010 . BRZ-CN12(218) , BULLOCK

COUNTY: BULLOCK

WORKING DAYS: 60

for constructing the Bridge Rehabilitation and Guardrail Installation on CR-87 and on CR-177 at various sites as indicated by the plans. Length 0.245 mi.

The Bracket Ranges shown herein are to provide general financial information to Contractors and Bonding Companies concerning a Project's complexity and size only. THESE BRACKETS SHOULD NOT BE USED IN PREPARING A BID, NOR WILL THESE BRACKETS HAVE ANY BEARING ON THE DECISION TO AWARD ANY CONTRACT.

BRACKET ESTIMATE: $517,000 TO $630,000


THE PRINCIPAL ITEMS OF WORK ARE APPROXIMATELY AS FOLLOWS:

ITEM CODE QUANTITY UNIT ITEM DESCRIPTION
201A002 1 LS Clear & Grub (Maximum Allowable Bid $ 4,000.00/Acre) (Approximately 2 Acres)
206D001 928 LF Removing Guardrail
210D001 3125 CUYD Borrow Excavation (Loose Truckbed Meas)
504G001 554 LF Steel Piling Encasement Dry Condition
512G000 1 EACH Precast Conc Abut Wing Cap Panels
600A000 1 LS Mobilization
610C001 3600 TON Loose Riprap Class 2
610D003 2640 SQYD Filter Blanket Geotextile
630A004 760 LF Steel Beam Guardrail, Cl B, Ty 2
630C022 24 EACH Guardrail End Anchor, Type Special
630C070 24 EACH Guardrail End Anchor, Type 10 Series
636A000 246 LF Barbed Wire Fence, 4 Strands, 4' High
652A100 1 ACRE Seeding
656A010 1 ACRE Mulching
665F000 240 EACH Hay Bales
665J002 2400 LF Silt Fence
665O001 2400 LF Silt Fence Removal
698A000 1 LS Construction Fuel (Maximum Bid Limited 16,350.00)
740B000 96 SQFT Construction Signs
740E000 25 EACH Cones (36" High)
740M001 25 EACH Ballast For Cone