COUNTY: CHEROKEE
WORKING DAYS: 45
MBE/DBE CONTRACT OBLIGATION: 3 %
for constructing the Resurfacing and Traffic Stripe on CR-19 from CR-39 to CR-71 southwest of Centre. Length 5.550 mi.The Bracket Ranges shown herein are to provide general financial information to Contractors and Bonding Companies concerning a Project's complexity and size only. THESE BRACKETS SHOULD NOT BE USED IN PREPARING A BID, NOR WILL THESE BRACKETS HAVE ANY BEARING ON THE DECISION TO AWARD ANY CONTRACT.
BRACKET ESTIMATE: $1,435,000 TO $1,755,000
| ITEM CODE | QUANTITY | UNIT | ITEM DESCRIPTION | |
|---|---|---|---|---|
| 401A004 | 71632 | SQYD | Bituminous Treatment E | |
| 405A000 | 2150 | GAL | Tack Coat | |
| 407B000 | 6 | MILE | Joint Sealant For Hot Mix Asphalt Pave | |
| 424A341 | 6205 | TON | Superpave Wrg Surf 3/4" ESAL A/B | |
| 424A346 | 750 | TON | Superpave Wrg Surf Lev 1/2" ESAL A/B | |
| 424B636 | 12536 | TON | Superpave Upr Bndr Lay 1" Esal A/B | |
| 424B640 | 100 | TON | Superpave Upr Bndr Pat 1" Esal A/B | |
| 430B043 | 3125 | TON | Agg Surf (1" Down, Crusher Run) | |
| 600A000 | 1 | LS | Mobilization | |
| 698A000 | 1 | LS | Construction Fuel (Maximum Bid Limited 75,660.00) | |
| 701A030 | 11 | MILE | Solid White Cl 2T Ty A Traf Stripe | |
| 701A034 | 7 | MILE | Solid Yellow Cl 2T Ty A Traf Stripe | |
| 701A044 | 4 | MILE | Broken Yellow Cl 2T Ty A Traf Stripe | |
| 701C000 | 12 | MILE | Broken Temporary Traffic Stripe | |
| 701C001 | 21 | MILE | Solid Temporary Traffic Stripe | |
| 701G252 | 275 | LF | Solid White Cl 2 Ty A Traf Str 5" WRS | |
| 703A002 | 132 | SQFT | Traffic Control Marking, Class 2, Type A | |
| 705A032 | 185 | EACH | Pavement Markers, Class A-H, Type 1-B | |
| 705A037 | 545 | EACH | Pavement Markers, Class A-H, Type 2-D | |
| 740B000 | 321 | SQFT | Construction Signs | |
| 740E000 | 25 | EACH | Cones (36" High) | |
| 740M001 | 25 | EACH | Ballast For Cone | |
| 740O000 | 1 | EACH | Pilot Car |