023 . HRRR-1901(203) , COOSA

COUNTY: COOSA

WORKING DAYS: 30

for the Traffic Stripe and Pavement Markers on CR-29 from SR-22 at Kellys Crossroads to CR-56 at Weogufka. Length 14.260 mi.

The Bracket Ranges shown herein are to provide general financial information to Contractors and Bonding Companies concerning a Project's complexity and size only. THESE BRACKETS SHOULD NOT BE USED IN PREPARING A BID, NOR WILL THESE BRACKETS HAVE ANY BEARING ON THE DECISION TO AWARD ANY CONTRACT.

BRACKET ESTIMATE: $120,000 TO $150,000


THE PRINCIPAL ITEMS OF WORK ARE APPROXIMATELY AS FOLLOWS:

ITEM CODE QUANTITY UNIT ITEM DESCRIPTION
600A000 1 LS Mobilization
701A231 29 MILE Solid White Cl 2 Ty A Traf Str
701A235 26 MILE Solid Yellow Cl 2 Ty A Traf Str
701A245 3 MILE Broken Yellow Cl 2 Ty A Traf Str
705A032 118 EACH Pavement Markers, Class A-H, Type 1-B
705A037 1621 EACH Pavement Markers, Class A-H, Type 2-D