Office Engineer

Proposal Letting List
January 26, 2018, Transportation Letting

Welcome to the Proposal Letting List Page. We now include the approximate items of work with each proposal. Please e-mail us with your comments.

4. NHF-0158(502), MOBILE 9. ACAA61053-ATRP(017), MONTGOMERY
20. ACBRZ59417-ATRP(010), CALHOUN 22. ACBRZ60457-ATRP(012), MARION
24. ACBRZ60568-ATRP(011), LAWRENCE 32. ACNU61881-ATRP(017), ETC., SUMTER
33. ACNU62435-ATRP(004), FRANKLIN 37. ACOA61202-ATRP(006), JACKSON
40. BR-0010(505), CHOCTAW 54. IM-I065(459), MONTGOMERY, ETC.
59. NH-0013(604), WASHINGTON *62. NH-0157(522), LAWRENCE
65. RP-IM-I059(396), JEFFERSON 69. STPNU-0017(571), SUMTER
70. STPAA-0036(509), MORGAN 73. STPAA-0089(502), ETC., WILCOX
76. STPAA-HSIP-0018(510), FAYETTE 78. STPAA-HSIP-0095(506), BARBOUR, ETC.
80. STPAA-HSIP-0189(504), COFFEE 84. STPMN-5114(251), MONTGOMERY
88. STPNU-1416(251), CLAY 89. STPNU-6217(250), TALLAPOOSA
90. STPOA-3517(251), HOUSTON 93. STPOA-NR14(906), LEE
95. ST-063-069-012, TUSCALOOSA 96. 99-508-014-682-720, CHOCTAW, ETC.
200. STPAA-NR13(940), BIBB, ETC.
*-WITHDRAWN FROM THE LETTING

The Bracket Ranges shown herein are to provide general financial information to Contractors and Bonding Companies concerning a Project's complexity and size. THESE BRACKETS SHOULD NOT BE USED IN PREPARING A BID, NOR WILL THESE BRACKETS HAVE ANY BEARING ON THE DECISION TO AWARD ANY CONTRACT.


4.NHF-0158(502) ,MOBILE COUNTY

Contract Time: 420 Working Days

DBE Goal Percent:4.00

for constructing the Roadway Extension (Grading, Drainage, Pavement, and Bridge) on SR-158 from a point east of SR-217 (Lott Road) to the junction of Schillinger Road in Semmes. Length 1.544 mi.

The Bracket Estimate on this project is from $17,475,217 to $21,358,599 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $114.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


9.ACAA61053-ATRP(017) ,MONTGOMERY COUNTY

Contract Time: 50 Working Days

DBE Goal Percent:8.00

for constructing the Planing, Resurfacing, and Traffic Stripe on CR-64 (Wares Ferry Road) from the Montgomery City Limits to the intersection of SR-126 (US-80) in Mt. Meigs. Length 5.596 mi.

The Bracket Estimate on this project is from $1,214,851 to $1,484,818 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $4.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


20.ACBRZ59417-ATRP(010) ,CALHOUN COUNTY

Contract Time: 120 Working Days

DBE Goal Percent:8.00

for constructing the Bridge Replacement (Grading, Drainage, Pavement, and Striping) on CR-533 (Gilbert's Ferry Road) over a tributary to Ohatchee Creek northwest of Wellington. Length 0.371 mi.

The Bracket Estimate on this project is from $1,888,712 to $2,308,426 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $20.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


22.ACBRZ60457-ATRP(012) ,MARION COUNTY

Contract Time: 110 Working Days

DBE Goal Percent:7.00

for constructing the Bridge Replacement and Approaches on CR-369 (Grandview Drive) over Williams Creek in Hamilton. Length 0.139 mi.

The Bracket Estimate on this project is from $1,251,273 to $1,529,334 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $12.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


24.ACBRZ60568-ATRP(011) ,LAWRENCE COUNTY

Contract Time: 100 Working Days

for constructing the Bridge Replacements on CR-165 over an Unnamed Stream northwest of Moulton (Site 1) and on CR-377 over Mallard Creek southwest of Hillsboro (Site 2). Length 0.017 mi.

The Bracket Estimate on this project is from $407,327 to $497,844 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $8.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


32.ACNU61881-ATRP(017), ACBR61888-ATRP(017) & ACBR61889-ATRP(017) ,SUMTER COUNTY

Contract Time: 135 Working Days

DBE Goal Percent:4.00

for constructing the Resurfacing (Full Depth Reclamation) and Traffic Stripe on CR-20 (West Union Road) from the Mississippi State Line to the intersection of SR-17 south of Emelle to include the Bridge Replacements and Approaches over an Unnamed Tributary of Little Sanusi Creek and over Little Sanusi Creek. Length 3.493 mi.

The Bracket Estimate on this project is from $2,493,731 to $3,047,894 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $22.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


33.ACNU62435-ATRP(004) ,FRANKLIN COUNTY

Contract Time: 30 Working Days

DBE Goal Percent:10.00

for constructing the Resurfacing and Traffic Stripe on CR-11 from the Bear Creek Bridge north of Red Bay to the junction of CR-15. Length 6.377 mi. .

The Bracket Estimate on this project is from $423,759 to $517,928 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


37.ACOA61202-ATRP(006) ,JACKSON COUNTY

Contract Time: 100 Working Days

DBE Goal Percent:5.00

for constructing the Resurfacing and Traffic Stripe on Clemons Road from the junction of SR-35 to 0.200 mile south of the junction of Summer Drive in Scottsboro. Length 3.757 mi.

The Bracket Estimate on this project is from $1,648,256 to $2,014,535 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $30.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


40.BR-0010(505) ,CHOCTAW COUNTY

Contract Time: 235 Working Days

DBE Goal Percent:7.00

for constructing the Bridge Replacement and Culvert Extensions (Grading, Drainage, Base, and Pavement) on SR-10 over Bogue Chitto Creek southeast of Lisman. Length 0.814 mi.

The Bracket Estimate on this project is from $7,068,706 to $8,639,529 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $33.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


54.IM-I065(459) ,MONTGOMERY AND ELMORE COUNTIES

Contract Time: 180 Working Days

for constructing the Bridge Repairs (Girders, Caps, and Bearing Pads) on I-65 Relief Bridges 2, 3, and 11.

The Bracket Estimate on this project is from $1,413,746 to $1,727,912 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $10.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


59.NH-0013(604) ,WASHINGTON COUNTY

Contract Time: 65 Working Days

DBE Goal Percent:4.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-13 (US-43) from the Bassetts Creek Bridge to the north end of the Tombigbee River Bridge northeast of Leroy. Length 6.570 mi.

The Bracket Estimate on this project is from $2,577,557 to $3,150,347 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $6.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


62.NH-0157(522) ,LAWRENCE COUNTY

Contract Time: 75 Working Days

DBE Goal Percent:8.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-157 from south of the junction of SR-33 in Moulton to the junction of CR-505/506. Length 4.450 mi.

The Bracket Estimate on this project is from $1,705,303 to $2,084,259 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $4.00 per set.

**** WITHDRAWN FROM THE LETTING ****

Return To: Proposal Letting List (Top of web page)


65.RP-IM-I059(396) ,JEFFERSON COUNTY

Contract Time: 80 Working Days

DBE Goal Percent:4.00

for constructing the Planing, Resurfacing, and Traffic Stripe on I-59 from the Tuscaloosa County Line to the junction of the I-459 Interchange. Length 5.373 mi.

The Bracket Estimate on this project is from $4,361,995 to $5,331,328 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $9.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


69.STPNU-0017(571) ,SUMTER COUNTY

Contract Time: 45 Working Days

DBE Goal Percent:8.00

for constructing the Planing, Resurfacing, Bridge Rail Retrofit, Curb Ramp Installation, and Traffic Stripe on SR-17 from south of the intersection of SR-8 (US-80) to the intersection of SR-7 (US-11) in York. Length 3.988 mi.

The Bracket Estimate on this project is from $1,574,561 to $1,924,464 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $9.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


70.STPAA-0036(509) ,MORGAN COUNTY

Contract Time: 35 Working Days

DBE Goal Percent:7.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-36 from the Lawrence County Line to 0.040 mile west of the junction of New Cut Road. Length 5.310 mi.

The Bracket Estimate on this project is from $1,353,499 to $1,654,277 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


73.STPAA-0089(502) & STPAA-0021(562) ,WILCOX COUNTY

Contract Time: 30 Working Days

DBE Goal Percent:2.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-89 from the junction of SR-21 to the Dallas County Line (Site 1) and on SR-21 from east of the Cedar Creek Bridge (MP 95.461) to the Lowndes County Line (Site 2). Length 5.185 mi.

The Bracket Estimate on this project is from $738,856 to $903,046 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $9.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


76.STPAA-HSIP-0018(510) ,FAYETTE COUNTY

Contract Time: 30 Working Days

DBE Goal Percent:3.00

for constructing the Safety Widening, Planing, Resurfacing, and Traffic Stripe on SR-18 from just west of the junction of CR-125 to the Walker County Line. Length 3.297 mi.

The Bracket Estimate on this project is from $1,339,295 to $1,636,917 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $6.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


78.STPAA-HSIP-0095(506) ,BARBOUR AND HENRY COUNTIES

Contract Time: 65 Working Days

DBE Goal Percent:7.00

for constructing the Safety Widening, Planing, Resurfacing, and Traffic Stripe on SR-95 from the junction of CR-92 to the junction of SR-1 (US-431) in Eufaula. Length 9.442 mi.

The Bracket Estimate on this project is from $2,081,499 to $2,544,055 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $14.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


80.STPAA-HSIP-0189(504) ,COFFEE COUNTY

Contract Time: 55 Working Days

DBE Goal Percent:9.00

for constructing the Safety Widening, Resurfacing, and Traffic Striping on SR-189 from the junction of SR-52 in Kingston to north of the junction of CR-442 northwest of Alberton. Length 5.445 mi.

The Bracket Estimate on this project is from $1,462,477 to $1,787,472 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $15.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


84.STPMN-5114(251) ,MONTGOMERY COUNTY

Contract Time: 75 Working Days

DBE Goal Percent:6.00

for constructing the Planing, Resurfacing, and Traffic Stripe on Wares Ferry Road from the junction of Atlanta Highway to the intersection of SR-53 (US-231/Eastern Boulevard) in Montgomery. Length 2.499 mi.

The Bracket Estimate on this project is from $1,530,055 to $1,870,067 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $5.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


88.STPNU-1416(251) ,CLAY COUNTY

Contract Time: 40 Working Days

for constructing the Resurfacing (Full Depth Reclamation) and Traffic Stripe on Adams Gap Road from the junction of Blue Ridge Road west of Pyriton to the junction of SR-281. Length 1.650 mi.

The Bracket Estimate on this project is from $263,671 to $322,264 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $2.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


89.STPNU-6217(250) ,TALLAPOOSA COUNTY

Contract Time: 30 Working Days

DBE Goal Percent:3.00

for constructing the Resurfacing and Traffic Stripe on CR-75 (Dudleyville Road) from the North City Limits of Dadeville to the junction of CR-32 (Denver Road). Length 5.867 mi.

The Bracket Estimate on this project is from $529,041 to $646,606 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


90.STPOA-3517(251) ,HOUSTON COUNTY

Contract Time: 30 Working Days

DBE Goal Percent:10.00

for constructing the Resurfacing and Traffic Stripe on CR-33 from south of the intersection of Lucy Grade Road to the intersection of SR-12 (US-84) in Ashford. Length 3.704 mi.

The Bracket Estimate on this project is from $530,779 to $648,730 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


93.STPOA-NR14(906) ,LEE COUNTY

Contract Time: 80 Working Days

for constructing the Signalized Intersections via the Centralized Traffic Control Center at various locations in Auburn as indicated in the plans.

The Bracket Estimate on this project is from $818,616 to $1,000,531 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $22.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


95.ST-063-069-012 ,TUSCALOOSA COUNTY

Contract Time: 55 Working Days

for constructing the Additional Lanes, Planing, Resurfacing, and Traffic Stripe on SR-69 from the junction of Maxwell Loop Road to the junction of SR-7 (US-11/Skyland Boulevard) in Tuscaloosa. Length 3.852 mi.

The Bracket Estimate on this project is from $912,550 to $1,115,339 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $13.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


96.99-508-014-682-720 ,CHOCTAW AND MARENGO COUNTIES

Contract Time: 130 Working Days

for the Maintenance Bridge Painting on SR-10 over The Tombigbee River west of Nanafalia. Length 0.755 mi.

The Bracket Estimate on this project is from $610,287 to $745,906 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $6.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


200.STPAA-NR13(940) ,BIBB AND CHILTON COUNTIES

Contract Time: 45 Working Days

for constructing the Sidewalk Improvements (Curb and Ramp Installation) at various locations on SR-25, SR-139, SR-22, SR-145, and SR-3 as indicated in the plans.

The Bracket Estimate on this project is from $268,278 to $327,895 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $21.00 per set.

THIS PROJECT HAS BEEN DESIGNATED AS AN SBE PROJECT, AND CAN ONLY BE BID ON BY QUALIFIED SBE CONTRACTORS THAT HAVE BEEN PRE-APPROVED BY THE ALDOT DBE UNIT AND ALDOT OFFICE ENGINEER.

View Items

Return To: Proposal Letting List (Top of web page)