COUNTY: CALHOUN
WORKING DAYS: 45
MBE/DBE CONTRACT OBLIGATION: 3 %
for constructing the Resurfacing and Traffic Stripe on Choccolocco Road (CR-55) from Scarborough Lane to the junction of SR-9. Length 5.939 mi.The Bracket Ranges shown herein are to provide general financial information to Contractors and Bonding Companies concerning a Project's complexity and size only. THESE BRACKETS SHOULD NOT BE USED IN PREPARING A BID, NOR WILL THESE BRACKETS HAVE ANY BEARING ON THE DECISION TO AWARD ANY CONTRACT.
BRACKET ESTIMATE: $1,422,247 TO $1,738,302
| ITEM CODE | QUANTITY | UNIT | ITEM DESCRIPTION | |
|---|---|---|---|---|
| 401B106 | 20909 | SQYD | Bituminous Treatment JG (W/Polymer) | |
| 401B108 | 83635 | SQYD | Bituminous Treatment G (W/Polymer) | |
| 405A000 | 2610 | GAL | Tack Coat | |
| 407B000 | 6 | MILE | Joint Sealant For Hot Mix Asphalt Pave | |
| 424A340 | 5850 | TON | Superpave Wrg Surf 1/2" ESAL A/B | |
| 424A346 | 500 | TON | Superpave Wrg Surf Lev 1/2" ESAL A/B | |
| 424B635 | 8364 | TON | Superpave Upr Bndr Lay 3/4" Esal A/B | |
| 424B639 | 350 | TON | Superpave Upr Bndr Pat 3/4" Esal A/B | |
| 430B043 | 3500 | TON | Agg Surf (1" Down, Crusher Run) | |
| 600A000 | 1 | LS | Mobilization | |
| 698A000 | 1 | LS | Construction Fuel (Maximum Bid Limited 86,000.00) | |
| 701A231 | 12 | MILE | Solid White Cl 2 Ty A Traf Str | |
| 701A235 | 9 | MILE | Solid Yellow Cl 2 Ty A Traf Str | |
| 701A245 | 2 | MILE | Broken Yellow Cl 2 Ty A Traf Str | |
| 701C000 | 6 | MILE | Broken Temporary Traffic Stripe | |
| 701C001 | 27 | MILE | Solid Temporary Traffic Stripe | |
| 701G251 | 300 | LF | Solid White Cl 2 Ty A Traf Str 6" WRS | |
| 703A002 | 360 | SQFT | Traffic Control Marking, Class 2, Type A | |
| 703D001 | 360 | SQFT | Temporary Traffic Control Markings | |
| 705A032 | 196 | EACH | Pavement Markers, Class A-H, Type 1-B | |
| 705A037 | 588 | EACH | Pavement Markers, Class A-H, Type 2-D | |
| 740B000 | 500 | SQFT | Construction Signs | |
| 740O000 | 1 | EACH | Pilot Car |