002 . IM-I065(437) , LOWNDES, etc. 005 . STPBHF-1059(355) , JEFFERSON
**011 . HPP-0216(502) , TUSCALOOSA 015 . ACBRZ58307-ATRP(001) , BALDWIN
017 . ACNU59986-ATRP(001) , COFFEE 018 . ACOA57217-ATRP(001) , HOUSTON
019 . ACNU59563-ATRP(001) , CHAMBERS 021 . ACOA58341-ATRP(001) , DALLAS
022 . ACOA58426-ATRP(001) , BALDWIN 023 . ACOA59010-ATRP(001) , BALDWIN
024 . ACNU58340-ATRP(001) , BUTLER 026 . DE-A194(934) , JEFFERSON
032 . HSIP-STPOA-0095(502) , HENRY 035 . NH-0038(532) , LEE
037 . SRTS-SR09(903) , JEFFERSON 038 . STPOA-0042(525) , BALDWIN
039 . EB-0055(510) , COVINGTON, etc. ** 041 . RECA-STPOA-HSIP-0046(504) , CLEBURNE
042 . STPOA-HSIP-0087(511) , GENEVA 044 . STPMN-7780(600) , MONTGOMERY
045 . STPNU-2100(204) , CRENSHAW 046 . STPNU-2800(214) , ETOWAH
047 . STPNU-4202(200) , LIMESTONE 048 . STPNU-5408(201) , PICKENS
049 . STPNU-CN13(207) , MARSHALL 050 . STPNU-CN13(208) , TALLAPOOSA
053 . STPOA-9027(600) , LEE 057 . ST-002-181-010 , BALDWIN
059 . ST-049-016-009 , MOBILE 062 . 99-406-513-006-111 , MONTGOMERY
** 063 . 99-504-690-000-201 , CLEBURNE, etc. 200 . HRRR-6705(201) , WINSTON
** - ALL BIDS REJECTED

002 . IM-I065(437) LOWNDES & MONTGOMERY COUNTIES

LENGTH: 9.33 MILES.

SHALL BE COMPLETED BY: March 1, 2014
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 4.00

for constructing the Planing, Resurfacing, Traffic Stripe and Counting Units on I-65 from 0.5 miles south of SR-97 (MP 150.560) to the relief bridge before Pintlala Creek (MP 159.886) near Montgomery. Length 9.325 mi.

BRACKET ESTIMATE: $5,006,744 TO $6,119,354

VIEW ITEMS


005 . STPBHF-I059(355) JEFFERSON COUNTY

LENGTH: 4.13 MILES.

SHALL BE COMPLETED BY: May 1, 2014
COST OF PLANS: $36.00

for constructing the I-20/59 Lighting (Phase 1A) from 3700 feet east of the Eastbound Stephens Expressway Interchange to 2000 feet east of the I-20/59 split in Birmingham. Length 3.522 mi.

BRACKET ESTIMATE: $3,890,958 TO $4,755,616

VIEW ITEMS


011 . HPP-0216(502) TUSCALOOSA COUNTY

LENGTH: 0.30 MILES.

WORKING DAYS: 60
DBE CONTRACT OBLIGATION: 4 % COST OF PLANS: $30.00

for constructing the Safety Widening, Resurfacing and Traffic Stripe on SR-216 (Intersection Improvements at Connie Drive in Lakeview). Length 0.302 mi

BRACKET ESTIMATE: $497,886 TO $608,528

**ALL BIDS REJECTED**

015 . ACBRZ58307- ATRP(001) BALDWIN COUNTY

LENGTH: 0.18 MILES.

WORKING DAYS: 80
COST OF PLANS: $13.00

for constructing the Bridge Replacement and Approaches on CR-71 (College Avenue) over Rock Creek in Robertsdale. Length 0.183 mi.

BRACKET ESTIMATE: $441,887 TO $540,084

VIEW ITEMS


017 . ACNU59986-ATRP(001) , ACNU58510-ATRP(001) , ACNU58512-ATRP(001) , ACNU58526-ATRP(001) , ACNU58511-ATRP(001) , ACNU58531-ATRP(001) , ACNU59405-ATRP(001) , ACNU59406-ATRP(001) & ACNU59403-ATRP(001) COFFEE COUNTY

LENGTH: 26.03 MILES.

WORKING DAYS: 180
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $22.00

for constructing the Planing, Resurfacing, and Traffic Stripe on Various Routes as indicated in the plans. Length 26.659 mi.

BRACKET ESTIMATE: $3,652,641 TO $4,464,338

VIEW ITEMS


018 . ACOA57217-ATRP(001) & ACNU59477-ATRP(001) HOUSTON COUNTY

LENGTH: 11.24 MILES.

WORKING DAYS: 45
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 7.00

for constructing the Resurfacing and Traffic Stripe on CR-40 (Fortner Street) from Cumbie Road to 875 feet west of South Brannon Stand Road and on CR-32 (Judge Logue Road) from SR-123 to SR-12 (US-84) in Dothan. Length 11.257 mi.

BRACKET ESTIMATE: $2,130,869 TO $2,604,395

VIEW ITEMS


019 . ACNU59563-ATRP(001) & STPNU-0924(200) CHAMBERS COUNTY

LENGTH: 6.98 MILES.

WORKING DAYS: 45
DBE CONTRACT OBLIGATION: 2 % COST OF PLANS: $ 7.00

for constructing the Full Depth Reclamation, Pave, and Traffic Stripe on CR-258 (1258) from CR-234 (1234) North to the Randolph County Line Northwest of Five Points and on CR-53 (1053) from CR-62 (1062) to CR-114 (1114) Northwest of Lafayette. Length 6.976 mi.

BRACKET ESTIMATE: $1,102,407 TO $1,347,386

VIEW ITEMS


021 . ACOA58341-ATRP(001) DALLAS COUNTY

LENGTH: 1.04 MILES.

WORKING DAYS: 60
DBE CONTRACT OBLIGATION: 4 % COST OF PLANS: $11.00

for constructing the Planing, Resurfacing, Guardrail, and Traffic Stripe (Pavement Rehabilitation) on Old Cahaba Road from Old Marion Junction Road to King Street and on Medical Center Parkway from Old Cahaba Road to the Junction of SR-8 (US-80) in Selma. Length 2.702 mi.

BRACKET ESTIMATE: $716,650 TO $875,906

VIEW ITEMS


022 . ACOA58426-ATRP(001) BALDWIN COUNTY

LENGTH: 2.26 MILES.

WORKING DAYS: 180
DBE CONTRACT OBLIGATION: 5 % COST OF PLANS: $28.00

for constructing the Widening, Resurfacing, Bike Lane Addition, and Traffic Stripe on CR-4 (Cotton Creek Drive) from the intersection of SR-59 to Cotton Creek Bridge in Gulf Shores. Length 2.262 mi.

BRACKET ESTIMATE: $1,759,709 TO $2,150,756

VIEW ITEMS


023 . ACOA59010-ATRP(001) BALDWIN COUNTY

LENGTH: 1.93 MILES.

WORKING DAYS: 110
DBE CONTRACT OBLIGATION: 5 % COST OF PLANS: $20.00

for constructing the Planing, Resurfacing, and Traffic Stripe on Bayview Drive and Ridgewood Drive East of North Main Street in Daphne. Length 1.894 mi.

BRACKET ESTIMATE: $1,839,017 TO $2,247,687

VIEW ITEMS


024 . ACNU58340-ATRP(001) BUTLER COUNTY

LENGTH: 8.93 MILES.

WORKING DAYS: 45
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 3.00

for constructing the Leveling, Resurfacing, and Traffic Stripe on CR-50 (Honoraville Road) from the junction of SR-10 east of Greenville to the Crenshaw County Line. Length 8.928 mi.

BRACKET ESTIMATE: $1,062,219 TO $1,298,268

VIEW ITEMS


026 . DE-A194(934) JEFFERSON COUNTY

LENGTH: 1.70 MILES.

WORKING DAYS: 45
COST OF PLANS: $ 7.00

for constructing the Roadway Revitalization (Landscaping and Lighting) of SR-75 from south of Huffman Road to 25th Court NE in Centerpoint. Length 1.799 mi.

BRACKET ESTIMATE: $100,434 TO $122,752

VIEW ITEMS


032 . HSIP-STPOA-0095(502) HENRY COUNTY

LENGTH: 8.55 MILES.

WORKING DAYS: 70
DBE CONTRACT OBLIGATION: 4 % COST OF PLANS: $12.00

for constructing the Planing, Widening, Resurfacing and Traffic Stripe on SR-95 from the Houston County Line to Haleburg (MP 32.867). Length 8.545 mi.

BRACKET ESTIMATE: $2,527,870 TO $3,089,618

VIEW ITEMS


035 . NH-0038(532) LEE COUNTY

WORKING DAYS: 70
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 3.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-38 (US-280) from SR-147 to 0.3 miles west of Veterans Parkway northwest of Opelika. Length 3.460 mi.

BRACKET ESTIMATE: $2,674,306 TO $3,268,596

VIEW ITEMS


037 . SRTS-SR09(903) & SRTS-SR09(904) JEFFERSON COUNTY

WORKING DAYS: 130
DBE CONTRACT OBLIGATION: 5 % COST OF PLANS: $20.00

for constructing the Installation of Sidewalks, Crosswalks, and Signs near Mountain Brook Elementary School along Canterbury Road, Overhill Road, and Watkins Road & near Crestline Elementary School along Vine Street and West Montcrest Drive in Mountain Brook.

BRACKET ESTIMATE: $557,308 TO $681,154

VIEW ITEMS


038 . STPOA-0042(525) BALDWIN COUNTY

LENGTH: 8.56 MILES.

WORKING DAYS: 80
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 6.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-42 (US-98) from SR-104 (MP 43.685) to CR-98 (MP 52.241) in Barnwell. Length 8.555 mi.

BRACKET ESTIMATE: $2,317,798 TO $2,832,864

VIEW ITEMS


039 . EB-0055(510) COVINGTON & CONECUH COUNTIES

LENGTH: 10.28 MILES.

WORKING DAYS: 30
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 8.00

for constructing the Planing, Resurfacing and Traffic Stripe on SR-55 from the North City Limits of Red Level to the Conecuh/Butler County Line. Length 10.276 mi.

BRACKET ESTIMATE: $940,195 TO $1,149,127

VIEW ITEMS


041 . RECA-STPOA-HSIP-0046(504) CLEBURNE COUNTY

LENGTH: 10.09 MILES.

WORKING DAYS: 65
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 3.00

for constructing the Safety Widening, Planing Resurfacing and Traffic Stripe on SR-46 from west of CR-620 (MP 10.988) to the Georgia State Line (MP 21.074). Length 10.086 mi.

BRACKET ESTIMATE: $2,559,040 TO $3,127,715

**ALL BIDS REJECTED**

042 . STPOA-HSIP-0087(511) GENEVA COUNTY

LENGTH: 10.38 MILES.

WORKING DAYS: 90
DBE CONTRACT OBLIGATION: 4 % COST OF PLANS: $16.00

for constructing the Planing, Resurfacing, Safety Widening, and Traffic Stripe on SR-87 from the Florida State Line to the North City Limits of Samson. Length 10.375 mi.

BRACKET ESTIMATE: $3,126,690 TO $3,821,510

VIEW ITEMS


044 . STPMN-7780(600) & IAR-051-000-005 MONTGOMERY COUNTY

LENGTH: 3.24 MILES.

WORKING DAYS: 150
DBE CONTRACT OBLIGATION: 5 % COST OF PLANS: $55.00

for constructing the Planing, Resurfacing, Traffic Stripe, and Fiber Optic and Signals on W.L. Dickinson Drive from CSX Railroad to 0.23 miles south of SR-9 (US-231) including Industrial Access Improvements at Maxwell AFB (Gunter Annex) Cyber Commander. Length 1.886 mi.

BRACKET ESTIMATE: $2,484,723 TO $3,036,884

VIEW ITEMS


045 . STPNU-2100(204) CRENSHAW COUNTY

LENGTH: 6.36 MILES.

WORKING DAYS: 30
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 2.00

for constructing the Widening, Resurfacing, and Traffic Stripe on CR-31/35 (Quail Tower Road) from north of the Rutledge Town Limits to the intersection of CR-50. Length 6.357 mi.

BRACKET ESTIMATE: $762,454 TO $931,888

VIEW ITEMS


046 . STPNU-2800(214) ETOWAH COUNTY

LENGTH: 3.58 MILES.

WORKING DAYS: 30
DBE CONTRACT OBLIGATION: 4 % COST OF PLANS: $ 5.00

for constructing the Resurfacing and Traffic Stripe on CR-32 (Tumlin Gap Road) from the intersection of Gallant Road to the intersection of SR-132 near Gallant. Length 3.589 mi.

BRACKET ESTIMATE: $1,066,972 TO $1,304,077

VIEW ITEMS


047 . STPNU-4202(200) LIMESTONE COUNTY

LENGTH: 2.96 MILES.

WORKING DAYS: 30
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 3.00

for constructing the Resurfacing and Traffic Stripe on CR-71 (Mooresville Road) from CR-292 (Thach Road) to CR-117 (Sweet Springs Road) southwest of Ardmore. Length 2.959 mi.

BRACKET ESTIMATE: $597,074 TO $729,757

VIEW ITEMS


048 . STPNU-5408(201) PICKENS COUNTY

LENGTH: 7.13 MILES.

WORKING DAYS: 45
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 8.00

for constructing the Resurfacing, Traffic Stripe, and Guardrail Installation on CR-35 from SR-86 in Carrollton to 0.217 miles south of CR-37. Length 7.126 mi.

BRACKET ESTIMATE: $1,348,029 TO $1,647,590

VIEW ITEMS


049 . STPNU-CN13(207) MARSHALL COUNTY

LENGTH: 2.17 MILES.

WORKING DAYS: 30
COST OF PLANS: $ 3.00

for constructing the Resurfacing and Traffic Stripe on CR-152 (Oneonta Cut-Off Road) from CR-166 (Section Line Road) to SR-205 west of Albertville. Length 2.169 mi.

BRACKET ESTIMATE: $380,010 TO $464,457

VIEW ITEMS


050 . STPNU-CN13(208) TALLAPOOSA COUNTY

LENGTH: 2.94 MILES.

WORKING DAYS: 30
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 3.00

for constructing the Resurfacing and Traffic Stripe on CR-17 (North Central Avenue) from the Alexander City Limits to the intersection of SR-63. Length 2.935 mi.

BRACKET ESTIMATE: $413,889 TO $505,865

VIEW ITEMS


053 . STPOA-9027(600) LEE COUNTY

LENGTH: 0.64 MILES.

WORKING DAYS: 35
COST OF PLANS: $ 3.00

for constructing the Planing, Resurfacing, and Traffic Stripe on CR-97 (Shelton Mill Road) from the intersection of SR-147 (North College Street) to just south of Shelton Lane in Auburn. Length 0.639 mi.

BRACKET ESTIMATE: $224,693 TO $274,625

VIEW ITEMS


057 . ST-002-181-010 BALDWIN COUNTY

WORKING DAYS: 75
COST OF PLANS: $28.00

for constructing the Widening (Grade, Drain, Base, and Pave) on SR-181 from south of CR-48 to south of CR-30 in Fairhope. Length 1.188 mi.

BRACKET ESTIMATE: $740,000 TO $900,000

VIEW ITEMS


059 . ST-049-016-009 MOBILE COUNTY

WORKING DAYS: 60
COST OF PLANS: $14.00

for constructing the Access Improvements (Widening and Lighting Relocation) on the Service Road south of the Bankhead Tunnel going onto SR-16 (US-90/98) in Mobile. Length 0.123 mi.

BRACKET ESTIMATE: $166,864 TO $203,944

VIEW ITEMS


062 . 99-406-513-006-111 & 99-406-513-009-114 MONTGOMERY COUNTY

WORKING DAYS: 100
COST OF PLANS: $21.00

for constructing the Intersection Improvements (Grade, Drain, Base, and Pave) on SR-6 (US-82) (Southern Boulevard) (Sites 1-3) & on SR-9 (US-231) (Eastern Bypass) (Sites 4-14) as indicated in the plans in Montgomery.

BRACKET ESTIMATE: $664,539 TO $812,215

VIEW ITEMS


063 . 99-504-690-000-201 CLEBURNE , COOSA , RUSSELL & TALLAPOOSA COUNTIES

WORKING DAYS: 110
COST OF PLANS: $ 2.00

for the Maintenance Bridge Painting on various routes as indicated in the plans.

BRACKET ESTIMATE: $523,778 TO $640,174

**ALL BIDS REJECTED**

200 . HRRR-6705(201) WINSTON COUNTY

LENGTH: 3.05 MILES.

WORKING DAYS: 30
COST OF PLANS: $ 3.00

for constructing the Paved Shoulders and Traffic Stripe on CR-63 from Farley Road near Arley to Old Arley Road near Houston. Length 3.053 mi.

BRACKET ESTIMATE: $158,661 TO $193,919

VIEW ITEMS