041 . STPNU-1600(225), COFFEE 041 . STPNU-1600(225) , COFFEE

COUNTY: COFFEE

WORKING DAYS: 60

MBE/DBE CONTRACT OBLIGATION: 3 %
for constructing the Resurfacing and Traffic Stripe on CR-223 from SR-167 to SR-125 in Victoria. Length 4.366 mi.

The Bracket Ranges shown herein are to provide general financial information to Contractors and Bonding Companies concerning a Project's complexity and size only. THESE BRACKETS SHOULD NOT BE USED IN PREPARING A BID, NOR WILL THESE BRACKETS HAVE ANY BEARING ON THE DECISION TO AWARD ANY CONTRACT.

BRACKET ESTIMATE: $609,000 TO $744,000


THE PRINCIPAL ITEMS OF WORK ARE APPROXIMATELY AS FOLLOWS:

ITEM CODE QUANTITY UNIT ITEM DESCRIPTION
210D021 3416 CUYD Borrow Excav (Lse Trb Meas)(A-4 Better)
212A000 461 STA Machine Grading Shoulders
405A000 3228 GAL Tack Coat
407B000 5 MILE Joint Sealant For Hot Mix Asphalt Pave
424A341 4438 TON Superpave Wrg Surf 3/4" ESAL A/B
424A346 2049 TON Superpave Wrg Surf Lev 1/2" ESAL A/B
424B641 375 TON Superpave Upr Bndr Pat 11/2" ESAL A/B
424B648 897 TON Superpave Upr Bndr Wide 11/2" Esal A/B
600A000 1 LS Mobilization
652A100 9 ACRE Seeding
656A010 9 ACRE Mulching
665F000 50 EACH Hay Bales
665J002 1000 LF Silt Fence
665O001 1000 LF Silt Fence Removal
698A000 1 LS Construction Fuel (Maximum Bid Limited 31,320.00).
701C000 4 MILE Broken Temporary Traffic Stripe
701C001 12 MILE Solid Temporary Traffic Stripe
703D001 70 SQFT Temporary Traffic Control Markings
740B000 417 SQFT Construction Signs
740O000 1 EACH Pilot Car