1. IMF-I085(339), ETC., MONTGOMERY 9. ACBR60321-ATRP(011), FAYETTE
10. ACBR61108-ATRP(016), LEE 14. ACBRZ58501-ATRP(015), TUSCALOOSA
16. ACBRZ60362-ATRP(014), PERRY 17. ACBRZ60383-ATRP(010), PICKENS
18. BRZ-1917(252), ETC., COOSA 19. ACBRZ60447-ATRP(012), WILCOX
22. ACBRZ61315-ATRP(015), MARSHALL 29. ACOA61532-ATRP(005), ESCAMBIA
*36. BR-0006(559), AUTAUGA 41. ER-9010(935), PIKE
48. IM-HSIP-I010(338), MOBILE 52. IM-I059(402), ETC., SUMTER
53. IM-I059(406), TUSCALOOSA 54. IM-I065(483), LIMESTONE
56. IM-I459(315), JEFFERSON 58. NH-0013(606), ETC., CLARKE
59. NH-0009(563), MONTGOMERY 60. NH-0012(562), CONECUH
62. NH-0024(512), LAWRENCE 63. NH-0038(537), TALLAPOOSA, ETC.
64. NH-0059(515), BALDWIN 65. NH-0075(533), JEFFERSON
66. NH-0079(518), JEFFERSON *67. NH-0150(504), JEFFERSON
68. NH-0024(511), LAWRENCE 69. NH-HSIP-0009(552), CRENSHAW
73. RP-IM-I459(311), JEFFERSON 75. STPAA-0071(502), JACKSON
76. STPAA-0033(505), LAWRENCE 78. STPAA-0105(504), DALE, ETC.
79. STPAA-0130(501), PIKE, ETC. *80. STPAA-0155(504), SHELBY
82. STPAA-0223(503), PIKE 83. STPAA-HSIP-0061(505), HALE
85. STPAA-HSIP-0004(544), CALHOUN 86. STPAA-HSIP-0009(564), CLAY
93. STPMN-ACAA59590-ATRP(011), MONTGOMERY 94. STPNU-0079(517), JACKSON
96. STPOA-1115(250), CHILTON 97. STPNU-1617(251), ETC., COFFEE
98. STPNU-4715(250), MARION 99. STPNU-5216(251), MORGAN
102. STPOA-9215(600), MORGAN 105. ST-005-160-007, BLOUNT
108. 99-306-576-208-702, RUSSELL 111. 99-502-391-002-801, LAUDERDALE
113. 99-505-632-215-601, TUSCALOOSA 200. STPAA-NR13(904), DALLAS
*-WITHDRAWN FROM THE LETTING

The Bracket Ranges shown herein are to provide general financial information to Contractors and Bonding Companies concerning a Project's complexity and size. THESE BRACKETS SHOULD NOT BE USED IN PREPARING A BID, NOR WILL THESE BRACKETS HAVE ANY BEARING ON THE DECISION TO AWARD ANY CONTRACT.


1.IMF-I085(339) & NH-0008(568) ,MONTGOMERY COUNTY

Contract Time: 180 Working Days

DBE Goal Percent:7.00

for constructing the Pavement Rehabilitation (Grading, Drainage, Base, Pavement, Resurfacing, Signing, Lighting, and Installation of ITS Devices) on I-85 from west of the SR-8 (US-80/Eastern Boulevard) Interchange to east of the SR-271 (Taylor Road) Interchange to include the Intersection Improvements (Grading, Drainage, Base, Pavement, Signing, and Traffic Signals) on SR-8 (US-231/Eastern Boulevard) at the I-85 Interchange from the intersection of Woodmere Boulevard to north of the junction of Monticello Drive in Montgomery. Length 4.377 mi.

The Bracket Estimate on this project is from $15,135,371 to $18,498,786 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $92.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


9.ACBR60321-ATRP(011) ,FAYETTE COUNTY

Contract Time: 110 Working Days

DBE Goal Percent:5.00

for constructing the Bridge Replacement and Approaches on CR-289 (Jenkins Cemetery Road) over North River north of Berry. Length 0.136 mi.

The Bracket Estimate on this project is from $1,037,162 to $1,267,642 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $15.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


10.ACBR61108-ATRP(016) ,LEE COUNTY

Contract Time: 90 Working Days

DBE Goal Percent:8.00

for constructing the Bridge Replacement on Cunningham Drive over Pepperell Creek in Opelika. Length 0.080 mi.

The Bracket Estimate on this project is from $1,505,134 to $1,655,647 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $15.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


14.ACBRZ58501-ATRP(015) ,TUSCALOOSA COUNTY

Contract Time: 75 Working Days

for constructing the Bridge Replacement on CR-155 (South Sandy Road) over Big Sandy Creek. Length 0.045 mi.

The Bracket Estimate on this project is from $410,858 to $502,160 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $7.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


16.ACBRZ60362-ATRP(014) ,PERRY COUNTY

Contract Time: 60 Working Days

DBE Goal Percent:3.00

for constructing the Bridge Replacement on CR-49 (Levert Road) over Potato Patch Creek east of Heiberger. Length 0.217 mi.

The Bracket Estimate on this project is from $641,344 to $783,865 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $13.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


17.ACBRZ60383-ATRP(010) ,PICKENS COUNTY

Contract Time: 45 Working Days

DBE Goal Percent:5.00

for constructing the Bridge Replacement on CR-47 (Bradford Road) over Beaver Creek west of McMullen. Length 0.012 mi.

The Bracket Estimate on this project is from $295,019 to $360,579 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $9.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


18.BRZ-1917(252) & ACBRZ60410-ATRP(014) ,COOSA COUNTY

Contract Time: 120 Working Days

DBE Goal Percent:4.00

for constructing the Bridge Replacement and Approaches on CR-56 over Weogufka Creek (Site 1) and over Spear Branch (Site 2) in Weogufka. Length 0.177mi.

The Bracket Estimate on this project is from $754,437 to $922,089 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $22.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


19.ACBRZ60447-ATRP(012) ,WILCOX COUNTY

Contract Time: 100 Working Days

for constructing the Bridge Replacement on CR-40 over a channel on Lake Dannelly. Length 0.117 mi.

The Bracket Estimate on this project is from $904,387 to $994,826 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $22.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


22.ACBRZ61315-ATRP(015) ,MARSHALL COUNTY

Contract Time: 180 Working Days

DBE Goal Percent:10.00

for constructing the Bridge Replacement on CR-106 (New Home Road) over Clear Creek southeast of Center Point. Length 0.094 mi.

The Bracket Estimate on this project is from $850,008 to $1,038,899 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $15.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


29.ACOA61532-ATRP(005) ,ESCAMBIA COUNTY

Contract Time: 120 Working Days

DBE Goal Percent:8.00

for constructing the Planing, Resurfacing, and Traffic Stripe on Sowell Road from south of the junction of Rankin Street to the intersection of Gordon Lane in Brewton. Length 1.135 mi.

The Bracket Estimate on this project is from $917,893 to $1,121,869 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $9.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


36.BR-0006(559) ,AUTAUGA COUNTY

Contract Time: 255 Working Days

DBE Goal Percent:5.00

for constructing the Bridge Culvert Replacement on SR-6 (US-82/Prattville ByPass) over Pine Creek in Prattville. Length 0.564 mi.

The Bracket Estimate on this project is from $6,372,739 to $7,788,903 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $40.00 per set.

**** WITHDRAWN FROM THE LETTING ****

Return To: Proposal Letting List (Top of web page)


41.ER-9010(935) ,PIKE COUNTY

Contract Time: 75 Working Days

DBE Goal Percent:5.00

for constructing the Culvert Extension and Slope Repair on SR-10 (US-231) at MP 169.000 (Southbound Roadway) north of Troy. Length 0.122 mi.

The Bracket Estimate on this project is from $522,395 to $638,483 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $10.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


48.IM-HSIP-I010(338) ,MOBILE COUNTY

Contract Time: 165 Working Days

DBE Goal Percent:3.00

for constructing the Planing, Resurfacing, Cable Guiderail Installation, and Traffic Stripe on I-10 from west of the CR-39 (McDonald Road) Interchange to the CR-59 (Carol Plantation Road) Underpass. Length 4.569 mi.

The Bracket Estimate on this project is from $7,096,527 to $8,673,534 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $22.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


52.IM-I059(402) & IM-I059(403) ,SUMTER COUNTY

Contract Time: 180 Working Days

DBE Goal Percent:3.00

for constructing the Planing, Resurfacing, Bridgerail Retrofit, Guardrail Installation, and Traffic Stripe on I-59 from north of the Exit 1 Interchange in Cuba to south of the McCainville Road Underpass. Length 17.898 mi.

The Bracket Estimate on this project is from $15,019,282 to $18,356,901 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $19.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


53.IM-I059(406) ,TUSCALOOSA COUNTY

Contract Time: 110 Working Days

DBE Goal Percent:3.00

for constructing the Planing, Resurfacing, and Traffic Stripe on I-59 from east of the Exit 79 Interchange (SR-7/US-11/University Boulevard) to east of the Exit 86 Interchange (Covered Bridge Road) to include the Northbound and Southbound Rest Areas. Length 5.801 mi.

The Bracket Estimate on this project is from $6,710,385 to $8,201,582 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $15.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


54.IM-I065(483) ,LIMESTONE COUNTY

Contract Time: 75 Working Days

DBE Goal Percent:8.00

for constructing the Planing, Resurfacing, and Traffic Stripe on I-65 from MP 359.000 (a point 2.000 miles south of the Thach Road Interchange) to the Tennessee State Line. Length 7.272 mi.

The Bracket Estimate on this project is from $3,214,110 to $3,928,356 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $4.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


56.IM-I459(315) ,JEFFERSON COUNTY

Contract Time: 180 Working Days

DBE Goal Percent:3.00

for constructing the Pavement Rehabilitation, Planing, Resurfacing, and Traffic Stripe on I-459 from a point south of the CR-52 Interchange in Bessemer to south of the SR-150 Interchange in Hoover. Length 5.311 mi.

The Bracket Estimate on this project is from $12,304,919 to $15,039,346 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $11.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


58.NH-0013(606) & 99-408-134-013-616 ,CLARKE COUNTY

Contract Time: 55 Working Days

DBE Goal Percent:3.00

for constructing the Planing, Resurfacing, Drainage Inlet Repair, and Traffic Stripe on SR-13 (US-43) from the Tombigbee River Bridge to 0.210 mile north of the junction of CR-10 (Walker Springs Road) in Jackson. Length 5.272 mi.

The Bracket Estimate on this project is from $1,794,567 to $2,193,360 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $9.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


59.NH-0009(563) ,MONTGOMERY COUNTY

Contract Time: 50 Working Days

DBE Goal Percent:3.00

for constructing the Planing, Resurfacing (Scrub Seal), and Traffic Stripe on SR-9 (US-331) from south of the junction of Hobbie Road (MP 94.070) southeast of Hope Hull to the junction of Norman Bridge Road in Montgomery. Length 4.230 mi.

The Bracket Estimate on this project is from $3,099,355 to $3,788,101 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


60.NH-0012(562) ,CONECUH COUNTY

Contract Time: 70 Working Days

DBE Goal Percent:7.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-12 (US-84) from east of the junction of SR-3 (US-31) northeast of Centerville to the Covington County Line. Length 11.460 mi.

The Bracket Estimate on this project is from $2,054,369 to $2,510,896 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $8.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


62.NH-0024(512) ,LAWRENCE COUNTY

Contract Time: 45 Working Days

DBE Goal Percent:4.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-24 from the intersection of SR-101 to near the intersection of CR-122 west of Moulton. Length 4.071 mi.

The Bracket Estimate on this project is from $1,380,364 to $1,687,111 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


63.NH-0038(537) ,TALLAPOOSA AND CHAMBERS COUNTIES

Contract Time: 80 Working Days

DBE Goal Percent:3.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-38 (US-280) from 0.060 mile east of the junction of Ross Road to the Lee County Line. Length 4.542 mi.

The Bracket Estimate on this project is from $2,427,799 to $2,967,310 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


64.NH-0059(515) ,BALDWIN COUNTY

Contract Time: 100 Working Days

DBE Goal Percent:4.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-59 from the junction of Windbigler Drive north of Foley to the junction of CR-54 in Robertsdale. Length 9.062 mi.

The Bracket Estimate on this project is from $3,061,371 to $3,741,676 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $8.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


65.NH-0075(533) ,JEFFERSON COUNTY

Contract Time: 45 Working Days

DBE Goal Percent:6.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-75 from the junction of the I-59 Interchange to north of the junction of Huffman Road in Birmingham. Length 1.995 mi.

The Bracket Estimate on this project is from $1,262,653 to $1,543,243 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $4.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


66.NH-0079(518) ,JEFFERSON COUNTY

Contract Time: 45 Working Days

DBE Goal Percent:6.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-79 from the junction of the I-59 Interchange to the intersection of Cedar Street in Birmingham. Length 1.700 mi.

The Bracket Estimate on this project is from $1,234,703 to $1,509,081 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $4.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


67.NH-0150(504) ,JEFFERSON COUNTY

Contract Time: 45 Working Days

DBE Goal Percent:4.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-150 from the junction of Morgan Road to 0.060 mile west of the junction of Lake Cyrus Boulevard in Bessemer. Length 4.219 mi.

The Bracket Estimate on this project is from $1,279,184 to $1,563,447 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $4.00 per set.

**** WITHDRAWN FROM THE LETTING ****

Return To: Proposal Letting List (Top of web page)


68.NH-0024(511) ,LAWRENCE COUNTY

Contract Time: 60 Working Days

DBE Goal Percent:6.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-24 from the Franklin County Line to the junction of SR-101. Length 5.502 mi.

The Bracket Estimate on this project is from $1,998,796 to $2,442,973 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


69.NH-HSIP-0009(552) ,CRENSHAW COUNTY

Contract Time: 85 Working Days

DBE Goal Percent:10.00

for constructing the Safety Widening, Planing, Resurfacing, and Traffic Stripe on SR-9 (US-331) from the Covington County Line to approximately one mile north of the South City Limits of Brantley. Length 10.084 mi.

The Bracket Estimate on this project is from $2,944,920 to $3,599,347 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $21.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


73.RP-IM-I459(311) ,JEFFERSON COUNTY

Contract Time: 150 Working Days

DBE Goal Percent:3.00

for constructing the Pavement Rehabilitation, Planing, Resurfacing, and Traffic Stripe on I-459 from the I-20/59 Interchange in McCalla to a point south of the CR-52 Interchange in Bessemer. Length 5.355 mi.

The Bracket Estimate on this project is from $9,051,236 to $11,062,621 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $12.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


75.STPAA-0071(502) ,JACKSON COUNTY

Contract Time: 60 Working Days

DBE Goal Percent:5.00

for constructing the Resurfacing (Scrub Seal) and Traffic Stripe on SR-71 from the intersection of SR-117 in Flat Rock to the Georgia State Line. Length 10.549 mi.

The Bracket Estimate on this project is from $2,757,244 to $3,369,965 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $5.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


76.STPAA-0033(505) ,LAWRENCE COUNTY

Contract Time: 30 Working Days

DBE Goal Percent:8.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-33 from 0.300 mile north of the intersection of SR-157 north of Moulton to the junction of CR-578. Length 6.890 mi.

The Bracket Estimate on this project is from $856,749 to $1,047,137 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


78.STPAA-0105(504) ,DALE AND BARBOUR COUNTIES

Contract Time: 30 Working Days

DBE Goal Percent:5.00

for constructing the Resurfacing (High Performance Chip Seal) and Traffic Stripe on SR-105 from north of the intersection of CR-33 in Skipperville to the junction of SR-10 in Barbour County. Length 9.809 mi.

The Bracket Estimate on this project is from $682,475 to $834,136 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $6.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


79.STPAA-0130(501) ,PIKE AND BARBOUR COUNTIES

Contract Time: 40 Working Days

DBE Goal Percent:8.00

for constructing the Resurfacing (High Performance Chip Seal) and Traffic Stripe on SR-130 from the junction of SR-15 (US-29) to the junction of SR-51 in Louisville. Length 15.444 mi.

The Bracket Estimate on this project is from $1,171,659 to $1,432,028 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $6.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


80.STPAA-0155(504) ,SHELBY COUNTY

Contract Time: 45 Working Days

DBE Goal Percent:4.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-155 from the Chilton County Line to the junction of SR-25 in Montevallo. Length 2.214 mi.

The Bracket Estimate on this project is from $555,494 to $678,937 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

**** WITHDRAWN FROM THE LETTING ****

Return To: Proposal Letting List (Top of web page)


82.STPAA-0223(503) ,PIKE COUNTY

Contract Time: 40 Working Days

DBE Goal Percent:1.00

for constructing the Resurfacing (High Performance Chip Seal) and Traffic Stripe on SR-223 from the junction of SR-15 (US-29) northwest of Banks to the Bullock County Line. Length 11.648 mi.

The Bracket Estimate on this project is from $1,062,424 to $1,298,518 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $6.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


83.STPAA-HSIP-0061(505) ,HALE COUNTY

Contract Time: 45 Working Days

DBE Goal Percent:3.00

for constructing the Safety Widening, Planing, Resurfacing, and Traffic Stripe on SR-61 from the Perry County Line to the South City Limits of Newbern. Length 6.927 mi.

The Bracket Estimate on this project is from $2,682,309 to $3,278,378 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $8.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


85.STPAA-HSIP-0004(544) ,CALHOUN COUNTY

Contract Time: 55 Working Days

DBE Goal Percent:3.00

for constructing the Safety Widening, Planing, Resurfacing, and Traffic Stripe on SR-4 (US-78) from the Talladega County Line to the Norfolk Southern Railroad Crossing 0.300 mile west of the intersection of SR-202 in Oxford. Length 5.223 mi.

The Bracket Estimate on this project is from $1,670,969 to $2,042,296 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


86.STPAA-HSIP-0009(564) ,CLAY COUNTY

Contract Time: 60 Working Days

DBE Goal Percent:4.00

for constructing the Safety Widening, Planing, Resurfacing, Bridge Rail Retrofit, and Traffic Stripe on SR-9 from MP 187.215 in Lineville to a point north of the Mad Indian Creek Bridge (MP 193.931). Length 6.716 mi.

The Bracket Estimate on this project is from $1,738,935 to $2,125,365 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


93.STPMN-ACAA59590-ATRP(011) ,MONTGOMERY COUNTY

Contract Time: 110 Working Days

DBE Goal Percent:4.00

for constructing the Planing, Resurfacing, and Traffic Stripe on CR-626 (Vaughn Road) from the intersection of SR-271 (Taylor Road) in Montgomery to the junction of SR-110 (Chantilly Parkway). Length 4.425 mi.

The Bracket Estimate on this project is from $3,042,557 to $3,718,681 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $79.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


94.STPNU-0079(517) ,JACKSON COUNTY

Contract Time: 40 Working Days

DBE Goal Percent:6.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-79 from the junction of SR-146 south of Hytop to the Tennessee State Line. Length 10.240 mi.

The Bracket Estimate on this project is from $2,458,743 to $3,005,130 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $5.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


96.STPOA-1115(250) ,CHILTON COUNTY

Contract Time: 45 Working Days

DBE Goal Percent:4.00

for constructing the Resurfacing and Traffic Stripe on CR-81 from the junction of SR-3 (US-31) to the junction of SR-145 to include a 0.250 mile segment of CR-13 in Clanton. Length 2.100 mi.

The Bracket Estimate on this project is from $785,790 to $960,410 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $6.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


97.STPNU-1617(251) & STPNU-1617(252) ,COFFEE COUNTY

Contract Time: 35 Working Days

DBE Goal Percent:4.00

for constructing the Resurfacing, Guardrail Installation, and Traffic Stripe on CR-479 (Hickman Avenue West) from the Geneva County Line to the junction of SR-52 in Kinston (Site 1) and on CR-342 from the junction of SR-87 north of Elba to the intersection of CR-349 (Site 2). Length 4.814 mi.

The Bracket Estimate on this project is from $674,999 to $824,998 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $21.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


98.STPNU-4715(250) ,MARION COUNTY

Contract Time: 30 Working Days

DBE Goal Percent:6.00

for constructing the Planing, Resurfacing (Full Depth Reclamation), and Traffic Stripe on CR-29 from the junction of SR-17 (US-43) in Hamilton to the junction of Lovejoy Road. Length 3.244 mi.

The Bracket Estimate on this project is from $662,909 to $810,222 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


99.STPNU-5216(251) ,MORGAN COUNTY

Contract Time: 50 Working Days

DBE Goal Percent:5.00

for constructing the Drainage Improvements (Roadway Culvert Replacement), Resurfacing, and Traffic Stripe on Wilhite Road from the junction of Milligan Road to the junction of CR-55 west of Eva. Length 2.193 mi.

The Bracket Estimate on this project is from $507,442 to $620,207 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $7.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


102.STPOA-9215(600) ,MORGAN COUNTY

Contract Time: 360 Working Days

DBE Goal Percent:8.00

for constructing the Additional Lanes (Grading, Drainage, Pavement, Retaining Walls, Signage, Signals, and Traffic Stripe) on Spring Avenue from the junction of Day Road to the junction of Cedar Lake Road in Decatur. Length 1.915 mi.

The Bracket Estimate on this project is from $8,761,462 to $10,708,454 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $71.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


105.ST-005-160-007 ,BLOUNT COUNTY

Contract Time: 125 Working Days

for constructing the Intersection Improvements (Grading, Drainage, and Pavement) on SR-160 at Mountain Woods Lake Road to the include Drainage Improvements at Standholton Drive. Length 0.369 mi.

The Bracket Estimate on this project is from $1,891,781 to $2,312,177 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $44.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


108.99-306-576-208-702 ,RUSSELL COUNTY

Contract Time: 30 Working Days

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-208 from the junction of SR-165 east of Cottonton to the Chattahoochee River Bridge. Length 0.699 mi.

The Bracket Estimate on this project is from $205,289 to $250,909 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $2.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


111.99-502-391-002-801 ,LAUDERDALE COUNTY

Contract Time: 75 Working Days

for the Maintenance Bridge Painting on SR-2 (US-72) at MP 51.419 (Westbound Roadway) over Second Creek west of Rogersville.

The Bracket Estimate on this project is from $426,581 to $521,377 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


113.99-505-632-215-601 ,TUSCALOOSA COUNTY

Contract Time: 75 Working Days

for the Maintenance Bridge Painting on SR-215 (Veterans Memorial Parkway) at MP 9.200 over The Alabama Great Southern Railroad in Tuscaloosa.

The Bracket Estimate on this project is from $240,281 to $293,677 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $4.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


200.STPAA-NR13(904) ,DALLAS COUNTY

Contract Time: 180 Working Days

for constructing the Curb Ramp Installations and Repairs on various routes at various locations as indicated in the plans.

The Bracket Estimate on this project is from $804,840 to $983,693 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $17.00 per set.

THIS PROJECT HAS BEEN DESIGNATED AS AN SBE PROJECT, AND CAN ONLY BE BID ON BY QUALIFIED SBE CONTRACTORS THAT HAVE BEEN PRE-APPROVED BY THE ALDOT DBE UNIT AND ALDOT OFFICE ENGINEER.