Office Engineer

Proposal Letting List
September 25, 2015, Transportation Letting

Welcome to the Proposal Letting List Page. We now include the approximate items of work with each proposal. Please e-mail us with your comments.

1. APDF-0471(535), JEFFERSON 5. NHF-0053(530), ETC., MADISON
7. ACAA58379-ATRP(002), JEFFERSON 10. ACBR61185-ATRP(008), MOBILE
14. ACBRZ59384-ATRP(003), ETOWAH 15. ACBRZ59784-ATRP(012), ST. CLAIR
16. ACBRZ60320-ATRP(002), FAYETTE 17. ACBRZ60409-ATRP(011), COOSA
18. ACBRZ61144-ATRP(015), LEE *21. ACNU60291-ATRP(005), ETC., BIBB
24. ACOA59679-ATRP(016), MORGAN 26. ACOA61865-ATRP(017), TUSCALOOSA
29. BR-0003(580), LIMESTONE 33. BR-0041(501), ESCAMBIA
37. CMAQ-9802(929), JEFFERSON 45. IM-I065(451), AUTAUGA
46. IM-I085(345), CHAMBERS 47. IM-I085(346), LEE
50. NH-0378(500), JEFFERSON 56. SB-NR13(955), TUSCALOOSA
63. STPNU-1514(254), CLEBURNE 66. STPNU-5014(250), MONROE
73. 99-506-513-008-505, MONTGOMERY 74. 99-508-692-000-520, WILCOX
*- WITHDRAWN FROM THE LETTING

The Bracket Ranges shown herein are to provide general financial information to Contractors and Bonding Companies concerning a Project's complexity and size. THESE BRACKETS SHOULD NOT BE USED IN PREPARING A BID, NOR WILL THESE BRACKETS HAVE ANY BEARING ON THE DECISION TO AWARD ANY CONTRACT.


1.APDF-0471(535) ,JEFFERSON COUNTY

Contract Time: 60 Working Days

for constructing the Roadway Lighting on Corridor X (Future I-22) from 4500 feet west of I-65 to the I-65 Route Interchange in Birmingham. Length 1.041 mi.

The Bracket Estimate on this project is from $557,308 to $681,154 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $11.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


5.NHF-0053(530), NHF-0053(531) & ST-045-053-008 ,MADISON COUNTY

Contract Time: 6/1/2019 Completion Date

DBE Goal Percent:5.00

for constructing the Roadway Improvements (Grade, Drain, Base, Pave, Bridge Removal/Installations, Retaining Walls, Signing, Signals, and Lighting) on SR-53 (US-231/Memorial Parkway) from just north of the junction of Whitesburg Drive to just south of the junction of Golf Road to include the Interchange of Frontage Road and Martin Road in Huntsville. Length 4.080 km.

The Bracket Estimate on this project is from $40,000,000 to $50,000,000 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $337.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


7.ACAA58379-ATRP(002) ,JEFFERSON COUNTY

Contract Time: 180 Working Days

DBE Goal Percent:6.00

for constructing the Roadway Improvements (Grade, Drain, Base, Pave, Culvert Extensions, Resurfacing, and Signal Installation) on CR-153 from 500 feet south of the I-59 Overpass to north of CR-2133 in Trussville. Length 0.440 mi.

The Bracket Estimate on this project is from $1,509,217 to $1,844,598 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $24.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


10.ACBR61185-ATRP(008) ,MOBILE COUNTY

Contract Time: 240 Working Days

DBE Goal Percent:5.00

for constructing the Bridge Replacement and Approaches on CR-23 (Padgett Switch Road) over Carls Creek in Bayou La Batre. Length 0.467 mi.

The Bracket Estimate on this project is from $2,862,083 to $3,498,102 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $35.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


14.ACBRZ59384-ATRP(003) ,ETOWAH COUNTY

Contract Time: 80 Working Days

DBE Goal Percent:5.00

for constructing the Bridge Replacement on Tuscaloosa Avenue over Black Creek in Gadsden. Length 0.154 mi.

The Bracket Estimate on this project is from $779,043 to $952,163 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $15.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


15.ACBRZ59784-ATRP(012) ,ST. CLAIR COUNTY

Contract Time: 55 Working Days

DBE Goal Percent:4.00

for constructing the Bridge Rehabilitation on CR-80 (Rivercrest Drive) over Logan Martin Lake northeast of Vincent. Length 0.031 mi.

The Bracket Estimate on this project is from $790,713 to $966,428 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $9.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


16.ACBRZ60320-ATRP(002) ,FAYETTE COUNTY

Contract Time: 80 Working Days

for constructing the Bridge Replacement and Approaches on CR-186 (Overhead Road) over Deadwater Creek west of Berry. Length 0.102 mi.

The Bracket Estimate on this project is from $363,472 to $444,243 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $7.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


17.ACBRZ60409-ATRP(011) ,COOSA COUNTY

Contract Time: 60 Working Days

for constructing the Bridge Replacement and Approaches on CR-68 over Shelton Creek north of Stewartville. Length 0.132 mi.

The Bracket Estimate on this project is from $426,611 to $521,414 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $7.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


18.ACBRZ61144-ATRP(015) ,LEE COUNTY

Contract Time: 45 Working Days

for constructing the Bridge Replacement on CR-156 over a Tributary to Halawakee Creek east of Opelika. Length 0.006 mi.

The Bracket Estimate on this project is from $249,291 to $304,689 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $6.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


21.ACNU60291-ATRP(005), ACNU60292-ATRP(015) & ACNU60294-ATRP(006) ,BIBB COUNTY

Contract Time: 90 Working Days

DBE Goal Percent:4.00

for constructing the Resurfacing and Traffic Stripe on CR-12 (Grey Hill Road) from 0.3 mile west of the junction of CR-282 west of Green Pond to the Shelby County Line (Site #1); on CR-9/CR-24 (Vance Road) from the Tuscaloosa County Line to the intersection of SR-5 in West Blocton (Site #2); and on CR-26 (Haysop Church Road) from the intersection of SR-6 (US-82) to the junction of CR-131 northwest of Eoline (Site #3). Length 12.744 mi.

The Bracket Estimate on this project is from $2,511,220 to $3,069,269 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $10.00 per set.

*** WITHDRAWN FROM THE LETTING ***

Return To: Proposal Letting List (Top of web page)


24.ACOA59679-ATRP(016) ,MORGAN COUNTY

Contract Time: 30 Working Days

DBE Goal Percent:4.00

for constructing the Resurfacing and Traffic Stripe on CR-606 (Old Highway 24) from the west Town Limits of Trinity to the intersection of CR-204 (Woodall Road). Length 2.927 mi.

The Bracket Estimate on this project is from $612,418 to $748,511 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


26.ACOA61865-ATRP(017) ,TUSCALOOSA COUNTY

Contract Time: 30 Working Days

DBE Goal Percent:3.00

for constructing the Resurfacing and Traffic Stripe on CR-47 (Watermelon Road) from the junction of CR-62 (Union Chapel Road) to the Tuscaloosa City Limits. Length 0.951 mi.

The Bracket Estimate on this project is from $192,924 to $235,797 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $4.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


29.BR-0003(580) ,LIMESTONE COUNTY

Contract Time: 150 Working Days

DBE Goal Percent:6.00

for constructing the Bridge Replacement (Grade, Drain, Base, Pave, and Bridge) of the southbound roadway on SR-3 (US-31) over Swan Creek north of Decatur. Length 0.457 mi.

The Bracket Estimate on this project is from $2,032,794 to $2,484,526 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $27.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


33.BR-0041(501) ,ESCAMBIA COUNTY

Contract Time: 345 Working Days

DBE Goal Percent:5.00

for constructing the Bridge Replacements (Grade, Drain, Base, Pave, and Bridges) on SR-41 (Conecuh River and Relief) in Riverview. Length 0.826 mi.

The Bracket Estimate on this project is from $14,443,844 to $17,653,587 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $63.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


37.CMAQ-9802(929) ,JEFFERSON COUNTY

Contract Time: 150 Working Days

DBE Goal Percent:5.00

for constructing the Trussville Greenway Multi-Use Trail (Grade, Drain, Base, Sidewalk, Retaining Wall, Pedestrian Bridge, and Lighting) along the Cahaba River.

The Bracket Estimate on this project is from $1,424,590 to $1,741,165 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $42.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


45.IM-I065(451) ,AUTAUGA COUNTY

Contract Time: 40 Working Days

DBE Goal Percent:3.00

for constructing the Planing, Resurfacing, and Traffic Stripe on I-65 from south of the SR-3 (US-31) Interchange (MP 186.000) to one mile south of the CR-61 Overpass (MP 190.000) south of Marbury. Length 4.000 mi.

The Bracket Estimate on this project is from $1,257,073 to $1,536,423 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


46.IM-I085(345) ,CHAMBERS COUNTY

Contract Time: 70 Working Days

for constructing the Interchange Lighting Rehabilitation on I-85 at Fob James Drive (Exit 77). Length 0.842 mi.

The Bracket Estimate on this project is from $170,879 to $208,852 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $8.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


47.IM-I085(346) ,LEE COUNTY

Contract Time: 250 Working Days

DBE Goal Percent:1.00

for constructing the Partial Interchange Lighting on I-85 at various sites as indicated in the plans.

The Bracket Estimate on this project is from $789,560 to $965,018 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $22.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


50.NH-0378(500) ,JEFFERSON COUNTY

Contract Time: 75 Working Days

DBE Goal Percent:5.00

for constructing the Pavement Rehabilitation on SR-378 (Finley Boulevard) from the junction of SR-5 (US-78) to the intersection of SR-3 (US-31) in Birmingham. Length 2.302 mi.

The Bracket Estimate on this project is from $2,172,629 to $2,655,436 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $11.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


56.SB-NR13(955) ,TUSCALOOSA COUNTY

Contract Time: 65 Working Days

DBE Goal Percent:2.00

for constructing the Scenic Byway Riverwalk Continuation (Grade, Drain, Base, Pave, Pedestrian Lighting, and Retaining Walls) along the Black Warrior River in Tuscaloosa. Length 0.270 mi.

The Bracket Estimate on this project is from $548,557 to $670,458 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $12.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


63.STPNU-1514(254) ,CLEBURNE COUNTY

Contract Time: 30 Working Days

DBE Goal Percent:3.00

for constructing the Resurfacing and Traffic Stripe on CR-24 from the junction of CR-3 to the junction of SR-1 (US-431) northwest of Hollis Crossroads. Length 4.210 mi.

The Bracket Estimate on this project is from $709,409 to $867,056 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $4.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


66.STPNU-5014(250) ,MONROE COUNTY

Contract Time: 30 Working Days

DBE Goal Percent:2.00

for constructing the Resurfacing and Traffic Stripe on CR-15 from the junction of CR-45 to the junction of Dewise Street south of Megargel. Length 2.948 mi.

The Bracket Estimate on this project is from $635,251 to $776,418 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


73.99-506-513-008-505 ,MONTGOMERY COUNTY

Contract Time: 45 Working Days

for constructing the Bridge Abutment Slope Protection and Joint Seal on SR-8 (US-80) at various locations as indicated in the plans.

The Bracket Estimate on this project is from $214,960 to $262,729 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


74.99-508-692-000-520 ,WILCOX COUNTY

Contract Time: 30 Working Days

for the Bridge Scour Repair on SR-5 at BIN 002264 southwest of Kimbrough.

The Bracket Estimate on this project is from $70,633 to $86,329 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $8.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)