Office Engineer

Proposal Letting List
September 27, 2019, Transportation Letting

Welcome to the Proposal Letting List Page. You may view the approximate items of work with each proposal as a "printer friendly" page by clicking on the View Items hyperlink. Adobe Acrobat Reader will now be required to view the "View Items" pages. Please e-mail us with your comments.

Note: Adobe Acrobat Reader is now required to view the Proposal Item Summary pages.

* 1. BRF-0013(501), MARENGO 3. RPF-NHF-0210(508), HOUSTON
6. BR-0046(503), CLEBURNE 7. BR-0048(502), RANDOLPH
10. CMAQ-3715(268), JEFFERSON 11. CMAQ-5918(250), SHELBY
14. HRRR-0219(253), BALDWIN 15. HRRR-0319(250), BARBOUR
16. HRRR-1519(250), CLEBURNE 17. HRRR-2119(250), CRENSHAW
18. HRRR-2419(251), DALLAS 19. HRRR-2619(253), ELMORE
20. HRRR-2719(250), ESCAMBIA 21. HRRR-3019(250), FRANKLIN
22. HRRR-3619(250), JACKSON 23. HRRR-4519(250), MADISON
24. HRRR-5219(250), MORGAN 25. HRRR-5519(250), PIKE
26. HRRR-5919(250), SHELBY 27. HRRR-6119(250), TALLADEGA
29. HSIP-I085(364), LEE 30. IM-I065(503), MORGAN
31. IM-I065(506), BUTLER, ETC. 34. STPBH-ACBR59503-ATRP(012), SHELBY
37. STPHV-4514(251), MADISON 40. STPMB-7550(601), MOBILE
43. STPMN-2619(252), ELMORE 46. STPNU-3519(250), ETC., HOUSTON
50. STPPC-ACBR59582-ATRP(011), RUSSELL 56. 99-508-693-000-921, WILCOX
* - WITHDRAWN FROM THE LETTING

The Bracket Ranges shown herein are to provide general financial information to Contractors and Bonding Companies concerning a Project's complexity and size. THESE BRACKETS SHOULD NOT BE USED IN PREPARING A BID, NOR WILL THESE BRACKETS HAVE ANY BEARING ON THE DECISION TO AWARD ANY CONTRACT.


1.BRF-0013(501) ,MARENGO COUNTY

Contract Time: 140 Working Days

DBE Goal Percent:5.00

for constructing the Bridge Replacement (Grading, Drainage, Pavement, and Bridge) on SR-13 (US-43) over the AGR Railroad southeast of Demopolis. Length 0.652 mi.

The Bracket Estimate on this project is from $4,066,539 to $4,970,215 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $40.00 per set.

****WITHDRAWN FROM THE LETTING****

Return To: Proposal Letting List (Top of web page)



3.RPF-NHF-0210(508) ,HOUSTON COUNTY

Contract Time: 6/24/2022 Completion Date

DBE Goal Percent:8.00

for constructing the Additional Lanes (Grading, Drainage, Pavement, Traffic Signals, Traffic Signs, and Traffic Stripe) on SR-210 (Ross Clark Circle) from south of the intersection of SR-12 (US-84) to south of the junction of Meadowbrook Drive in Dothan (Site 1) and on SR-12 (US-84) from the junction of Bel Aire Drive to the junction of North Englewood Avenue in Dothan (Site 2). Length 1.645 mi.

The Bracket Estimate on this project is from $15,181,103 to $18,554,681 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $363.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)



6.BR-0046(503) ,CLEBURNE COUNTY

Contract Time: 150 Working Days

DBE Goal Percent:5.00

for constructing the Bridge Replacement (Grading, Drainage, Pavement, and Bridge) on SR-46 over Cane Creek in Heflin. Length 0.230 mi.

The Bracket Estimate on this project is from $2,420,850 to $2,958,816 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $30.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)



7.BR-0048(502) ,RANDOLPH COUNTY

Contract Time: 190 Working Days

DBE Goal Percent:5.00

for constructing the Bridge Replacement (Grading, Drainage, Pavement, and Bridge) on SR-48 over Fox Creek east of the Clay County Line. Length 0.581 mi.

The Bracket Estimate on this project is from $3,653,309 to $4,465,155 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $37.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)



10.CMAQ-3715(268) ,JEFFERSON COUNTY

Contract Time: 45 Working Days

DBE Goal Percent:6.00

for constructing the Sidewalk Installations from a point on Poinciana Drive north of the junction of Hermosa Drive to the junction of 20th Place South and on 20th Place South from the junction of Poinciana Drive to the junction of Cahaba Road. Length 0.522 mi.

The Bracket Estimate on this project is from $384,395 to $469,816 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $18.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)



11.CMAQ-5918(250) ,SHELBY COUNTY

Contract Time: 50 Working Days

DBE Goal Percent:6.00

for constructing the Intersection Improvements on CR-52 at CR-93 west of Helena. Length 0.204 mi.

The Bracket Estimate on this project is from $963,904 to $1,178,105 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $16.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)



14.HRRR-0219(253) ,BALDWIN COUNTY

Contract Time: 15 Working Days

for constructing the Guardrail Installations on CR-87 over the Styx River (Site 1); on Hoyle Bryars Road over I-65 (Site 2); and on Scrange Road over Horseneck Creek (Site 3). Length 0.287 mi.

The Bracket Estimate on this project is from $188,741 to $230,683 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)



15.HRRR-0319(250) ,BARBOUR COUNTY

Contract Time: 15 Working Days

for constructing the Guardrail Installations on CR-31 over Stinking Creek (Site 1); on CR-26 over Jackson Creek (Site 2); on CR-77 (Jack Jones Road) over the Pea River (Site 3); and on CR-36 over White Oak Creek (Site 4). Length 0.229 mi.

The Bracket Estimate on this project is from $93,413 to $114,171 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $6.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)



16.HRRR-1519(250) ,CLEBURNE COUNTY

Contract Time: 30 Working Days

for constructing the Safety Improvements (Guardrail Installation, Pavement Markers, Rumble Strip, Traffic Signs, and Traffic Stripe) on CR-24 from the Calhoun County Line to the junction of CR-3 in Abel. Length 2.358 mi.

The Bracket Estimate on this project is from $149,699 to $182,965 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $4.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)



17.HRRR-2119(250) ,CRENSHAW COUNTY

Contract Time: 20 Working Days

for constructing the Guardrail Installations on CR-30 over Piney Woods Creek and Blue Creek (Site 1 and Site 2) and on CR-66 over Dry Creek (Site 3). Length 0.167 mi.

The Bracket Estimate on this project is from $129,298 to $158,030 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $4.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)



18.HRRR-2419(251) ,DALLAS COUNTY

Contract Time: 30 Working Days

for constructing the Guardrail Installations on CR-83 over Mulberry Creek (Site 1); on CR-74 over Soapstone Creek (Site 2); on CR-11 over Tatum Creek (Site 3); and on CR-29 over Dry Creek (Site 4). Length 0.505 mi.

The Bracket Estimate on this project is from $197,407 to $241,275 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $4.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)



19.HRRR-2619(253) ,ELMORE COUNTY

Contract Time: 20 Working Days

for constructing the Guardrail Installations on Sewell Road over Weoka Creek (Site 1); on Baltzer Road over Calloway Creek (Site 2); and on Peace Church Road over Brenson Branch (Site 3). Length 0.204 mi.

The Bracket Estimate on this project is from $116,535 to $142,432 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $5.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)



20.HRRR-2719(250) ,ESCAMBIA COUNTY

Contract Time: 15 Working Days

for constructing the Safety Improvements (Pavement Markers, Pavement Markings, and Traffic Stripe) on CR-4 (Bradley Road) from the intersection of SR-15 (US-29) to the Covington County Line. Length 17.746 mi.

The Bracket Estimate on this project is from $161,519 to $197,413 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $5.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)



21.HRRR-3019(250) ,FRANKLIN COUNTY

Contract Time: 30 Working Days

for constructing the Safety Improvements (Cross Slope Corrections, Guardrail Installation, Traffic Control Devices, and Traffic Stripe) on CR-12 (College Road) from the junction of SR-17 (US-43) to the junction of Dan Street in Phil Campbell. Length 2.773 mi.

The Bracket Estimate on this project is from $287,128 to $350,934 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $2.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)



22.HRRR-3619(250) ,JACKSON COUNTY

Contract Time: 20 Working Days

for constructing the Safety Improvements (Curve Warning Sign Installations, Pavement Markings, and Traffic Stripe) on CR-77 from the junction of SR-79 southwest of Scottsboro to the Marshall County Line. Length 1.872 mi.

The Bracket Estimate on this project is from $48,383 to $59,134 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)



23.HRRR-4519(250) ,MADISON COUNTY

Contract Time: 20 Working Days

for constructing the Guardrail Installations on CR-28 (Cherry Tree Road) over Goose Creek and over Unnamed Tributary in Huntsville. Length 0.060 mi.

The Bracket Estimate on this project is from $58,353 to $71,320 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $5.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)



24.HRRR-5219(250) ,MORGAN COUNTY

Contract Time: 15 Working Days

for constructing the Guardrail Installations on CR-1004 (Danville Road) over a tributary of No Business Creek (Site 1); on CR 1296 (Apple Grove Road) over Hughes Creek and Cotaco Creek (Site 2 and Site 3); and on CR 1252 (Lockhart Road) over Shoal Creek. Length 0.226 mi.

The Bracket Estimate on this project is from $125,505 to $153,395 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $5.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)



25.HRRR-5519(250) ,PIKE COUNTY

Contract Time: 25 Working Days

for constructing the Guardrail Installations on CR-4442 over the Pea River Relief Bridge (Site 1); on CR-1165 over Youngblood Creek (Site 2); on CR-3339 over Whitewater Creek (Site 3); on CR-5534 over an unnamed creek (Site 4); and on CR-1111 over Beeman Creek (Site 5). Length 0.388 mi.

The Bracket Estimate on this project is from $227,926 to $278,577 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $5.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)



26.HRRR-5919(250) ,SHELBY COUNTY

Contract Time: 30 Working Days

for constructing the Safety Improvements (Clearing, Scoring, and Pavement Markers) on CR-26 from Walker Run to the junction of SR-70 in Columbiana. Length 4.663 mi.

The Bracket Estimate on this project is from $94,239 to $115,182 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $2.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)



27.HRRR-6119(250) ,TALLADEGA COUNTY

Contract Time: 35 Working Days

for constructing the Guardrail Installations on CR-399 over Cheaha and Choccolocco Creeks (Site 1 and Site 2); on CR-326 over Choccolocco Creek (Site 3); on CR-211 over Talladega Creek (Site 4); on CR-207 over Talladega Creek (Site 5); and on CR-009 over Four Mile Creek (Site 6). Length 0.694 mi.

The Bracket Estimate on this project is from $274,550 to $335,561 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $7.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)



29.HSIP-I085(364) ,LEE COUNTY

Contract Time: 55 Working Days

for constructing the Interstate Lighting Upgrades on I-85 at the Exit 58 Interchange in Opelika. Length 0.738 mi.

The Bracket Estimate on this project is from $432,312 to $528,381 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $12.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)



30.IM-I065(503) ,MORGAN COUNTY

Contract Time: 45 Working Days

for constructing the Interchange Lighting (LED Retrofit) on I-65 at SR-36 (Exit 328) in Hartselle. Length 0.748 mi.

The Bracket Estimate on this project is from $410,032 to $501,150 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $11.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)



31.IM-I065(506) ,BUTLER AND LOWNDES COUNTIES

Contract Time: 225 Working Days

for constructing the Guardrail Installation on I-65 from the Conecuh County Line to the Montgomery County Line. Length 53.171 mi.

The Bracket Estimate on this project is from $3,633,156 to $4,440,525 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $5.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)



34.STPBH-ACBR59503-ATRP(012) ,SHELBY COUNTY

Contract Time: 175 Working Days

DBE Goal Percent:5.00

for constructing the Bridge Replacement and Approaches on CR-52 over the Cahaba River from the junction of Oak View Lane to the junction of Old Cahaba Lane in Helena. Length 0.567 mi.

The Bracket Estimate on this project is from $6,523,741 to $7,973,461 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $39.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)



37.STPHV-4514(251) ,MADISON COUNTY

Contract Time: 390 Working Days

DBE Goal Percent:5.00

for constructing the Bridge Replacement (Grading, Drainage, Pavement, and Bridges) on CR-242 (Old Highway 431) over the Flint River and various unnamed tributaries north of Owens Cross Roads. Length 1.225 mi.

The Bracket Estimate on this project is from $10,387,518 to $12,695,855 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $81.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)



40.STPMB-7550(601) ,MOBILE COUNTY

Contract Time: 300 Working Days

DBE Goal Percent:8.00

for constructing the Additional Lanes (Grading, Drainage, Pavement, Traffic Signals, and Traffic Stripe) on CR-656 (Zeigler Boulevard) from the intersection of CR-372 (Schillinger Road) to the intersection of CR-429 (Cody Road) west of Mobile. Length 1.433 mi.

The Bracket Estimate on this project is from $8,706,751 to $10,641,584 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $100.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)



43.STPMN-2619(252) ,ELMORE COUNTY

Contract Time: 30 Working Days

DBE Goal Percent:3.00

for constructing the Widening, Resurfacing, and Traffic Stripe on the Coosada Parkway from the junction of the Alabama River Parkway to the junction of SR-14 southwest of Elmore. Length 5.709 mi.

The Bracket Estimate on this project is from $1,163,684 to $1,422,280 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $7.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)



46.STPNU-3519(250) & STPOA-3519(251) ,HOUSTON COUNTY

Contract Time: 35 Working Days

DBE Goal Percent:4.00

for constructing the Resurfacing and Traffic Stripe on CR-277 (Cumbie Road) from the Geneva County Line to the intersection of CR-32 (Judge Logue Road) northeast of Wicksburg (Site 1) and on Willie Varnum Road from the intersection of CR-33 to the junction of Eddins Road south of Dothan (Site 2). Length 6.903 mi.

The Bracket Estimate on this project is from $878,516 to $1,073,742 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $6.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)



50.STPPC-ACBR59582-ATRP(011) ,RUSSELL COUNTY

Contract Time: 120 Working Days

DBE Goal Percent:5.00

for constructing the Bridge Replacement on CR-427 (Opelika Road) and the Roadway Improvements (Grading, Drainage, Pavement, and Traffic Stripe) on CR-296 (Cutrate Road) in Phenix City. Length 0.245 mi.

The Bracket Estimate on this project is from $2,471,594 to $3,020,837 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $24.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)



56.99-508-693-000-921 ,WILCOX COUNTY

Contract Time: 50 Working Days

for the Maintenance Bridge Painting on SR-10 over Beaver Creek and the Alabama River Relief Bridges.

The Bracket Estimate on this project is from $92,029 to $112,480 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $9.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)