COUNTY: COVINGTON
WORKING DAYS: 40
MBE/DBE CONTRACT OBLIGATION: 3 %
for constructing the Resurfacing and Traffic Stripe on CR-24 east of the Conecuh National Forest from the junction of SR-137 to the junction of SR-55. Length 7.729 mi.The Bracket Ranges shown herein are to provide general financial information to Contractors and Bonding Companies concerning a Project's complexity and size only. THESE BRACKETS SHOULD NOT BE USED IN PREPARING A BID, NOR WILL THESE BRACKETS HAVE ANY BEARING ON THE DECISION TO AWARD ANY CONTRACT.
BRACKET ESTIMATE: $781,531 TO $955,205
| ITEM CODE | QUANTITY | UNIT | ITEM DESCRIPTION | |
|---|---|---|---|---|
| 210D021 | 5000 | CUYD | Borrow Excav (Lse Trb Meas)(A-4 Better) | |
| 212A000 | 811 | STA | Machine Grading Shoulders | |
| 405A000 | 2720 | GAL | Tack Coat | |
| 407B000 | 8 | MILE | Joint Sealant For Hot Mix Asphalt Pave | |
| 424A341 | 7855 | TON | Superpave Wrg Surf 3/4" ESAL A/B | |
| 424A347 | 600 | TON | Superpave Wrg Surf Lev 3/4" ESAL A/B | |
| 600A000 | 1 | LS | Mobilization | |
| 652A100 | 19 | ACRE | Seeding | |
| 652C000 | 19 | ACRE | Mowing | |
| 656A010 | 19 | ACRE | Mulching | |
| 665J002 | 2400 | LF | Silt Fence | |
| 665O001 | 2400 | LF | Silt Fence Removal | |
| 698A000 | 1 | LS | Construction Fuel (Maximum Bid Limited 40,000.00) | |
| 701A235 | 8 | MILE | Solid Yellow Cl 2 Ty A Traf Str | |
| 701A245 | 5 | MILE | Broken Yellow Cl 2 Ty A Traf Str | |
| 703A002 | 140 | SQFT | Traffic Control Marking, Class 2, Type A | |
| 740B000 | 699 | SQFT | Construction Signs | |
| 740O000 | 1 | EACH | Pilot Car |