Office Engineer

Proposal Letting List
January 31, 2014 Transportation Letting

Welcome to the Proposal Letting List Page. You may view the approximate items of work for each proposal in the Letting by clicking on the View Items hyperlink to view the Project Item Pages. Please take a minute to review these pages and e-mail us with your comments.


The Bracket Ranges shown herein are to provide general financial information to Contractors and Bonding Companies concerning a Project's complexity and size only. THESE BRACKETS SHOULD NOT BE USED IN PREPARING A BID, NOR WILL THESE BRACKETS HAVE ANY BEARING ON THE DECISION TO AWARD ANY CONTRACT.


002 . IM-I059(365) , JEFFERSON * 003 . IM-IMD-I010(323) , MOBILE *
025 . ACBRZ58475-ATRP(001) , WASHINGTON * 027 . ACBRZ58646-ATRP(001) , JACKSON *
032 . ACNU58478-ATRP(001) , WASHINGTON 034 . ACNU58536-ATRP(001) , COVINGTON
035 . ACNU58635-ATRP(001) , CHEROKEE 036 . ACNU58643-ATRP(001) , JACKSON
037 . ACNU59368-ATRP(001) , GREENE 038 . ACNU59435-ATRP(001) , COVINGTON
039 . ACNU59453-ATRP(001) , COVINGTON 040 . ACNU59584-ATRP(001) , AUTAUGA *
043 . ACNU60037-ATRP(001) , MONROE 044 . ACNU60545-ATRP(001) , HENRY
051 . ACOA60714-ATRP(001) , PIKE 052 . ACOA61164-ATRP(001) , BALDWIN
059 . NH-0002(560) , MADISON 061 . NH-0003(576) , JEFFERSON
062 . NH-0016(515) , MOBILE * 063 . NH-0038(533) , LEE
067 . RECA-STPOA-HSIP-0046(504) , CLEBURNE 072 . SRTS-SR13(918) , MOBILE *
075 . STPAA-0004(540) , TALLADEGA 076 . STPAA-HSIP-0009(554) , CLEBURNE *
077 . STPAA-0017(551) , WASHINGTON 078 . STPAA-0021(546) , ESCAMBIA *
079 . STPAA-0109(500) , HOUSTON 080 . STPAA-0127(500) , LIMESTONE
082 . STPAA-0233(502) , MARION 083 . STPAA-7804(602) , AUTAUGA, etc. *
084 . STPAA-7806(600) , AUTAUGA * 086 . STPAA-HSIP-0015(524) , COVINGTON
088 . STPAA-HSIP-0068(507) , CHEROKEE 089 . STPAA-HSIP-0085(501) , GENEVA, etc.
092 . STPAA-HSIP-0125(502) , PIKE 094 . STPAA-HSIP-0153(500) , GENEVA
098 . STPNU-1600(228) , COFFEE 102 . 99-401-224-I65-401 , CULLMAN
103 . 99-401-253-I59-401 , DEKALB 104 . 99-507-690-000-301 , BARBOUR, etc.
200 . HPP-A138(900) , TUSCALOOSA

* - WITHDRAWN FROM LETTING


002 . IM-I059(365) JEFFERSON COUNTY

SHALL BE COMPLETED BY: July 1, 2015
DBE CONTRACT OBLIGATION: 6 % COST OF PLANS: $52.00

for constructing the Polymer Modified Open Graded Friction Course, Concrete Slab Replacement, Guardrail and Median Barrier Replacement, Bridge Rail Retrofit, Traffic Stripe and Signing on I-59 from north of SR-3 (US-31/EB Stephens Expressway) to north of the I-20 Interchange. Length 4.143 mi.

BRACKET ESTIMATE: $12,965,220 TO $15,846,380

*** WITHDRAWN FROM LETTING ***

003 . IM-IMD-I010(323) MOBILE COUNTY
SHALL BE COMPLETED BY: April 15, 2016
DBE CONTRACT OBLIGATION: 5 % COST OF PLANS: $115

for constructing the Welcome Center Replacement (Grade, Drain, Base, Pave, Demolition, Building, Lighting, Landscaping, Sewer, and Lagoon Removal) on I-10 at the Alabama/Mississippi State Line.

BRACKET ESTIMATE: $16,351,071 TO $19,984,642

*** WITHDRAWN FROM LETTING ***

025 . ACBRZ58475-ATRP(001) WASHINGTON COUNTY
WORKING DAYS: 240
DBE CONTRACT OBLIGATION: 2 % COST OF PLANS: $ 6.00

for constructing the Bridge and Two Relief Bridge Replacements on CR-8 over the Escatawpa River. Length 0.159 mi.

RACKET ESTIMATE: $2,105,492 TO $2,573,380

*** WITHDRAWN FROM LETTING ***

027 . ACBRZ58646-ATRP(001) JACKSON COUNTY
WORKING DAYS: 120
DBE CONTRACT OBLIGATION: 5 % COST OF PLANS: $10.00

for constructing the Bridge Replacement and Approaches on CR-151 over Bryant Creek east of Pisgah. Length 0.241 mi.

*** WITHDRAWN FROM LETTING ***

032 . ACNU58478-ATRP(001) WASHINGTON COUNTY

LENGTH: 25.25 MILES.

WORKING DAYS: 100
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 4.00

for constructing the Resurfacing and Traffic Stripe on CR-34 from SR-17 in Millry to SR-13 (US-43) in Leroy. Length 25.250 mi.

BRACKET ESTIMATE: $4,223,463 TO $5,162,011

VIEW ITEMS


034 . ACNU58536-ATRP(001) COVINGTON COUNTY

LENGTH: 3.09 MILES.

WORKING DAYS: 60
DBE CONTRACT OBLIGATION: 5 % COST OF PLANS: $ 4.00

for constructing the Planing, Resurfacing, Traffic Stripe, and Pavement Markers on West Cummings Avenue from SR-12 (US-84) to SR-9 (Main Street). Length 3.089 mi.

BRACKET ESTIMATE: $566,321 TO $692,170

VIEW ITEMS


035 . ACNU58635-ATRP(001) , ACNU58636-ATRP(001) & ACNU58634-ATRP(001) CHEROKEE COUNTY

LENGTH: 13.40 MILES.

WORKING DAYS: 60
DBE CONTRACT OBLIGATION: 4 % COST OF PLANS: $ 8.00

for constructing the Resurfacing, Traffic Stripe, and Guardrail Improvements on CR-15 from CR-259 North to the Georgia State Line; on CR-147 from CR-44 North to the intersection of SR-273; and on CR-29 from CR-12 North to the intersection of SR-25 (US-411). Length 13.398 mi.

BRACKET ESTIMATE: $1,734,510 TO $2,119,957

VIEW ITEMS


036 . ACNU58643-ATRP(001) JACKSON COUNTY

LENGTH: 1.66 MILES.

WORKING DAYS: 30
COST OF PLANS: $ 3.00

for constructing the Resurfacing, Shoulders, and Traffic Stripe on CR-470 from CR-21 to CR-33 northwest of Hollywood. Length 1.663 mi.

BRACKET ESTIMATE: $232,918 TO $284,678

VIEW ITEMS


037 . ACNU59368-ATRP(001) GREENE COUNTY

LENGTH: 10.60 MILES.

WORKING DAYS: 50
DBE CONTRACT OBLIGATION: 4 % COST OF PLANS: $ 4.00

for constructing the Widening, Resurfacing, and Traffic Stripe on CR-208 from the North Right-of-Way Limits of the I-20/I-59 Interchange to the intersection of CR-60. Length 10.599 mi.

BRACKET ESTIMATE: $1,853,998 TO $2,265,997

VIEW ITEMS


038 . ACNU59435-ATRP(001) COVINGTON COUNTY

LENGTH: 3.90 MILES.

WORKING DAYS: 30
DBE CONTRACT OBLIGATION: 5 % COST OF PLANS: $ 3.00

for constructing the Surface Treatment, Leveling, and Resurfacing on CR-4 from SR-54 to the Geneva County Line. Length 3.901 mi.

BRACKET ESTIMATE: $561,618 TO $686,422

VIEW ITEMS


039 . ACNU59453-ATRP(001) COVINGTON COUNTY

LENGTH: 3.26 MILES.

WORKING DAYS: 30
DBE CONTRACT OBLIGATION: 7 % COST OF PLANS: $ 3.00

for constructing the Leveling, Resurfacing and Guardrail Installation on CR-70 (Horsehead Creek Road) from CR-77 (Babbie Road) to SR-9 (US-331) north of Opp. Length 3.259 mi.

BRACKET ESTIMATE: $480,472 TO $587,243

VIEW ITEMS


040 . ACNU59584-ATRP(001) AUTAUGA COUNTY

WORKING DAYS: 45
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 3.00

for constructing the Leveling, Resurfacing, and Traffic Stripe on CR-40 from the intersection of CR-1 to the intersection of CR-19. Length 7.745 mi.

BRACKET ESTIMATE: $810,528 TO $990,646

*** WITHDRAWN FROM LETTING ***

043 . ACNU60037-ATRP(001) MONROE COUNTY

LENGTH: 5.58 MILES.

WORKING DAYS: 40
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 3.00

for constructing the Leveling, Resurfacing, Guardrail Installation, and Traffic Stripe on CR-8 from SR-59 to the intersection of CR-1 & CR-8 (Tower Road). Length 5.577 mi.

BRACKET ESTIMATE: $1,078,079 TO $1,317,652

VIEW ITEMS


044 . ACNU60545-ATRP(001) HENRY COUNTY

LENGTH: 7.37 MILES.

WORKING DAYS: 45
DBE CONTRACT OBLIGATION: 4 % COST OF PLANS: $ 4.00

for constructing the Planing, Leveling, Resurfacing, Guardrail Installation and Traffic Stripe on CR-99 from CR-12 to CR-41 south of Abbeville. Length 7.369 mi.

BRACKET ESTIMATE: $1,828,912 TO $2,235,337

VIEW ITEMS


051 . ACOA60714-ATRP(001) PIKE COUNTY

LENGTH: 5.60 MILES.

WORKING DAYS: 60
DBE CONTRACT OBLIGATION: 4 % COST OF PLANS: $ 7.00

for constructing the Widening, Resurfacing and Traffic Stripe on CR-3363 (Enzor Road) from CR-3304 to SR-87 and the Resurfacing and Traffic Stripe of CR-2290 (Henderson Highway) from CR-2221 to KW Road in Troy. Length 5.627 mi.

BRACKET ESTIMATE: $1,113,662 TO $1,361,142

VIEW ITEMS


052 . ACOA61164-ATRP(001) BALDWIN COUNTY

LENGTH: 0.31 MILES.

WORKING DAYS: 85
DBE CONTRACT OBLIGATION: 5 % COST OF PLANS: $23.00

for constructing the Intersection Improvements (Grade, Drain, Base, Pave, Striping, Signing, and Signals) at SR-59 and CR-48 in Robertsdale. Length 0.356 mi.

BRACKET ESTIMATE: $887,912 TO $1,085,226

VIEW ITEMS


059 . NH-0002(560) & NH-HSIP-0255(501) MADISON COUNTY

LENGTH: 2.70 MILES.

WORKING DAYS: 45
DBE CONTRACT OBLIGATION: 4 % COST OF PLANS: $11.00

for constructing the Resurfacing & Traffic Stripe on SR-2 (US-72/Lee Highway) from Enterprise Way to the Southbound On-Ramp of SR-255 and Safety Widening, Planing, Resurfacing, & Traffic Stripe on SR-255 from Redstone Arsenal Gate 9 to 0.5 miles south of SR-2 (US-72/Lee Highway). Length 2.696 mi.

BRACKET ESTIMATE: $1,308,585 TO $1,599,381

VIEW ITEMS


061 . NH-0003(576) & ST-037-003-009 JEFFERSON COUNTY

LENGTH: 2.81 MILES.

WORKING DAYS: 110
DBE CONTRACT OBLIGATION: 5 % COST OF PLANS: $43.00

for constructing the Widening, Planing, Resurfacing, Traffic Stripe, Guardrail Replacement, Bridge Rail Retrofit, and Additional Lanes & Intersection Improvements on SR-3 (US-31) from the Shelby County Line to I-459 in Hoover. Length 1.494 mi.

BRACKET ESTIMATE: $1,731,304 TO $2,116, 038

VIEW ITEMS


062 . NH-0016(515) MOBILE COUNTY

WORKING DAYS: 130
DBE CONTRACT OBLIGATION: 5 % COST OF PLANS: $11.00

for constructing the Resurfacing and Traffic Stripe on SR-16 (US-90) from the Halls Mill Creek Bridge to the Pavement Joint at Pinehill Drive in Mobile. Length 5.203 mi.

BRACKET ESTIMATE: $2,417,887 TO $2,955,196

*** WITHDRAWN FROM LETTING ***

063 . NH-0038(533) LEE COUNTY

LENGTH: 4.13 MILES.

WORKING DAYS: 85
DBE CONTRACT OBLIGATION: 6 % COST OF PLANS: $ 4.00

for constructing the Resurfacing and Traffic Stripe on SR-38 from 0.3 miles west of the Waverly Parkway to the junction of I-85. Length 4.127 mi.

BRACKET ESTIMATE: $2,865,477 TO $3,502,250

VIEW ITEMS


067 . RECA-STPOA-HSIP-0046(504) CLEBURNE COUNTY

LENGTH: 10.09 MILES.

WORKING DAYS: 65
DBE CONTRACT OBLIGATION: 4 % COST OF PLANS: $ 3.00

for constructing the Safety Widening, Planing, Resurfacing, and Traffic Stripe on SR-46 from west of CR-620 (MP 10.988) to the Georgia State Line (MP 21.074). Length 10.086 mi.

BRACKET ESTIMATE: $2,364,706 TO $2,809,196

VIEW ITEMS


072 . SRTS-SR13(918) MOBILE COUNTY

WORKING DAYS: 45
COST OF PLANS: $18.00

for constructing the Sidewalks and Crosswalks on 12th Avenue and Kansas Street in Chickasaw. Length 0.794 mi.

BRACKET ESTIMATE: $155,652 TO $190,241

*** WITHDRAWN FROM LETTING ***

075 . STPAA-0004(540) TALLADEGA COUNTY

LENGTH: 3.31 MILES.

WORKING DAYS: 55
DBE CONTRACT OBLIGATION: 5 % COST OF PLANS: $ 3.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-4 (US-78) from just west of CR-207 to just east of SR-77 in Lincoln. Length 3.305 mi.

BRACKET ESTIMATE: $1,829,104 TO $2,235,572

VIEW ITEMS


076 . STPAA-HSIP-0009(554) CLEBURNE COUNTY

WORKING DAYS: 80
DBE CONTRACT OBLIGATION: 4 % COST OF PLANS: $ 3.00

for constructing the Resurfacing, Widening, and Traffic Stripe on SR-9 from the Clay County Line to I-20. Length 10.330 mi.

BRACKET ESTIMATE: $3,152,580 TO $3,853,153

*** WITHDRAWN FROM LETTING ***

077 . STPAA-0017(551) WASHINGTON COUNTY

LENGTH: 7.65 MILES.

WORKING DAYS: 40
DBE CONTRACT OBLIGATION: 5 % COST OF PLANS: $ 6.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-17 from SR-57 (US-45) to 1.37 miles south of CR-20 south of Tibbie. Length 7.649 mi.

BRACKET ESTIMATE: $1,269,920 TO $1,552,125

VIEW ITEMS


078 . STPAA-0021(546) ESCAMBIA COUNTY

WORKING DAYS: 45
DBE CONTRACT OBLIGATION: 5 % COST OF PLANS: $ 9.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-21 from 0.2 miles south of I-65 (MP 7.947) to the south abutment of the Little River Bridge. Length 10.760 mi.

BRACKET ESTIMATE: $1,997,313 TO $2,441,160

*** WITHDRAWN FROM LETTING ***

079 . STPAA-0109(500) HOUSTON COUNTY

LENGTH: 9.79 MILES.

WORKING DAYS: 45
DBE CONTRACT OBLIGATION: 4 % COST OF PLANS: $ 6.00

for constructing the Resurfacing and Traffic Stripe on SR-109 from the Florida State Line to the pavement joint at SR-1 (US-231). Length 9.794 mi.

BRACKET ESTIMATE: $1,953,270 TO $2,387,330

VIEW ITEMS


080 . STPAA-0127(500) LIMESTONE COUNTY

LENGTH: 4.59 MILES.

WORKING DAYS: 30
DBE CONTRACT OBLIGATION: 5 % COST OF PLANS: $ 3.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-127 from the intersection of SR-99 to CR-273 (Maples Circle) (MP 4.590). Length 4.589 mi.

BRACKET ESTIMATE: $1,040,976 TO $1,272,304

VIEW ITEMS


082 . STPAA-0233(502) MARION COUNTY

LENGTH: 4.60 MILES.

WORKING DAYS: 30
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 3.00

for constructing the Resurfacing and Traffic Stripe on SR-233 from 2.2 miles south of CR-92 (MP 10.000) to the intersection of SR-74 (US-278) (MP 14.561). Length 4.597 mi.

BRACKET ESTIMATE: $953,197 TO $1,165,018

VIEW ITEMS


083 . STPAA-7804(602) AUTAUGA & ELMORE COUNTIES

WORKING DAYS: 30
DBE CONTRACT OBLIGATION: 5 % COST OF PLANS: $ 8.00

for constructing the Resurfacing and Traffic Stripe on CR-2 (Cobbs Ford Road) from CR-75 (McQueen Smith Road) to SR-6 (US-82) in Prattville. Length 0.757 mi.

BRACKET ESTIMATE: $395,964 TO $483,956

*** WITHDRAWN FROM LETTING ***

084 . STPAA-7806(600) AUTAUGA COUNTY

WORKING DAYS: 30
COST OF PLANS: $ 5.00

for constructing the Resurfacing and Traffic Stripe on CR-2 (Wetumpka Street) from the junction of CR-2 (North Washington Street) to the junction of SR-3 (US-31, South Memorial Drive) in Prattville. Length 1.072 mi.

BRACKET ESTIMATE: $226,491 TO $276,822

*** WITHDRAWN FROM LETTING ***

086 . STPAA-HSIP-0015(524) COVINGTON COUNTY

LENGTH: 2.14 MILES.

WORKING DAYS: 40
DBE CONTRACT OBLIGATION: 5 % COST OF PLANS: $11.00

for constructing the Resurfacing, Safety Widening, and Traffic Stripe on SR-15 from the intersection of SR-55 to East Three Notch Street in Andalusia. Length 2.143 mi.

BRACKET ESTIMATE: $762,376 TO $931,793

VIEW ITEMS


088 . STPAA-HSIP-0068(507) CHEROKEE COUNTY

LENGTH: 7.02 MILES.

WORKING DAYS: 60
DBE CONTRACT OBLIGATION: 5 % COST OF PLANS: $ 9.00

for constructing the Widening, Resurfacing, and Traffic Stripe on SR-68 from the Dekalb County Line to the intersection of SR-25 (US-411) in Leesburg. Length 7.020 mi.

BRACKET ESTIMATE: $1,669,673 TO $2,040,712

VIEW ITEMS


089 . STPAA-HSIP-0085(501) GENEVA & DALE COUNTIES

LENGTH: 12.23 MILES.

WORKING DAYS: 100
DBE CONTRACT OBLIGATION: 5 % COST OF PLANS: $15.00

for constructing the Resurfacing, Safety Widening, and Traffic Stripe on SR-85 from the junction of SR-27 in Geneva to the junction of SR-167. Length 12.232 mi.

BRACKET ESTIMATE: $3,749,463 TO $4,582,677

VIEW ITEMS


092 . STPAA-HSIP-0125(502) PIKE COUNTY

LENGTH: 6.22 MILES.

WORKING DAYS: 50
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $11.00

for constructing the Resurfacing, Safety Widening, and Traffic Stripe on SR-125 from the Coffee County Line to the junction of SR-53 (US-231). Length 6.219 mi.

BRACKET ESTIMATE: $1,624,079 TO $1,984,985

VIEW ITEMS


094 . STPAA-HSIP-0153(500) GENEVA COUNTY

LENGTH: 8.90 MILES.

WORKING DAYS: 75
DBE CONTRACT OBLIGATION: 4 % COST OF PLANS: $13.00

for constructing the Safety Widening, Resurfacing, and Traffic Stripe on SR-153 from the Florida State Line to the intersection of SR-52. Length 8.980 mi.

BRACKET ESTIMATE: $2,690,459 TO $3,288,338

VIEW ITEMS


098 . STPNU-1600(228) COFFEE COUNTY

LENGTH: 2.42 MILES.

WORKING DAYS: 30
DBE CONTRACT OBLIGATION: 3 % COST OF PLANS: $ 3.00

for constructing the Resurfacing and Traffic Stripe on CR-537 from the junction of CR-555 to the junction of SR-134 in Enterprise. Length 2.421 mi.

BRACKET ESTIMATE: $380,615 TO $465,196

VIEW ITEMS


102 . 99-401-224-I65-401 CULLMAN COUNTY

LENGTH: 26.89 MILES.

WORKING DAYS: 24
COST OF PLANS: $ 4.00

for the Litter Collection and Maintenance Roadside Mowing on I-65 from the Blount County Line to the Morgan County Line.

BRACKET ESTIMATE: $60,772 TO $74,276

VIEW ITEMS


103 . 99-401-253-I59-401 DEKALB COUNTY

LENGTH: 42.49 MILES.

WORKING DAYS: 42
COST OF PLANS: $ 4.00

for the Litter Collection and Maintenance Roadside Mowing on I-59 from the Etowah County Line to the Georgia State Line.

BRACKET ESTIMATE: $114,324 TO $139,730

VIEW ITEMS


104 . 99-507-690-000-301 BARBOUR , COFFEE , GENEVA & PIKE COUNTIES

WORKING DAYS: 75
COST OF PLANS: $15.00

for constructing the Pile Encasements and Riprap Placement on Various Bridges in the Seventh Division.

BRACKET ESTIMATE: $344,882 TO $421,522

VIEW ITEMS


200 . HPP-A138(900) TUSCALOOSA COUNTY

LENGTH: 0.77 MILES.

WORKING DAYS: 90
COST OF PLANS: $ 6.00

for constructing the Pedestrian Improvements at various locations in the City of Northport. Length 0.434 mi.

BRACKET ESTIMATE: $221,753 TO $271,031

VIEW ITEMS

Return To: Top of this Page