COUNTY: JEFFERSON
WORKING DAYS: 125
for the Maintenance Roadside Mowing at Various Locations along I-20, I-65, I-459, and SR-4 as indicated in the plans.The Bracket Ranges shown herein are to provide general financial information to Contractors and Bonding Companies concerning a Project's complexity and size only. THESE BRACKETS SHOULD NOT BE USED IN PREPARING A BID, NOR WILL THESE BRACKETS HAVE ANY BEARING ON THE DECISION TO AWARD ANY CONTRACT.
BRACKET ESTIMATE: $402,013 TO $491,349
| ITEM CODE | QUANTITY | UNIT | ITEM DESCRIPTION | |
|---|---|---|---|---|
| 655A009 | 2 | CYCL | Maintenance Roadside Mowing (Approximate 5320 Acres Per Cycle) | |
| 655A010 | 1 | CYCL | Maintenance Roadside Mowing (Approximate 3079 Acres) | |
| 698A000 | 1 | LS | Construction Fuel (Maximum Bid Limited 20,000.00) | |
| 740B000 | 640 | SQFT | Construction Signs |