056 . SRTS-SR11(901) , CALHOUN

COUNTY: CALHOUN

WORKING DAYS: 60

for constructing the Sidewalk and Pedestrian Bridge along the Old Piedmont Gadsden Highway from SR-200 to Fifth Avenue North in Piedmont. Length 0.376 mi.

The Bracket Ranges shown herein are to provide general financial information to Contractors and Bonding Companies concerning a Project's complexity and size only. THESE BRACKETS SHOULD NOT BE USED IN PREPARING A BID, NOR WILL THESE BRACKETS HAVE ANY BEARING ON THE DECISION TO AWARD ANY CONTRACT.

BRACKET ESTIMATE: $150,000 TO $180,000


THE PRINCIPAL ITEMS OF WORK ARE APPROXIMATELY AS FOLLOWS:

ITEM CODE QUANTITY UNIT ITEM DESCRIPTION
201A002 1 LS Clear & Grub (Maximum Allowable Bid $ 4000 Per Acre)(Approximately 2 Acres)
206E007 5 EACH Removing Mailboxes (Res w/new Tim Post)
210D001 800 CUYD Borrow Excavation (Loose Truckbed Meas)
516D000 1 LS Pedestrian Bridge
517D000 20 LF Sidewalk Handrail
529A016 100 SQFT Retaining Wall (Modular Block Wall)
600A000 1 LS Mobilization
618A000 994 SQYD Concrete Sidewalk, 4" Thick
618A001 67 SQYD Concrete Sidewalk, 6" Thick
652A100 2 ACRE Seeding
654A000 320 SQYD Solid Sodding
656A010 2 ACRE Mulching
665J002 2000 LF Silt Fence
665O001 2000 LF Silt Fence Removal
680A001 1 LS Geometric Controls
703A002 200 SQFT Traffic Control Marking, Class 2, Type A
710A125 31 SQFT Cl 7 Alum Sig 0.08"/St 14 IV VII VIII IX
710B021 52 LF Rdwy Sign Pt(#3 UCh GS or 2"14Ga SqTuSt)
740B000 104 SQFT Construction Signs
740E000 25 EACH Cones (36" High)