COUNTY: CONECUH
WORKING DAYS: 60
MBE/DBE CONTRACT OBLIGATION: 3 %
for constructing the Resurfacing and Traffic Stripe on CR-29 from the intersection of SR-83 in Evergreen to the Sepulga River Bridge. Length 9.902 mi.The Bracket Ranges shown herein are to provide general financial information to Contractors and Bonding Companies concerning a Project's complexity and size only. THESE BRACKETS SHOULD NOT BE USED IN PREPARING A BID, NOR WILL THESE BRACKETS HAVE ANY BEARING ON THE DECISION TO AWARD ANY CONTRACT.
BRACKET ESTIMATE: $1,147,663 TO $1,402,663
| ITEM CODE | QUANTITY | UNIT | ITEM DESCRIPTION | |
|---|---|---|---|---|
| 212A000 | 1046 | STA | Machine Grading Shoulders | |
| 405A000 | 6400 | GAL | Tack Coat | |
| 407B000 | 10 | MILE | Joint Sealant For Hot Mix Asphalt Pave | |
| 424A340 | 9900 | TON | Superpave Wrg Surf 1/2" ESAL A/B | |
| 424A346 | 1200 | TON | Superpave Wrg Surf Lev 1/2" ESAL A/B | |
| 600A000 | 1 | LS | Mobilization | |
| 650A000 | 7800 | CUYD | Topsoil | |
| 652A100 | 19 | ACRE | Seeding | |
| 656A010 | 19 | ACRE | Mulching | |
| 698A000 | 1 | LS | Construction Fuel (Maximum Bid Limited 69,000.00) | |
| 701A235 | 19 | MILE | Solid Yellow Cl 2 Ty A Traf Str | |
| 701A245 | 1 | MILE | Broken Yellow Cl 2 Ty A Traf Str | |
| 701C000 | 1 | MILE | Broken Temporary Traffic Stripe | |
| 701C001 | 19 | MILE | Solid Temporary Traffic Stripe | |
| 740B000 | 402 | SQFT | Construction Signs | |
| 740O000 | 1 | EACH | Pilot Car |