Proposal Letting List
May 25, 2012 Transportation Letting

Welcome to the Proposal Letting List Page. You may view the approximate items of work for each proposal in the Letting by clicking on the View Items hyperlink to view the Project Item Pages. Please take a minute to review these pages and e-mail us with your comments.


If you would like to order Plans, Proposals, Diskettes, Specification Standard Drawings, please use the ALDOT Order Form ; . THANKS !!!


The Bracket Ranges shown herein are to provide general financial information to Contractors and Bonding Companies concerning a Project's complexity and size only. THESE BRACKETS SHOULD NOT BE USED IN PREPARING A BID, NOR WILL THESE BRACKETS HAVE ANY BEARING ON THE DECISION TO AWARD ANY CONTRACT.


002 . IM-STPOAF-I059(346) , TUSCALOOSA 003 . IM-I059(352) , DEKALB
004 . IM-I065(430) , MORGAN, etc. 009 . BRF-0077(500) , TALLADEGA
015 . NHF-0001(573) , MADISON 016 . NHF-0038(529) , JEFFERSON, etc.
019 . BRZ-0200(214) , BALDWIN 023 . EB-0025(534) , SHELBY
030 . HRRR-3104(200) , GENEVA 032 . HSIP-0042(521) , BALDWIN
034 . HSIP-CN12(906) , BARBOUR, etc. 036 . NH-0001(574) , CALHOUN
037 . NH-0006(543) , ELMORE, etc. 043 . SRTS-SR12(900) , MOBILE
050 . STPAA-0003(569) , ESCAMBIA 053 . STPAA-0015(519) , ESCAMBIA
054 . STPOA-0017(545) , MARION 056 . STPOA-HSIP-0014(528) , LEE
057 . STPAA-HSIP-0070(501) , SHELBY 058 . STPAA-HSIP-0261(500) , SHELBY
060 . STPHV-8540(600) , MADISON 062 . STPNU-0116(200) , AUTAUGA
063 . STPOA-2642(201) , ELMORE 064 . STPOA-CN12(209) , DALE
066 . STPOA-0021(537) , ESCAMBIA 067 . STPOA-7909(600) , ELMORE
068 . STPOA-0900(227) , CHAMBERS 069 . STPOA-HSIP-0025(532) , MARENGO
070 . STPOA-STPNU-CN12(203) , ETOWAH

002 . IM-STPOAF-I059(346) TUSCALOOSA COUNTY
SHALL BE COMPLETED BY: October 19, 2012
COST OF PLANS: $24.00

for constructing the Bridge Raising, Resurfacing and Guardrail Replacement over I-59 at CR-1583 (Woodland Road) and at CR-566 (Clements Road) in Tuscaloosa. Length 0.169 mi.

BRACKET ESTIMATE: $822,000 TO $1,000,000

VIEW ITEMS


003 . IM-I059(352) DEKALB COUNTY

LENGTH: 0.87 MILES.

SHALL BE COMPLETED BY: June 29, 2013
COST OF PLANS: $10.00

for constructing the Interchange Lighting on I-59 at the 49th Street interchange in Fort payne. Length 0.867 mi.

BRACKET ESTIMATE: $1,030,000 TO $1,260,000

VIEW ITEMS


004 . IM-I065(430) MORGAN & LIMESTONE COUNTIES

LENGTH: 1.89 MILES.

WORKING DAYS: 20
COST OF PLANS: $ 2.00

for constructing the Bridge Deck Overlay, Spall Repair and Traffic Stripe on I-65 at the Tennessee River bridges east of Decatur. Length 1.887 mi.

BRACKET ESTIMATE: $7,475,000 TO $9,100,000

VIEW ITEMS


009 . BRF-0077(500) TALLADEGA COUNTY
WORKING DAYS: 190
DBE CONTRACT OBLIGATION: 8 % COST OF PLANS: $45.00

for constructing the Bridge Replacement and Approaches on SR-77 at the Norfolk-Southern Railroad in Lincoln. Length 0.672 mi.

BRACKET ESTIMATE: $3,050,000 TO $3,700,000

VIEW ITEMS


015 . NHF-0001(573) MADISON COUNTY
SHALL BE COMPLETED BY: November 16, 2012
COST OF PLANS: $ 7.00

for constructing the Adaptive Traffic Signal Control at sixteen intersections along SR-53/ SR-1 (Governors Drive) from 14th Street to California Street in Huntsville. Length 2.9 mi.

BRACKET ESTIMATE: $830,000 TO $1,020,000

VIEW ITEMS


016 . NHF-0038(529) JEFFERSON & SHELBY COUNTIES

LENGTH: 8.60 MILES.

SHALL BE COMPLETED BY: November 16, 2012
COST OF PLANS: $ 8.00

for constructing the Adaptive Traffic Signal Control at twenty five intersections along SR-38 (US-280) from Brook Manor Drive in Mountain Brook to Doug Baker Boulevard. Length 8.6 mi.

BRACKET ESTIMATE: $1,390,000 TO $1,700,000

VIEW ITEMS


019 . BRZ-0200(214) BALDWIN COUNTY

LENGTH: 0.18 MILES.

WORKING DAYS: 80
COST OF PLANS: $12.00

for constructing the Bridge Replacement and Approaches on CR-91 at Narrow Gap Creek northwest of Lillian. Length 0.184 mi.

BRACKET ESTIMATE: $645,000 TO $790,000

VIEW ITEMS


023 . EB-0025(534) SHELBY COUNTY

LENGTH: 6.09 MILES.

WORKING DAYS: 40
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 4.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-25 from SR-53 (US-231) to CR-55 in Sterrett. Length 6.090 mi.

BRACKET ESTIMATE: $1,105,000 TO $1,350,000

VIEW ITEMS


030 . HRRR-3104(200) GENEVA COUNTY

LENGTH: 0.07 MILES.

WORKING DAYS: 30
COST OF PLANS: $ 4.00

for the Removal and Realignment of a segment of CR-4 approximately three miles southeast of SR-52 near Thurston. Length 0.068 mi.

BRACKET ESTIMATE: $55,400 TO $67,800

VIEW ITEMS


032 . HSIP-0042(521) BALDWIN COUNTY

LENGTH: 0.26 MILES.

WORKING DAYS: 30
COST OF PLANS: $10.00

for constructing the Directional Turn Lanes and Median Closings on SR-42 (US-98) from the D'Olive Creek Bridge to Van Buren Street in Daphne. Length 0.262 mi.

BRACKET ESTIMATE: $85,500 TO $104,500

VIEW ITEMS


034 . HSIP-CN12(906) BARBOUR , COFFEE , COVINGTON , CRENSHAW , DALE , GENEVA & HOUSTON COUNTIES
WORKING DAYS: 100
COST OF PLANS: $11.00

for the Scoring Bituminous Pavement Surface (Shoulders) and Traffic Stripe on various routes throughout the Seventh Division.

BRACKET ESTIMATE: $190,000 TO $230,000

VIEW ITEMS


036 . NH-0001(574) CALHOUN COUNTY

LENGTH: 6.29 MILES.

WORKING DAYS: 60
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 4.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-1 (US-431) from SR-4 (US-78) to SR-21 in Oxford. Length 6.290 mi.

BRACKET ESTIMATE: $2,025,000 TO $2,475,000

VIEW ITEMS


037 . NH-0006(543) ELMORE & AUTAUGA COUNTIES

LENGTH: 2.08 MILES.

WORKING DAYS: 40
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 3.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-6 (US-82) from east of SR-3 (US-31) (MP 142.901) in Prattville to Cobbs Ford Road. Length 2.079 mi.

BRACKET ESTIMATE: $1,595,000 TO $1,900,000

VIEW ITEMS


043 . SRTS-SR12(900) MOBILE COUNTY
WORKING DAYS: 60
COST OF PLANS: $11.00

for constructing the Sidewalks, Crosswalks, Signs and Signals at the Holloway Elementary School and the Howard Elementary School in Mobile.

BRACKET ESTIMATE: $235,000 TO $285,000

VIEW ITEMS


050 . STPAA-0003(569) ESCAMBIA COUNTY

LENGTH: 2.85 MILES.

WORKING DAYS: 40
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 4.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-3 (US-31) from Burnt Corn Creek to north of Tiger Drive (MP 71.909) in Brewton. Length 2.849 mi.

BRACKET ESTIMATE: $797,000 TO $974,000

VIEW ITEMS


053 . STPAA-0015(519) ESCAMBIA COUNTY

LENGTH: 1.25 MILES.

WORKING DAYS: 30
COST OF PLANS: $ 5.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-15 from SR-3 (US-31) in Brewton to south of SR-15 (US-29)/SR-41 on SR-41 in East Brewton. Length 1.332 mi.

BRACKET ESTIMATE: $355,000 TO $430,000

VIEW ITEMS


054 . STPOA-0017(545) MARION COUNTY
WORKING DAYS: 30
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 4.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-17 (US-43) from SR-171 to CR-1 (Lovejoy Road) in Hamilton. Length 2.707 mi.

BRACKET ESTIMATE: $1,165,000 TO $1,425,000

VIEW ITEMS


056 . STPOA-HSIP-0014(528) LEE COUNTY
WORKING DAYS: 85
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 2.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-14 from the Macon county line to SR-147 in Auburn. Length 10.133 mi.

BRACKET ESTIMATE: $3,720,000 TO $4,540,000

VIEW ITEMS


057 . STPAA-HSIP-0070(501) SHELBY COUNTY
WORKING DAYS: 45
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 4.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-70 from east of SR-3 (US-31) (MP 0.515) to west of SR-25 (MP 8.244) in Columbiana. Length 7.728 mi.

BRACKET ESTIMATE: $1,430,000 TO $1,700,000

VIEW ITEMS


058 . STPAA-HSIP-0261(500) SHELBY COUNTY
WORKING DAYS: 60
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 6.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-261 from CR-17 in Helena to SR-3 (US-31) in Pelham. Length 5.940 mi.

BRACKET ESTIMATE: $1,255,000 TO $1,530,000

VIEW ITEMS


060 . STPHV-8540(600) MADISON COUNTY

LENGTH: 0.60 MILES.

WORKING DAYS: 195
DBE CONTRACT OBLIGATION: 9 % COST OF PLANS: $39.00

for constructing the Relocation (Grade, Drainage and Pavement) of Church Street from north of Pratt Avenue to Oakwood Avenue in Huntsville. Length 0.576 mi.

BRACKET ESTIMATE: $2,755,000 TO $3,365,000

VIEW ITEMS


062 . STPNU-0116(200) AUTAUGA COUNTY

LENGTH: 11.47 MILES.

WORKING DAYS: 40
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 3.00

for constructing the Resurfacing and Traffic Stripe on CR-40 from CR-21 at Old Kingston to the Elmore county line. Length 11.468 mi.

BRACKET ESTIMATE: $1,395,000 TO $1,700,000

VIEW ITEMS


063 . STPOA-2642(201) ELMORE COUNTY

LENGTH: 2.76 MILES.

WORKING DAYS: 30
COST OF PLANS: $ 3.00

for constructing the Resurfacing and Traffic Stripe on CR-155 (Cherokee Trail) at Neman to SR-229. Length 2.757 mi.

BRACKET ESTIMATE: $310,000 TO $380,000

VIEW ITEMS


064 . STPOA-CN12(209) & STPOA-CN12(215) DALE COUNTY

LENGTH: 28.84 MILES.

WORKING DAYS: 60
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 8.00

for constructing the Resurfacing and Guardrail on various county roads at sites as indicated by the plans. Length 28.838 mi.

BRACKET ESTIMATE: $1,190,000 TO $1,450,000

VIEW ITEMS


066 . STPOA-0021(537) ESCAMBIA COUNTY

LENGTH: 2.70 MILES.

WORKING DAYS: 30
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 5.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-21 from north of Magnolia Street in Atmore (MP 0.967) to the beginning of the four-lane section north of Sunset Drive (MP 3.665). Length 2.698 mi.

BRACKET ESTIMATE: $624,000 TO $763,000

VIEW ITEMS


067 . STPOA-7909(600) ELMORE COUNTY

LENGTH: 0.99 MILES.

WORKING DAYS: 30
COST OF PLANS: $ 4.00

for constructing the Planing, Resurfacing and Traffic Stripe on CR-116 (Chapman Road) from SR-143 (Main Street) in Robinson Springs to Airport Road. Length 0.984 mi.

BRACKET ESTIMATE: $160,000 TO $195,000

VIEW ITEMS


068 . STPOA-0900(227) & STPOA-CN12(214) CHAMBERS COUNTY

LENGTH: 5.08 MILES.

WORKING DAYS: 45
DBE CONTRACT OBLIGATION: 2 % COST OF PLANS: $ 5.00

for constructing the Full Depth Reclamation, Resurfacing and Traffic Stripe on CR-104 from CR-237 to the Randolph county line and on CR-186 from CR-299 to SR-50 west of Valley. Length 5.089 mi.

BRACKET ESTIMATE: $772,000 TO $943,000

VIEW ITEMS


069 . STPOA-HSIP-0025(532) MARENGO COUNTY

LENGTH: 6.60 MILES.

WORKING DAYS: 40
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 6.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-25 from south of CR-59 (MP 30.354) to the Hale county line. Length 6.590 mi.

BRACKET ESTIMATE: $1,295,000 TO $1,600,000

VIEW ITEMS


070 . STPOA-STPNU-CN12(203) ETOWAH COUNTY

LENGTH: 10.83 MILES.

WORKING DAYS: 45
DBE CONTRACT OBLIGATION: 4 % COST OF PLANS: $ 4.00

for constructing the Resurfacing and Traffic Stripe on CR-24 (Gallant Road) from the Saint Clair county line to SR-74 (US-278). Length 10.785 mi.

BRACKET ESTIMATE: $1,405,000 TO $1,720,000

VIEW ITEMS


Return To: Top of this Page