Office Engineer

Proposal Letting List
February 22, 2019, Transportation Letting

Welcome to the Proposal Letting List Page. You may view the approximate items of work with each proposal as a "printer friendly" page by clicking on the View Items hyperlink. Adobe Acrobat Reader will now be required to view the "View Items" pages. Please e-mail us with your comments.

Note: Adobe Acrobat Reader is now required to view the Proposal Item Summary pages.

3. ACBRZ60456-ATRP(008), MARION 6. ACNU60347-ATRP(013), HALE
9. ACOA61875-ATRP(017), TUSCALOOSA 12. BR-0010(515), CHOCTAW
22. HSIP-NR19(903), MORGAN, ETC. 26. IM-I065(490), CULLMAN, ETC.
27. IM-I065(494), MONTGOMERY 28. IM-I085(360), ETC., CHAMBERS, ETC.
31. NH-0001(602), MADISON 32. NH-0012(567), ETC., COVINGTON
35. NH-0038(544), COOSA 36. NH-0042(536), MOBILE
38. NH-0163(504), MOBILE *42. NH-HSIP-0012(563), ETC., COFFEE
46. STPAA-0010(546), WILCOX 47. STPAA-0015(533), BULLOCK
48. STPAA-0017(576), CHOCTAW 51. STPAA-0285(500), ETC., BARBOUR
55. STPAA-HSIP-0073(501), JACKSON 59. STPNU-1418(250), CLAY
60. STPNU-2515(251), ETC., DEKALB
* - WITHDRAWN FROM THE LETTING

The Bracket Ranges shown herein are to provide general financial information to Contractors and Bonding Companies concerning a Project's complexity and size. THESE BRACKETS SHOULD NOT BE USED IN PREPARING A BID, NOR WILL THESE BRACKETS HAVE ANY BEARING ON THE DECISION TO AWARD ANY CONTRACT.


3.ACBRZ60456-ATRP(008) ,MARION COUNTY

Contract Time: 60 Working Days

DBE Goal Percent:3.00

for constructing the Bridge Replacement on CR-9 over Barnesville Creek west of Hamilton. Length 0.022 mi.

The Bracket Estimate on this project is from $499,739 to $610,792 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $8.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


6.ACNU60347-ATRP(013) ,HALE COUNTY

Contract Time: 30 Working Days

DBE Goal Percent:3.00

for constructing the Resurfacing and Traffic Stripe on CR-10 from the intersection of SR-25 to the junction of SR-61 south of Newbern. Length 4.215 mi.

The Bracket Estimate on this project is from $1,015,043 to $1,240,608 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


9.ACOA61875-ATRP(017) ,TUSCALOOSA COUNTY

Contract Time: 45 Working Days

DBE Goal Percent:4.00

for constructing the Intersection Improvements and Widening on Watermelon Road at Union Chapel Road and Old Colony Road. Length 0.246 mi.

The Bracket Estimate on this project is from $574,600 to $702,288 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $19.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


12.BR-0010(515) ,CHOCTAW COUNTY

Contract Time: 130 Working Days

DBE Goal Percent:4.00

for constructing the Bridge Replacement (Grading, Drainage, Pavement, and Bridge Removal) on SR-10 over Tuckabum Creek southwest of Yantley. Length 0.605 mi.

The Bracket Estimate on this project is from $2,544,344 to $3,109,754 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $30.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


22.HSIP-NR19(903) ,MORGAN, LAUDERDALE, COLBERT, AND LIMESTONE COUNTIES

Contract Time: 30 Working Days

for constructing the Safety Improvements (Curve Warning Sign Installation) on various routes in the North Region (Tuscumbia Area) as indicated in the plans.

The Bracket Estimate on this project is from $118,574 to $144,924 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $4.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


26.IM-I065(490) ,CULLMAN AND MORGAN COUNTIES

Contract Time: 35 Working Days

DBE Goal Percent:8.00

for constructing the Planing, Resurfacing, and Traffic Stripe on I-65 from Hurricane Creek (MP 315.665) to south of the CSX Railroad Bridge. Length 3.523 mi.

The Bracket Estimate on this project is from $1,337,280 to $1,634,453 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $8.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


27.IM-I065(494) ,MONTGOMERY COUNTY

Contract Time: 40 Working Days

DBE Goal Percent:4.00

for constructing the Planing, Resurfacing, and Traffic Stripe on I-65 from Catoma Creek (MP 167.540) to north of the Fairview Avenue Interchange in Montgomery. Length 2.979 mi.

The Bracket Estimate on this project is from $2,136,882 to $2,611,744 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $10.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


28.IM-I085(360) & IM-I085(363) ,CHAMBERS AND LEE COUNTIES

Contract Time: 135 Working Days

DBE Goal Percent:3.00

for constructing the Pavement Rehabilitation, Planing, Resurfacing, and Traffic Stripe on I-85 from the Lee County Line to the Georgia State Line. Length 10.838 mi.

The Bracket Estimate on this project is from $7,978,406 to $9,751,385 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $6.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


31.NH-0001(602) ,MADISON COUNTY

Contract Time: 35 Working Days

DBE Goal Percent:8.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-1 (US-431) from the junction of Old Big Cove Road to the intersection of Bassett Street in Huntsville. Length 4.880 mi.

The Bracket Estimate on this project is from $1,497,407 to $1,830,164 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $9.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


32.NH-0012(567) & STPAA-HSIP-0100(500) ,COVINGTON COUNTY

Contract Time: 40 Working Days

DBE Goal Percent:6.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-12 (US-84) from the junction of SR-100 in Andalusia to west of the intersection of CR-67 (Site 1) and the Safety Widening, Planing, Resurfacing, and Traffic Stripe on SR-100 from the junction of SR-15 (East 3 Notch Street) to the junction of SR-12 (US-84) in Andalusia (Site 2). Length 4.816 mi.

The Bracket Estimate on this project is from $2,102,145 to $2,569,288 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $15.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


35.NH-0038(544) ,COOSA COUNTY

Contract Time: 35 Working Days

DBE Goal Percent:3.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-38 (US-280) from the Talladega County Line to 0.563 mile east of the intersection of CR-49. Length 6.505 mi.

The Bracket Estimate on this project is from $2,097,004 to $2,563,004 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


36.NH-0042(536) ,MOBILE COUNTY

Contract Time: 100 Working Days

DBE Goal Percent:3.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-42 (US-98) from the junction of Magnolia Grove Parkway to the junction of Stimpson Lane in Mobile. Length 5.017 mi.

The Bracket Estimate on this project is from $2,208,128 to $2,698,824 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $10.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


38.NH-0163(504) ,MOBILE COUNTY

Contract Time: 75 Working Days

DBE Goal Percent:4.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-163 from the south end of the Dog River Bridge (MP 2.525) to the south end of the I-10 Overpass (MP 8.562) in Mobile. Length 6.036 mi.

The Bracket Estimate on this project is from $2,215,333 to $2,707,629 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $14.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


42.NH-HSIP-0012(563) & NH-HSIP-0167(511) ,COFFEE COUNTY

Contract Time: 75 Working Days

DBE Goal Percent:6.00

for constructing the Safety Widening, Planing, Resurfacing, and Traffic Stripe on SR-12 (Enterprise Bypass) from the junction of SR-88/SR-192 (North Main Street) to the junction of SR-134 (East Park Avenue) (Site 1) and on SR-167 (Enterprise Bypass) from the junction of SR-88/SR-192 (Plaze Drive) to the junction of SR-134 (East Park Avenue) in Enterprise (Site 2). Length 4.411 mi.

The Bracket Estimate on this project is from $3,076,318 to $3,759,945 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for

***WITHDRAWN FROM THE LETTING***

Return To: Proposal Letting List (Top of web page)


46.STPAA-0010(546) ,WILCOX COUNTY

Contract Time: 45 Working Days

DBE Goal Percent:3.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-10 from west of the intersection of SR-221 to east of the junction of SR-41 in Camden. Length 4.491 mi.

The Bracket Estimate on this project is from $1,263,804 to $1,544,649 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $5.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


47.STPAA-0015(533) ,BULLOCK COUNTY

Contract Time: 55 Working Days

DBE Goal Percent:4.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-15 (US-29) from the junction of SR-6 (US-82) to the Macon County Line. Length 6.217 mi.

The Bracket Estimate on this project is from $2,422,604 to $2,960,960 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


48.STPAA-0017(576) ,CHOCTAW COUNTY

Contract Time: 50 Working Days

DBE Goal Percent:1.00

for constructing the Resurfacing and Traffic Stripe on SR-17 from 0.930 mile south of the junction of Snapdragon Lane to Wahalak Creek in Butler. Length 8.499 mi.

The Bracket Estimate on this project is from $1,767,121 to $2,159,814 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $6.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


51.STPAA-0285(500) & 99-807-036-000-901 ,BARBOUR COUNTY

Contract Time: 30 Working Days

for constructing the Preventative Maintenance (High Performance Chip Seal) and Traffic Stripe on State Park Road and SR-285 from SR-1 (US-431) to SR-165 in Eufaula. Length 2.273 mi.

The Bracket Estimate on this project is from $263,470 to $322,019 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $5.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


55.STPAA-HSIP-0073(501) ,JACKSON COUNTY

Contract Time: 45 Working Days

DBE Goal Percent:6.00

for constructing the Resurfacing (Scrub Seal), Safety Installation of High Friction Surface Treatment, Guardrail Replacement, and Traffic Stripe on SR-73 from the junction of SR-71 to the Tennessee State Line. Length 11.220 mi.

The Bracket Estimate on this project is from $2,267,846 to $2,771,812 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $5.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


59.STPNU-1418(250) ,CLAY COUNTY

Contract Time: 30 Working Days

DBE Goal Percent:3.00

for constructing the Resurfacing and Traffic Stripe on CR-130 (Idaho Road) from the Talladega County Line to the junction of SR-77. Length 6.707 mi.

The Bracket Estimate on this project is from $866,397 to $1,058,929 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


60.STPNU-2515(251) & STPNU-2515(252) ,DEKALB COUNTY

Contract Time: 60 Working Days

DBE Goal Percent:8.00

for constructing the Resurfacing and Traffic Stripe on CR-165 from the junction of CR-617 to the junction of CR-106 (Site 1) and on CR-631 from the junction of SR-117 in Mentone to the Georgia State Line (Site 2). Length 7.600 mi.

The Bracket Estimate on this project is from $338,572 to $413,810 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $6.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)