COUNTY: HOUSTON
WORKING DAYS: 75
for constructing the Sidewalk Improvements on South Park Avenue from Fortner Street to West Selma Street and on Woodland Drive from Valley Forge Road to South Park Avenue in Dothan. Length 0.895 mi.The Bracket Ranges shown herein are to provide general financial information to Contractors and Bonding Companies concerning a Project's complexity and size only. THESE BRACKETS SHOULD NOT BE USED IN PREPARING A BID, NOR WILL THESE BRACKETS HAVE ANY BEARING ON THE DECISION TO AWARD ANY CONTRACT.
BRACKET ESTIMATE: $151,458 TO $185,115
| ITEM CODE | QUANTITY | UNIT | ITEM DESCRIPTION | |
|---|---|---|---|---|
| 201A002 | 1 | LS | Clear & Grub (Maximum Allowable Bid $ 4,000.00)(Approximately 1 acre) | |
| 206E042 | 4 | EACH | Removing Inlets (Partial) | |
| 209A001 | 8 | EACH | Mailbox Reset Double | |
| 210A000 | 267 | CUYD | Unclassified Excavation | |
| 210D001 | 25 | CUYD | Borrow Excavation (Loose Truckbed Meas) | |
| 214A000 | 100 | CUYD | Structure Excavation | |
| 600A000 | 1 | LS | Mobilization | |
| 618A000 | 2299 | SQYD | Concrete Sidewalk, 4" Thick | |
| 618A001 | 126 | SQYD | Concrete Sidewalk, 6" Thick | |
| 621D025 | 4 | EACH | Inlet Units, Type S2 Or S4 (Mod) | |
| 650A000 | 282 | CUYD | Topsoil | |
| 652A100 | 1 | ACRE | Seeding | |
| 654A000 | 2550 | SQYD | Solid Sodding | |
| 656A010 | 1 | ACRE | Mulching | |
| 665F000 | 20 | EACH | Hay Bales | |
| 665G000 | 30 | EACH | Sand Bags | |
| 665J002 | 3979 | LF | Silt Fence | |
| 665O001 | 3979 | LF | Silt Fence Removal | |
| 665Q002 | 55 | LF | Wattle | |
| 680A001 | 1 | LS | Geometric Controls | |
| 703A002 | 1518 | SQFT | Traffic Control Marking, Class 2, Type A | |
| 740B000 | 482 | SQFT | Construction Signs | |
| 740D000 | 20 | EACH | Channelizing Drums | |
| 740E000 | 20 | EACH | Cones (36" High) | |
| 740M001 | 20 | EACH | Ballast For Cone |