COUNTY: HENRY
WORKING DAYS: 30
MBE/DBE CONTRACT OBLIGATION: 3 %
for constructing the Resurfacing and Traffic Stripe on CR-16 from the Dale County Line to SR-173. Length 3.537 mi.The Bracket Ranges shown herein are to provide general financial information to Contractors and Bonding Companies concerning a Project's complexity and size only. THESE BRACKETS SHOULD NOT BE USED IN PREPARING A BID, NOR WILL THESE BRACKETS HAVE ANY BEARING ON THE DECISION TO AWARD ANY CONTRACT.
BRACKET ESTIMATE: $415,530 TO $507,870
| ITEM CODE | QUANTITY | UNIT | ITEM DESCRIPTION | |
|---|---|---|---|---|
| 405A000 | 2490 | GAL | Tack Coat | |
| 407B000 | 4 | MILE | Joint Sealant For Hot Mix Asphalt Pave | |
| 424A340 | 3263 | TON | Superpave Wrg Surf 1/2" ESAL A/B | |
| 424A346 | 1660 | TON | Superpave Wrg Surf Lev 1/2" ESAL A/B | |
| 424B640 | 125 | TON | Superpave Upr Bndr Pat 1" Esal A/B | |
| 600A000 | 1 | LS | Mobilization | |
| 665F000 | 40 | EACH | Hay Bales | |
| 665J002 | 300 | LF | Silt Fence | |
| 665O001 | 300 | LF | Silt Fence Removal | |
| 698A000 | 1 | LS | Construction Fuel (Maximum Bid Limited 13,225.00) | |
| 701A231 | 7 | MILE | Solid White Cl 2 Ty A Traf Str | |
| 701A235 | 5 | MILE | Solid Yellow Cl 2 Ty A Traf Str | |
| 701A245 | 2 | MILE | Broken Yellow Cl 2 Ty A Traf Str | |
| 701C000 | 2 | MILE | Broken Temporary Traffic Stripe | |
| 701C001 | 5 | MILE | Solid Temporary Traffic Stripe | |
| 703A002 | 160 | SQFT | Traffic Control Marking, Class 2, Type A | |
| 703D001 | 160 | SQFT | Temporary Traffic Control Markings | |
| 705A032 | 66 | EACH | Pavement Markers, Class A-H, Type 1-B | |
| 705A037 | 198 | EACH | Pavement Markers, Class A-H, Type 2-D | |
| 740B000 | 213 | SQFT | Construction Signs | |
| 740O000 | 1 | EACH | Pilot Car |