Office Engineer

Proposal Letting List
May 25, 2018, Transportation Letting

Welcome to the Proposal Letting List Page. You may view the approximate items of work with each proposal as a "printer friendly" page by clicking on the View Items hyperlink. Adobe Acrobat Reader will now be required to view the "View Items" pages. Please e-mail us with your comments.

Note: Adobe Acrobat Reader is now required to view the Proposal Item Summary pages.

5. ACAA60993-ATRP(008), JEFFERSON 6. ACAA61010-ATRP(009), JEFFERSON
12. ACOA59517-ATRP(011), WALKER 15. BR-0074(517), CULLMAN
16. BR-0077(512), TALLADEGA 22. HSIP-I065(486), ETC., BALDWIN, ETC.
25. IM-I010(342), BALDWIN 26. IM-I065(480), BALDWIN
30. NH-0012(564), CONECUH 32. NH-0038(538), TALLAPOOSA
33. NH-0059(516), BALDWIN 35. NH-0157(523), MORGAN
38. NH-HSIP-0005(555), WILCOX 39. NH-HSIP-0013(609), MARENGO
42. RP-IM-I020(348), JEFFERSON 46. STPAA-0010(544), CRENSHAW
47. STPAA-0036(510), LAWRENCE 51. STPOA-0067(508), MORGAN
*52. STPAA-0099(505), LIMESTONE *53. STPAA-0099(506), LIMESTONE
54. STPAA-0101(569), LAWRENCE 57. STPAA-0181(504), ETC., BALDWIN
58. STPAA-0182(505), BALDWIN 62. STPAA-HSIP-0028(512), MARENGO
68. STPNU-1018(250), ETC., CHEROKEE 69. STPNU-4116(253), LEE
75. 99-403-582-620-802, ST. CLAIR 76. 99-407-203-015-601, COVINGTON
**78. 99-609-495-042-802, MOBILE 79. 99-509-491-665-703, MOBILE
*-WITHDRAWN FROM THE LETTING
**-ALL BIDS WERE REJECTED

The Bracket Ranges shown herein are to provide general financial information to Contractors and Bonding Companies concerning a Project's complexity and size. THESE BRACKETS SHOULD NOT BE USED IN PREPARING A BID, NOR WILL THESE BRACKETS HAVE ANY BEARING ON THE DECISION TO AWARD ANY CONTRACT.


5.ACAA60993-ATRP(008) ,JEFFERSON COUNTY

Contract Time: 40 Working Days

DBE Goal Percent:4.00

for constructing the Planing, Resurfacing, and Traffic Stripe on Messer Airport Highway from the junction of 31st Street North to the junction of 46th Street North in Birmingham. Length 1.708 mi.

The Bracket Estimate on this project is from $1,071,811 to $1,309,991 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $5.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


6.ACAA61010-ATRP(009) ,JEFFERSON COUNTY

Contract Time: 110 Working Days

DBE Goal Percent:6.00

for constructing the Intersection Improvements (Grading, Drainage, Pavement, Sidewalks, Traffic Signals, and Traffic Stripe) on Stadium Trace Parkway at Brocks Gap Parkway and Learning Lane in Hoover. Length 0.255 mi.

The Bracket Estimate on this project is from $1,186,628 to $1,450,323 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $25.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


12.ACOA59517-ATRP(011) ,WALKER COUNTY

Contract Time: 120 Working Days

DBE Goal Percent:8.00

for constructing the Widening (Grading, Drainage, and Pavement), Planing, Resurfacing, Traffic Signals, and Traffic Stripe on Airport Road from south of the intersection of SR-5 (US-78) to the junction of Woodland Drive. Length 0.694 mi.

The Bracket Estimate on this project is from $1,441,982 to $1,762,422 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $22.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


15.BR-0074(517) ,CULLMAN COUNTY

Contract Time: 200 Working Days

DBE Goal Percent:8.00

for constructing the Bridge Replacement (Grading, Drainage, Pavement, and Bridge) on SR-74 (US-278) over Brindley Creek 0.800 mile east of the junction of SR-69. Length 1.173 mi.

The Bracket Estimate on this project is from $6,192,618 to $7,568,755 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $82.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


16.BR-0077(512) ,TALLADEGA COUNTY

Contract Time: 200 Working Days

DBE Goal Percent:5.00

for constructing the Bridge Replacement (Grading, Drainage, Pavement, and Bridge) on SR-77 over Blue Eye Creek in Lincoln. Length 0.595 mi.

The Bracket Estimate on this project is from $2,843,102 to $3,474,902 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $31.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


22.HSIP-I065(486) & HSIP-I065(488) ,BALDWIN, MOBILE, AND ESCAMBIA COUNTIES

Contract Time: 185 Working Days

DBE Goal Percent:1.00

for constructing the Median Barrier Protection (Cable Guiderail Installation) on I-65 from the SR-59 Interchange to the Railroad Bridge at MP 75.500 (Site 1) and on I-65 from the SR-158 Interchange to north of the CR-41 Interchange (MP 16.900) in Saraland (Site 2). Length 45.698 mi.

The Bracket Estimate on this project is from $2,376,096 to $2,904,118 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $7.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


25.IM-I010(342) ,BALDWIN COUNTY

Contract Time: 20 Working Days

for constructing the Planing, Resurfacing, and Traffic Stripe at the I-10 Welcome Center west of the Florida State Line. Length 0.338 mi.

The Bracket Estimate on this project is from $308,177 to $376,661 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $8.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


26.IM-I065(480) ,BALDWIN COUNTY

Contract Time: 165 Working Days

DBE Goal Percent:4.00

for constructing the Planing, Resurfacing, and Traffic Stripe on I-65 from the Dyas Creek Bridge to the Escambia County Line. Length 7.319 mi.

The Bracket Estimate on this project is from $8,461,432 to $10,341,751 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $12.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


30.NH-0012(564) ,CONECUH COUNTY

Contract Time: 70 Working Days

DBE Goal Percent:3.00

for constructing the Planing, Resurfacing, Guardrail Installation, and Traffic Stripe on SR-12 (US-84) from the Monroe County Line to the junction of SR-3 (US-31) southwest of Evergreen. Length 16.818 mi.

The Bracket Estimate on this project is from $1,866,435 to $2,281,198 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $8.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


32.NH-0038(538) ,TALLAPOOSA COUNTY

Contract Time: 110 Working Days

DBE Goal Percent:4.00

for constructing the Planing, Resurfacing, Guardrail, and Traffic Stripe on SR-38 (US-280) from west of the junction of Dadeville Road to east of the junction of Depot Avenue in Jackson. Length 5.754 mi.

The Bracket Estimate on this project is from $4,424,197 to $5,407,351 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $18.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


33.NH-0059(516) ,BALDWIN COUNTY

Contract Time: 90 Working Days

DBE Goal Percent:3.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-59 from the intersection of CR-12 in Foley to the junction of Windbigler Drive. Length 6.469 mi.

The Bracket Estimate on this project is from $2,410,810 to $2,946,546 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $9.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


35.NH-0157(523) ,MORGAN COUNTY

Contract Time: 75 Working Days

DBE Goal Percent:5.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-157 from the Cullman County Line to the Lawrence County Line. Length 8.604 mi.

The Bracket Estimate on this project is from $3,086,636 to $3,772,555 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


38.NH-HSIP-0005(555) ,WILCOX COUNTY

Contract Time: 50 Working Days

DBE Goal Percent:5.00

for constructing the Safety Widening, Planing, Resurfacing, and Traffic Stripe on SR-5 from the SR-28 Overpass to the north end of Chilatchee Creek Bridge to include the ramp to SR-28. Length 4.544 mi.

The Bracket Estimate on this project is from $1,387,947 to $1,696,379 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $6.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


39.NH-HSIP-0013(609) ,MARENGO COUNTY

Contract Time: 45 Working Days

DBE Goal Percent:4.00

for constructing the Safety Widening, Planing, Resurfacing, and Traffic Stripe on SR-13 (US-43) from south of the junction of CR-30 to north of the junction of CR-47 southwest of Octagon. Length 5.567 mi.

The Bracket Estimate on this project is from $1,301,261 to $1,590,431 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $5.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


42.RP-IM-I020(348) ,JEFFERSON COUNTY

Contract Time: 90 Working Days

for constructing the Traffic Sign Rehabilitation on I-20 from MP 132.890 to MP 142.920 and on I-459 from MP 28.500 to MP 30.150. Length 10.030 mi.

The Bracket Estimate on this project is from $1,260,991 to $1,541,211 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $27.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


46.STPAA-0010(544) ,CRENSHAW COUNTY

Contract Time: 55 Working Days

DBE Goal Percent:10.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-10 from the Butler County Line to the junction of SR-9 (US-331) in Rutledge. Length 9.837 mi.

The Bracket Estimate on this project is from $1,723,898 to $2,106,986 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $8.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


47.STPAA-0036(510) ,LAWRENCE COUNTY

Contract Time: 35 Working Days

DBE Goal Percent:10.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-36 from the junction of SR-33 south of Moulton to the intersection of SR-157. Length 7.924 mi.

The Bracket Estimate on this project is from $880,823 to $1,076,562 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


51.STPOA-0067(508) ,MORGAN COUNTY

Contract Time: 35 Working Days

DBE Goal Percent:4.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-67 (State Docks Road) from the junction of SR-20 to the end of SR-67 (MP 47.107). Length 1.388 mi.

The Bracket Estimate on this project is from $606,107 to $740,797 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


52.STPAA-0099(505) ,LIMESTONE COUNTY

Contract Time: 30 Working Days

DBE Goal Percent:12.00

for constructing the Resurfacing (Scrub Seal) and Traffic Stripe on SR-99 from the Sheriff's Arena (MP 9.000) to north of the intersection of Harris Road. Length 5.513 mi.

The Bracket Estimate on this project is from $488,683 to $597,279 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $2.00 per set.

***WITHDRAWN FROM THE LETTING***

Return To: Proposal Letting List (Top of web page)


53.STPAA-0099(506) ,LIMESTONE COUNTY

Contract Time: 30 Working Days

DBE Goal Percent:12.00

for constructing the Resurfacing (Scrub Seal) and Traffic Stripe on SR-99 from north of the intersection of Harris Road to the Lauderdale County Line. Length 11.236 mi.

The Bracket Estimate on this project is from $922,714 to $1,127,761 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $2.00 per set.

***WITHDRAWN FROM THE LETTING***

Return To: Proposal Letting List (Top of web page)


54.STPAA-0101(569) ,LAWRENCE COUNTY

Contract Time: 30 Working Days

DBE Goal Percent:12.00

for constructing the Resurfacing (Scrub Seal) and Traffic Stripe on SR-101 from the junction of CR-460 to the junction of CR-131. Length 5.973 mi.

The Bracket Estimate on this project is from $526,083 to $642,990 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $2.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


57.STPAA-0181(504) & BP-002-181-011 ,BALDWIN COUNTY

Contract Time: 435 Working Days

DBE Goal Percent:3.00

for constructing the Additional Lanes (Grading, Drainage, Pavement, Traffic Signals, and Traffic Stripe) on SR-181 from south of the intersection of SR-104 north of Fairhope to south of the intersection of CR-64 in Belforest. Length 3.979 mi.

The Bracket Estimate on this project is from $17,874,500 to $21,846,611 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $158.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


58.STPAA-0182(505) ,BALDWIN COUNTY

Contract Time: 40 Working Days

DBE Goal Percent:3.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-182 from the junction of West Lagoon Avenue to the East City Limits of Gulf Shores. Length 4.062 mi.

The Bracket Estimate on this project is from $1,383,581 to $1,691,043 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $9.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


62.STPAA-HSIP-0028(512) ,MARENGO COUNTY

Contract Time: 60 Working Days

DBE Goal Percent:4.00

for constructing the Safety Widening, Planing, Resurfacing, and Traffic Stripe on SR-28 from the junction of CR-21 to the junction of SR-13 (US-43) in Linden. Length 8.804 mi.

The Bracket Estimate on this project is from $1,785,853 to $2,182,709 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $5.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


68.STPNU-1018(250) & STPNU-1018(251) ,CHEROKEE COUNTY

Contract Time: 30 Working Days

DBE Goal Percent:3.00

for constructing the Resurfacing and Traffic Stripe on CR-13 from the junction of CR-31 northwest of Whorton to the intersection of CR-22 (Site 1) and on CR-41 from the intersection of SR-35 southwest of Ringgold to the junction of CR-794 (Site 2). Length 4.900 mi.

The Bracket Estimate on this project is from $646,965 to $790,735 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $5.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


69.STPNU-4116(253) ,LEE COUNTY

Contract Time: 40 Working Days

for constructing the Resurfacing (Full Depth Reclamation) and Traffic Stripe on CR-11 from the junction of CR-039 to the junction of SR-51 south of Beauregard. Length 3.263 mi.

The Bracket Estimate on this project is from $672,133 to $821,496 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $4.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


75.99-403-582-620-802 ,ST. CLAIR COUNTY

Contract Time: 60 Working Days

for constructing the Planing, Resurfacing, and Traffic Stripe on I-20 from east of the Kelly Creek Road Interchange to west of the SR-4 (US-78) Interchange west of Pell City. Length 8.167 mi.

The Bracket Estimate on this project is from $3,257,293 to $3,981,136 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $7.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


76.99-407-203-015-601 ,COVINGTON COUNTY

Contract Time: 55 Working Days

for constructing the Front Slope Repair (Culvert Extension) on SR-15 (US-29) at MP 56.300 southwest of Clearview. Length 0.098 mi.

The Bracket Estimate on this project is from $569,471 to $696,020 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $10.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


78.99-609-495-042-802 ,MOBILE COUNTY

Contract Time: 120 Working Days

for constructing the Interior Lighting on SR-42 (US-98) in the Bankhead Tunnel in Mobile. Length 0.641 mi.

The Bracket Estimate on this project is from $1,300,658 to $1,589,693 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $22.00 per set.

***** ALL BIDS WERE REJECTED *****

Return To: Proposal Letting List (Top of web page)


79.99-509-491-665-703 ,MOBILE COUNTY

Contract Time: 20 Working Days

for constructing the Bridge Deck Replacement (Partial) on Airport Boulevard over I-65 in Mobile. Length 0.052 mi.

The Bracket Estimate on this project is from $256,844 to $313,920 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $10.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)