 . STPNU-6717(200) WINSTON COUNTY

LENGTH: 3.93 MILES.

WORKING DAYS: 40
DBE CONTRACT OBLIGATION: 2 % COST OF PLANS: $ 3.00

for constructing the Full Depth Reclamation, Surface Treatment and Traffic Stripe on CR-2 from east of SR-74 (US-278) east of Double Springs to CR-18. length 3.936 mi.

BRACKET ESTIMATE: $535,000 TO $655,000

VIEW ITEMS


075 . STPOA-4114(200) LEE COUNTY

LENGTH: 2.73 MILES.

WORKING DAYS: 45
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 3.00

for constructing the Resurfacing and Traffic Stripe on CR-391 from the Opelika city limits to US-280/431. Length 2.734 mi.

BRACKET ESTIMATE: $430,000 TO $526,000

VIEW ITEMS


076 . STPOA-5012(200) MONROE COUNTY

LENGTH: 5.13 MILES.

WORKING DAYS: 30
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 3.00

for constructing the Resurfacing and Traffic Stripe on CR-42 from east of SR-21 to CR-5 northeast of Monroeville. Length 5.128 mi. Length 5.128 mi.

BRACKET ESTIMATE: $1,170,000 TO $1,430,000

VIEW ITEMS


081 . TCSP-11AL(001) LEE COUNTY
WORKING DAYS: 75
COST OF PLANS: $10.00

for constructing the Streetscaping on North Railroad Avenue from Sixth Street to Eighth Street in Opelika. Length 0.179 mi.

BRACKET ESTIMATE: $440,000 TO $535,000

VIEW ITEMS


090 . ST-002-181-010 BALDWIN COUNTY
WORKING DAYS: 75
COST OF PLANS: $28.00

for constructing the Additional Lane (Grade, Drainage and Pavement) on SR-181 from south of CR-48 in Fairhope to south of CR-30. Length 1.188 mi.

BRACKET ESTIMATE: $740,000 TO $900,000

**WITHDRAWN FROM THE LETTING**

091 . ST-047-013-001 MARION COUNTY

LENGTH: 0.90 MILES.

WORKING DAYS: 110
COST OF PLANS: $33.00

for constructing the Roadway and Drainage Improvements on SR-13 in Bear Creek at sites as indicated by the plans. Length 0.896 mi.

BRACKET ESTIMATE: $900,000 TO $1,100,000

VIEW ITEMS


Return To: Top of this Page