083 . 99-507-690-000-201 , COFFEE , DALE , GENEVA & HENRY

COUNTY: COFFEE , DALE , GENEVA AND HENRY

WORKING DAYS: 115

for constructing the Pile Encasement and Riprap Placement on various bridges at sites as indicated by the plans.

The Bracket Ranges shown herein are to provide general financial information to Contractors and Bonding Companies concerning a Project's complexity and size only. THESE BRACKETS SHOULD NOT BE USED IN PREPARING A BID, NOR WILL THESE BRACKETS HAVE ANY BEARING ON THE DECISION TO AWARD ANY CONTRACT.

BRACKET ESTIMATE: $380,000 TO $460,000


THE PRINCIPAL ITEMS OF WORK ARE APPROXIMATELY AS FOLLOWS:

ITEM CODE QUANTITY UNIT ITEM DESCRIPTION
430B000 200 TON Agg Surf (ALDOT #467 or #57)
504G000 292 LF Steel Piling Encasement Wet Condition
600A000 1 LS Mobilization
610C001 2836 TON Loose Riprap Class 2
610D003 3165 SQYD Filter Blanket Geotextile
665J002 2464 LF Silt Fence
665L000 964 LF Floating Basin Boom
665N000 660 TON Temporary Coarse Aggregate ALDOT No 1
665O001 2464 LF Silt Fence Removal
665Q002 800 LF Wattle
680A001 1 LS Geometric Controls
698A000 1 LS Construction Fuel (Maximum Bid Limited 12,175.00)
740B000 1324 SQFT Construction Signs
740E000 130 EACH Cones (36" High)
740M001 130 EACH Ballast For Cone
741C010 2 EACH Port Seq Arrow & Chevron Sign Unit