Office Engineer

Proposal Letting List
December 05, 2014, Transportation Letting

Welcome to the Proposal Letting List Page. You may view the approximate items of work with each proposal as a "printer friendly" page by clicking on the View Items hyperlink. Adobe Acrobat Reader will now be required to view the "View Items" pages. Please e-mail us with your comments.

4. ACBR58351-ATRP(007), MACON 5. ACBR61143-ATRP(008), LEE
8. ACBRZ58361-ATRP(001), CALHOUN 9. ACBRZ59635-ATRP(007), MACON
12. ACNU59328-ATRP(007), CHOCTAW 13. ACNU59340-ATRP(003), MONROE
14. ACOA59519-ATRP(001), BALDWIN 15. ACNU59564-ATRP(008), CHAMBERS
16. ACNU60472-ATRP(005), LOWNDES 17. ACNU60580-ATRP(008), WINSTON
18. ACNU61272-ATRP(008), CULLMAN 19. ACNU61342-ATRP(003), CHOCTAW
20. ACNU61368-ATRP(007), MONROE 23. NH-0147(502), LEE
*24. ACNU59343-ATRP(004), MONROE 25. ACOA59518-ATRP(009), WALKER
26. ACOA59566-ATRP(006), LEE 27. ACOA8543-8828(601), COLBERT
33. ER-8950(967), DALLAS 35. ERPR-8960(917), CLARKE
36. ERPR-8960(919), WILCOX 37. ERPR-8930(921), ESCAMBIA
43. IMF-I059(361), GREENE 45. NH-0008(573), MONTGOMERY
46. NH-0009(555), MONTGOMERY 47. NH-0035(527), DEKALB
48. NH-HSIP-0012(559), CLARKE 51. STPAA-0003(589), SHELBY
52. STPAA-0016(516), BALDWIN 53. STPOA-0021(549), ESCAMBIA
54. STPAA-0021(551), WILCOX 56. STPAA-HSIP-0007(539), DEKALB
57. STPAA-HSIP-0008(578), MACON 58. STPAA-HSIP-0015(525), MACON
59. STPAA-HSIP-0025(539), BIBB 60. STPAA-HSIP-0131(500), BARBOUR
61. STPAA-HSIP-0164(500), WILCOX 66. ST-003-001-005, BARBOUR
*67. ST-067-999-005, WINSTON
*-WITHDRAWN FROM THE LETTING

The Bracket Ranges shown herein are to provide general financial information to Contractors and Bonding Companies concerning a Project's complexity and size. THESE BRACKETS SHOULD NOT BE USED IN PREPARING A BID, NOR WILL THESE BRACKETS HAVE ANY BEARING ON THE DECISION TO AWARD ANY CONTRACT.


4.ACBR58351-ATRP(007) ,MACON COUNTY

Contract Time: 160 Working Days

DBE Goal Percent: 5.00

for constructing the Bridge Replacement on CR-22 over Chewacla Creek east of Tuskegee. Length 0.273 mi.

The Bracket Estimate on this project is from $2,288,061 to $2,796,519 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $14.00 per set.

View Items

Return To: Proposal Letting List (Top of this web page)


5.ACBR61143-ATRP(008) ,LEE COUNTY

Contract Time: 75 Working Days

DBE Goal Percent: 5.00

for constructing the Bridge Replacement on CR-10 over Chewacla Creek south of the Auburn City Limits. Length 0.021 mi.

The Bracket Estimate on this project is from $573,481 to $700,921 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $9.00 per set.

View Items

Return To: Proposal Letting List (Top of this web page)


8.ACBRZ58361-ATRP(001) ,CALHOUN COUNTY

Contract Time: 60 Working Days

DBE Goal Percent: 2.00

for constructing the Bridge Replacement on CR-554 (Ranch Road) over an Unnamed Tributary to Tallasseehatchee Creek. Length 0.150 mi.

The Bracket Estimate on this project is from $621,881 to $760,076 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $6.00 per set.

View Items

Return To: Proposal Letting List (Top of this web page)


9.ACBRZ59635-ATRP(007) ,MACON COUNTY

Contract Time: 160 Working Days

DBE Goal Percent: 1.00

for constructing the Bridge Replacement on CR-7 (Cross Keys Road) over Cubahatchee Creek southeast of Shorter. Length 0.171 mi.

The Bracket Estimate on this project is from $1,406,972 to $1,719,633 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $8.00 per set.

View Items

Return To: Proposal Letting List (Top of this web page)


12.ACNU59328-ATRP(007), ACNU61337-ATRP(007) & ACNU61338-ATRP(007) ,CHOCTAW COUNTY

Contract Time: 65 Working Days

DBE Goal Percent: 5.00

for constructing the Resurfacing and Traffic Stripe on CR-14 and CR-25 from the junction of CR-21 to the junction of CR-9 (Site #1); on CR-23 (Ararat Road) from the junction of McCarty's Ferry Road to the junction of CR-43 (Site #2); and on CR-23 (Ararat Road) from the junction of CR-43 to the junction SR-17 (Site #3). Length 15.902 mi.

The Bracket Estimate on this project is from $3,053,368 to $3,731,895 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $4.00 per set.

View Items

Return To: Proposal Letting List (Top of this web page)


13.ACNU59340-ATRP(003) ,MONROE COUNTY

Contract Time: 35 Working Days

for constructing the Resurfacing and Traffic Stripe on CR-23 (Perdue Hill Road) from the junction of SR-21 to the Frisco City Limits. Length 1.533 mi.

The Bracket Estimate on this project is from $244,083 to $298,324 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of this web page)


14.ACOA59519-ATRP(001) ,BALDWIN COUNTY

Contract Time: 180 Working Days

DBE Goal Percent: 10.00

for constructing the Widening, Resurfacing, and Traffic Stripe on Wilters Street from the intersection of SR-59 to Rock Creek to include the extension of Wilters Street from Rock Creek to the junction of CR-83 (Baldwin Beach Express) in Robertsdale. Length 2.575 mi.

The Bracket Estimate on this project is from $1,412,514 to $1,726,406 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $55.00 per set.

View Items

Return To: Proposal Letting List (Top of this web page)


15.ACNU59564-ATRP(008) ,CHAMBERS COUNTY

Contract Time: 30 Working Days

DBE Goal Percent: 3.00

for constructing the Resurfacing and Traffic Stripe on CR-62 from the intersection of CR-54 to the junction of SR-77 northwest of Lafayette. Length 6.621 mi.

The Bracket Estimate on this project is from $1,151,677 to $1,407,606 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of this web page)


16.ACNU60472-ATRP(005) ,LOWNDES COUNTY

Contract Time: 45 Working Days

DBE Goal Percent: 3.00

for constructing the Resurfacing and Traffic Stripe on CR-37 from the junction of SR-8 (US-80) to the junction of CR-54. Length 3.881 mi.

The Bracket Estimate on this project is from $839,285 to $1,025,793 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $5.00 per set.

View Items

Return To: Proposal Letting List (Top of this web page)


17.ACNU60580-ATRP(008) ,WINSTON COUNTY

Contract Time: 30 Working Days

DBE Goal Percent: 4.00

for constructing the Resurfacing and Traffic Stripe on CR-22 from the junction of CR-77 to the Cullman County Line. Length 5.644 mi.

The Bracket Estimate on this project is from $590,573 to $721,811 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of this web page)


18.ACNU61272-ATRP(008) ,CULLMAN COUNTY

Contract Time: 30 Working Days

DBE Goal Percent: 4.00

for constructing the Resurfacing and Traffic Stripe on CR-1114 from the junction of SR-74 (US-278) to the junction of SR-157. Length 6.094 mi.

The Bracket Estimate on this project is from $842,400 to $1,029,600 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of this web page)


19.ACNU61342-ATRP(003) ,CHOCTAW COUNTY

Contract Time: 30 Working Days

DBE Goal Percent: 4.00

for constructing the Resurfacing and Traffic Stripe on CR-6 from the intersection of CR-31 in Bladon Springs to the junction of SR-12 (US-84). Length 3.755 mi.

The Bracket Estimate on this project is from $755,496 to $923,384 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of this web page)


20.ACNU61368-ATRP(007) ,MONROE COUNTY

Contract Time: 45 Working Days

DBE Goal Percent: 1.00

for constructing the Resurfacing and Traffic Stripe on CR-5 from the junction of CR-30 to Murder Creek. Length 9.844 mi.

The Bracket Estimate on this project is from $1,897,668 to $2,319,372 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of this web page)


23.NH-0147(502), ACOA58414-ATRP(005) & ACAA61107-ATRP(016), LEE COUNTY

Contract Time: 120 Working Days

DBE Goal Percent: 4.00

for constructing the Resurfacing, Traffic Stripe, and Intersection Improvements on Various Routes in Auburn as indicated in the plans. Length 2.807 mi.

The Bracket Estimate on this project is from $1,772,147 to $2,165,957 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $29.00 per set.

View Items

Return To: Proposal Letting List (Top of this web page)


24. ACNU59343-ATRP(004) & ACNU59344-ATRP(004),MONROE COUNTY

Contract Time: 140 Working Days

DBE Goal Percent: 5.00

for constructing the Resurfacing and Traffic Stripe on CR-20 (Drewry Road) from south of the junction of SR-41 (South Alabama Avenue) to the Monroeville City Limits to include the Intersection Realignment of CR-20 (Drewry Road) and SR-41 (South Alabama Avenue) in Monroeville. Length 2.148 mi.

The Bracket Estimate on this project is from $1,070,840 to $1,308,805 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $23.00 per set.

**WITHDRAWN FROM THE LETTING**

Return To: Proposal Letting List (Top of this web page)


25.ACOA59518-ATRP(009) ,WALKER COUNTY

Contract Time: 35 Working Days

DBE Goal Percent: 3.00

for constructing the Planing, Resurfacing, and Traffic Stripe on CR-358 (Old Birmingham Highway) from the junction of Commerce Avenue to the intersection of CR-371 (Industrial Parkway) in Jasper. Length 2.401 mi.

The Bracket Estimate on this project is from $694,269 to $848,552 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of this web page)


26.ACOA59566-ATRP(006) ,LEE COUNTY

Contract Time: 120 Working Days

DBE Goal Percent: 7.00

for constructing the Intersection Improvements at CR-48 (Opelika Road) and CR-706 (East University Drive) in Auburn. Length 0.507 mi.

The Bracket Estimate on this project is from $1,148,215 to $1,403,373 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $24.00 per set.

View Items

Return To: Proposal Letting List (Top of this web page)


27.ACOA8543-8828(601) ,COLBERT COUNTY

Contract Time: 280 Working Days

DBE Goal Percent: 10.00

for constructing the Additional Lanes (Grade, Drain, Base, and Pave) on Avalon Avenue from the intersection of SR-133 (Wilson Dam Road) to just east of Webster Street in Muscle Shoals. Length 0.845 mi.

The Bracket Estimate on this project is from $3,717,582 to $4,543,711 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $39.00 per set.

View Items

Return To: Proposal Letting List (Top of this web page)


33.ER-8950(967) ,DALLAS COUNTY

Contract Time: 30 Working Days

for constructing the Permanent Slope Repair (Grade, Drain, Base, and Pave) on CR-4 approximately 0.9 miles west of CR-85. Length 0.284 mi.

The Bracket Estimate on this project is from $145,908 to $178,332 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $8.00 per set.

View Items

Return To: Proposal Letting List (Top of this web page)


35.ERPR-8960(917) ,CLARKE COUNTY

Contract Time: 30 Working Days

for constructing the Slide Repair and Permanent Restoration on SR-13 (US-43) from CR-203 (Bear Fork Road) to 0.2 miles north of CR-203 south of Fulton. Length 0.018 mi.

The Bracket Estimate on this project is from $181,457 to $221,780 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $12.00 per set.

View Items

Return To: Proposal Letting List (Top of this web page)


36.ERPR-8960(919) ,WILCOX COUNTY

Contract Time: 90 Working Days

for constructing the Slide Repair and Permanent Restoration on SR-41 from 0.3 miles north of CR-12 to 0.6 miles north of CR-12. Length 0.184 mi.

The Bracket Estimate on this project is from $991,600 to $1,211,955 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $31.00 per set.

View Items

Return To: Proposal Letting List (Top of this web page)


37.ERPR-8930(921) ,CONECUH AND ESCAMBIA COUNTIES

Contract Time: 340 Working Days

DBE Goal Percent: 10.00

for constructing the Divisionwide Emergency Repairs at Various Sites as indicated in the plans.

The Bracket Estimate on this project is from $2,430,589 to $2,970,720 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $79.00 per set.

View Items

Return To: Proposal Letting List (Top of this web page)


43.IMF-I059(361) ,GREENE COUNTY

Contract Time: 125 Working Days

DBE Goal Percent: 3.00

for constructing the Bridge Guardrail Retrofit, Guardrail Replacement, Resurfacing, and Traffic Stripe on I-59 from the SR-14 Interchange (MP 40.307) to the CR-211 Overpass (MP 46.989) to include the Bridge Raisings at CR-170 and SR-14. Length 6.682 mi.

The Bracket Estimate on this project is from $5,698,569 to $6,964,918 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $38.00 per set.

View Items

Return To: Proposal Letting List (Top of this web page)


45.NH-0008(573) ,MONTGOMERY COUNTY

Contract Time: 70 Working Days

DBE Goal Percent: 3.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-8 (US-80) from the western city limits of Montgomery (MP 125.300) to the junction of I-65 (MP 129.595). Length 4.294 mi.

The Bracket Estimate on this project is from $3,136,294 to $3,833,248 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $4.00 per set.

View Items

Return To: Proposal Letting List (Top of this web page)


46.NH-0009(555) ,MONTGOMERY COUNTY

Contract Time: 120 Working Days

DBE Goal Percent: 5.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-9 from the junction of I-85 (MP 107.588) to the junction of SR-9 (US-231) (MP 111.920). Length 4.331 mi.

The Bracket Estimate on this project is from $3,964,982 to $4,846,089 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $5.00 per set.

View Items

Return To: Proposal Letting List (Top of this web page)


47.NH-0035(527) ,DEKALB COUNTY

Contract Time: 110 Working Days

DBE Goal Percent: 10.00

for constructing the Mandatory Brake Check Area (Grade, Drain, Base, Pave, and Lighting) on SR-35 just south of CR-89 (Desoto Parkway) from MP 18.840 to MP 19.100. Length 0.490 mi.

The Bracket Estimate on this project is from $1,430,704 to $1,748,638 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $30.00 per set.

View Items

Return To: Proposal Letting List (Top of this web page)


48.NH-HSIP-0012(559) ,CLARKE COUNTY

Contract Time: 55 Working Days

DBE Goal Percent: 4.00

for constructing the Safety Widening, Resurfacing, and Traffic Stripe on SR-12 (US-84) from 0.5 miles west of the junction of CR-3 (Winn Road) to 0.9 miles north of the junction of CR-23 west of Grove Hill. Length 8.090 mi.

The Bracket Estimate on this project is from $1,448,061 to $1,769,852 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $6.00 per set.

View Items

Return To: Proposal Letting List (Top of this web page)


51.STPAA-0003(589) ,SHELBY COUNTY

Contract Time: 45 Working Days

DBE Goal Percent: 4.00

for constructing the Planing, Resurfacing, Guardrail, and Traffic Stripe on SR-3 (US-31) from the junction of 7th Avenue in Calera to the south end of the I-65 Overpass (MP 245.649). Length 2.229 mi.

The Bracket Estimate on this project is from $476,868 to $582,839 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $4.00 per set.

View Items

Return To: Proposal Letting List (Top of this web page)


52.STPAA-0016(516) ,BALDWIN COUNTY

Contract Time: 35 Working Days

DBE Goal Percent: 3.00

for constructing the Resurfacing and Traffic Stripe on SR-16 (US-90) from the east end of Blakeley River Bridge (MP 42.718) to just west of the I-10 Westbound Ramp (MP 44.083). Length 1.364 mi.

The Bracket Estimate on this project is from $683,860 to $835,829 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $8.00 per set.

View Items

Return To: Proposal Letting List (Top of this web page)


53.STPOA-0021(549) ,ESCAMBIA COUNTY

Contract Time: 45 Working Days

DBE Goal Percent: 3.00

for constructing the Resurfacing and Traffic Stripe on SR-21 from just north of the intersection of Sunset Drive (the beginning of the four-lane section) to just south of the junction of CR-14. Length 3.705 mi.

The Bracket Estimate on this project is from $1,295,532 to $1,583,428 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $9.00 per set.

View Items

Return To: Proposal Letting List (Top of this web page)


54.STPAA-0021(551) ,WILCOX COUNTY

Contract Time: 65 Working Days

DBE Goal Percent: 5.00

for constructing the Resurfacing and Traffic Stripe on SR-21 from the junction of SR-28 to the intersection of CR-59 (Freedom Farm Road) in Furman. Length 7.331 mi.

The Bracket Estimate on this project is from $1,579,771 to $1,930,831 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $6.00 per set.

View Items

Return To: Proposal Letting List (Top of this web page)


56.STPAA-HSIP-0007(539) ,DEKALB COUNTY

Contract Time: 65 Working Days

DBE Goal Percent: 6.00

for constructing the Safety Widening, Resurfacing, and Traffic Stripe on SR-7 (US-11) from north of the Fort Payne City Limits (MP 236.660) to the Georgia State Line. Length 13.670 mi.

The Bracket Estimate on this project is from $3,626,101 to $4,431,902 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $5.00 per set.

View Items

Return To: Proposal Letting List (Top of this web page)


57.STPAA-HSIP-0008(578) ,MACON COUNTY

Contract Time: 65 Working Days

DBE Goal Percent: 3.00

for constructing the Safety Widening, Resurfacing, and Traffic Stripe on SR-8 (US-80) from east of Frazier Street (MP 174.667) to the junction of SR-15 (US-29) (MP 181.268) Length 6.600 mi.

The Bracket Estimate on this project is from $2,407,095 to $2,942,005 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $4.00 per set.

View Items

Return To: Proposal Letting List (Top of this web page)


58.STPAA-HSIP-0015(525) ,MACON COUNTY

Contract Time: 50 Working Days

DBE Goal Percent: 4.00

for constructing the Safety Widening, Resurfacing, and Traffic Stripe on SR-15 (US-29) from the junction of SR-8 (US-80) to the Lee County Line. Length 4.235 mi.

The Bracket Estimate on this project is from $1,764,744 to $2,156,909 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $4.00 per set.

View Items

Return To: Proposal Letting List (Top of this web page)


59.STPAA-HSIP-0025(539) ,BIBB COUNTY

Contract Time: 150 Working Days

DBE Goal Percent: 3.00

for constructing the Safety Widening, Resurfacing, and Traffic Stripe on SR-25 from the Hale County Line (MP 70.740) to the junction of SR-5 (MP 84.730) in Harrisburg. Length 13.985 mi.

The Bracket Estimate on this project is from $4,179,208 to $5,107,921 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $7.00 per set.

View Items

Return To: Proposal Letting List (Top of this web page)


60.STPAA-HSIP-0131(500) & STPAA-HSIP-0131(501), BARBOUR COUNTY

Contract Time: 140 Working Days

DBE Goal Percent: 3.00

for constructing the Safety Widening, Resurfacing, and Traffic Stripe on SR-131 from two hundred twenty-five feet south of the intersection of CR-79 in Baker Hill to the junction of SR-1 (US-431) in Eufaula (Site #1) and on SR-131 from the intersection of CR-53 in Texasville to two hundred twenty-five feet south of the intersection of CR-79 in Baker Hill (Site #2). Length 19.047 mi.

The Bracket Estimate on this project is from $4,781,949 to $5,844,604 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $29.00 per set.

View Items

Return To: Proposal Letting List (Top of this web page)


61.STPAA-HSIP-0164(500) & STPAA-HSIP-0221(500) ,WILCOX COUNTY

Contract Time: 40 Working Days

DBE Goal Percent: 3.00

for constructing the Safety Widening, Resurfacing, and Traffic Stripe on SR-164 from the junction of SR-10 to the intersection of SR-28 (Broad Street) in Camden (Site #1) and on SR-221 from the junction of SR-41 to the intersection of SR-10 in Camden (Site #2). Length 4.273 mi.

The Bracket Estimate on this project is from $945,221 to $1,155,270 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $6.00 per set.

View Items

Return To: Proposal Letting List (Top of this web page)


66.ST-003-001-005 ,BARBOUR COUNTY

Contract Time: 4/1/2015 Completion Date

for constructing the Minor Widening on SR-1 (US-431) from north of the intersection of Broad Street to four hundred feet south of the junction of Cotton Avenue in Eufaula. Length 0.800 mi.

The Bracket Estimate on this project is from $668,392 to $816,923 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $12.00 per set.

A MANDATORY pre-bid conference is scheduled for 10:00 a.m. on Tuesday, November 25, 2014, at the Department of Transportation; District 6 Project Office; 760 Highway 30; Eufaula, AL 36072 Any qualified bidder wishing to bid this proposal is required to have a company representative present at this MANDATORY pre-bid conference. Proposals issued to bidders who fail to attend the MANDATORY pre-bid conference and/or register their attendance will be voided and their bids will not be received nor considered.

View Items

Return To: Proposal Letting List (Top of this web page)


67.ST-067-999-005 ,WINSTON COUNTY

Contract Time: 150 Working Days

for constructing the Culvert Replacement on SR-13 at CR-7 (Dime Road) in Haleyville. Length 0.151 mi.

The Bracket Estimate on this project is from $888,172 to $1,085,544 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $21.00 per set.

A MANDATORY pre-bid conference is scheduled for 10:00 a.m. on Friday, November 21, 2014, at the Haleyville City Hall Courtroom; 1901 11th Avenue; Haleyville, AL 35565 Any qualified bidder wishing to bid this proposal is required to have a company representative present at this MANDATORY pre-bid conference. Proposals issued to bidders who fail to attend the MANDATORY pre-bid conference and/or register their attendance will be voided and their bids will not be received nor considered.

**WITHDRAWN FROM THE LETTING**

Return To: Proposal Letting List (Top of this web page)