Office Engineer

Proposal Letting List
January 31, 2020, Transportation Letting

Welcome to the Proposal Letting List Page. You may view the approximate items of work with each proposal as a "printer friendly" page by clicking on the View Items hyperlink. Adobe Acrobat Reader will now be required to view the "View Items" pages. Please e-mail us with your comments.

Note: Adobe Acrobat Reader is now required to view the Proposal Item Summary pages.

2. BR-0068(505), CHEROKEE 8. HRRR-BRZ-3119(250), GENEVA
9. HRRR-3419(250), HENRY 13. NH-0005(558), CLARKE
15. NH-0020(530), LAWRENCE 16. NH-0021(568), TALLADEGA
17. NH-0035(536), JACKSON 18. NH-0038(541), SHELBY
21. NH-0053(586), LIMESTONE 22. NH-0053(587), HOUSTON
23. NH-0057(501), WASHINGTON 24. NH-0193(506), MOBILE
27. NH-FMGR-0002(585), JACKSON 30. NH-HSIP-0009(574), COVINGTON
32. STPAA-0185(504), BUTLER 33. STPAA-0004(546), ETC., JEFFERSON
34. STPAA-0010(548), CHOCTAW 37. STPAA-0188(504), MOBILE
38. STPAA-0229(507), ELMORE 39. STPAA-0263(503), BUTLER, ETC.
40. RASTPAA-2619(255), ETC., ELMORE 41. RASTPAA-3019(251), FRANKLIN
44. STPAA-HSIP-0014(546), MACON, ETC. 45. STPAA-HSIP-0050(506), TALLAPOOSA
46. STPAA-HSIP-0052(517), GENEVA, ETC. 47. STPAA-HSIP-0134(508), COFFEE
48. STPAA-HSIP-0265(502), WILCOX 51. STPBH-3715(269), JEFFERSON
*52. STPBH-3716(253), JEFFERSON 55. 99-407-234-053-901, DALE
*ALL BIDS REJECTED

The Bracket Ranges shown herein are to provide general financial information to Contractors and Bonding Companies concerning a Project's complexity and size. THESE BRACKETS SHOULD NOT BE USED IN PREPARING A BID, NOR WILL THESE BRACKETS HAVE ANY BEARING ON THE DECISION TO AWARD ANY CONTRACT.


2.BR-0068(505) ,CHEROKEE COUNTY

Contract Time: 175 Working Days

DBE Goal Percent:4.00

for constructing the Bridge Replacement (Grading, Drainage, Pavement, and Bridge) on SR-68 over the abandoned TAG Railroad 0.500 mile north of the junction of SR-273 in Leesburg. Length 0.359 mi.

The Bracket Estimate on this project is from $3,019,911 to $3,691,002 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $39.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


8.HRRR-BRZ-3119(250) ,GENEVA COUNTY

Contract Time: 15 Working Days

for constructing the Guardrail Installations on CR-10 over Eight Mile Creek (Site 1) and on CR-1 over Natural Bridge Creek (Site 2). Length 0.103 mi.

The Bracket Estimate on this project is from $101,817 to $124,443 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $4.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


9.HRRR-3419(250) ,HENRY COUNTY

Contract Time: 20 Working Days

for constructing the Guardrail Installation on CR-46 over Abbie Creek. Length 0.085 mi.

The Bracket Estimate on this project is from $33,260 to $40,651 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $5.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


13.NH-0005(558) ,CLARKE COUNTY

Contract Time: 35 Working Days

DBE Goal Percent:3.00

for constructing the Micro-Milling, Resurfacing, and Traffic Stripe on SR-5 from the junction of SR-13 (US-43) to the Wilcox County Line. Length 4.725 mi.

The Bracket Estimate on this project is from $919,086 to $1,123,327 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $6.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


15.NH-0020(530) ,LAWRENCE COUNTY

Contract Time: 55 Working Days

DBE Goal Percent:5.00

for constructing the Micro-Milling, Resurfacing (High Density Mineral Bond), and Traffic Stripe on SR-20 (US-72A) from 0.100 mile east of the junction of CR-585 to 0.120 mile west of the junction of SR-33 in Courtland. Length 4.787 mi.

The Bracket Estimate on this project is from $1,827,328 to $2,233,401 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


16.NH-0021(568) ,TALLADEGA COUNTY

Contract Time: 65 Working Days

DBE Goal Percent:3.00

for constructing the Micro-Milling, Resurfacing, and Traffic Stripe on SR-21 from 0.370 mile south of the junction of SR-76 to 0.190 mile south of the junction of CR-238 southwest of Talladega. Length 4.486 mi.

The Bracket Estimate on this project is from $2,314,083 to $2,828,324 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $4.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


17.NH-0035(536) ,JACKSON COUNTY

Contract Time: 55 Working Days

DBE Goal Percent:4.00

for constructing the Micro-Milling, Resurfacing, and Traffic Stripe on SR-35 from the junction of Breland Bluff Road to the junction of CR-67 northwest of Dutton. Length 3.800 mi.

The Bracket Estimate on this project is from $2,604,449 to $3,183,216 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $6.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


18.NH-0038(541) ,SHELBY COUNTY

Contract Time: 80 Working Days

DBE Goal Percent:3.00

for constructing the Micro-Milling, Leveling, Patching, Resurfacing, and Traffic Stripe on SR-38 (US-280) from a point west of the junction of CR-62 in Harpersville to the Talladega County Line. Length 7.307 mi.

The Bracket Estimate on this project is from $4,900,634 to $5,989,663 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $4.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


21.NH-0053(586) ,LIMESTONE COUNTY

Contract Time: 40 Working Days

DBE Goal Percent:8.00

for constructing the Micro-Milling, Resurfacing, and Traffic Stripe on SR-53 from north of the junction of CR-122 to the junction of SR-251 in Ardmore. Length 5.628 mi.

The Bracket Estimate on this project is from $1,083,157 to $1,323,858 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $4.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


22.NH-0053(587) ,HOUSTON COUNTY

Contract Time: 45 Working Days

DBE Goal Percent:6.00

for constructing the Pavement Preservation (Micro-Milling, Resurfacing, and Traffic Stripe) on SR-53 (US-231) from the junction of SR-210 (US-431/Ross Clark Circle) in Dothan to the Dale County Line. Length 3.587 mi.

The Bracket Estimate on this project is from $1,568,211 to $1,916,703 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $8.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


23.NH-0057(501) ,WASHINGTON COUNTY

Contract Time: 45 Working Days

DBE Goal Percent:2.00

for constructing the Micro-Milling, Resurfacing, and Traffic Stripe on SR-57 (US-45) from 0.340 mile north of the junction of Doug Price Road to the Mississippi State Line. Length 8.214 mi.

The Bracket Estimate on this project is from $1,426,375 to $1,743,347 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $5.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


24.NH-0193(506) ,MOBILE COUNTY

Contract Time: 90 Working Days

DBE Goal Percent:5.00

for constructing the Planing, Resurfacing, Guardrail Installation, and Traffic Stripe on SR-193 from the intersection of SR-163 to the juction of Higgins Road in Cypress Shores. Length 3.699 mi.

The Bracket Estimate on this project is from $1,897,956 to $2,319,724 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $9.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


27.NH-FMGR-0002(585) ,JACKSON COUNTY

Contract Time: 60 Working Days

DBE Goal Percent:5.00

for constructing the Micro-Milling, Resurfacing, and Traffic Stripe on SR-2 (US-72) from the junction of Porter Road to 0.440 mile west of the SR-35 Interchange in Scottsboro. Length 3.100 mi.

The Bracket Estimate on this project is from $2,090,104 to $2,554,572 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $11.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


30.NH-HSIP-0009(574) ,COVINGTON COUNTY

Contract Time: 35 Working Days

DBE Goal Percent:8.00

for constructing the Safety Widening and Pavement Preservation (Micro-Milling, Resurfacing, and Traffic Stripe) on SR-9 (US-331) from the North City Limits of Florala to the junction of Randell Road. Length 6.913 mi.

The Bracket Estimate on this project is from $1,358,869 to $1,660,840 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $7.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


32.STPAA-0185(504) ,BUTLER COUNTY

Contract Time: 40 Working Days

DBE Goal Percent:3.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-185 from the north end of the Railroad Bridge (MP 3.354) to the junction of Willow Lane in Greenville. Length 2.180 mi.

The Bracket Estimate on this project is from $1,036,922 to $1,267,349 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $9.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


33.STPAA-0004(546) & STPAA-0004(548) ,JEFFERSON COUNTY

Contract Time: 150 Working Days

DBE Goal Percent:5.00

for constructing the Planing, Resurfacing, Curb & Gutter Installation, and Traffic Stripe on SR-4 (US-78) from the 1st Avenue North Interchange in Birmingham to the junction of St. Patrick Circle in Irondale. Length 6.279 mi.

The Bracket Estimate on this project is from $4,957,750 to $6,059,472 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $31.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


34.STPAA-0010(548) ,CHOCTAW COUNTY

Contract Time: 35 Working Days

DBE Goal Percent:3.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-10 from the junction of CR-45 northwest of Lisman to a point 0.470 mile west of the Butler Town Limits. Length 7.134 mi.

The Bracket Estimate on this project is from $1,475,049 to $1,802,838 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $6.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


37.STPAA-0188(504) ,MOBILE COUNTY

Contract Time: 40 Working Days

DBE Goal Percent:3.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-188 from the junction of Franklin Road north of Grand Bay to the junction of Lakeland Drive. Length 4.011 mi.

The Bracket Estimate on this project is from $737,958 to $901,948 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $8.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


38.STPAA-0229(507) ,ELMORE COUNTY

Contract Time: 30 Working Days

for constructing the Pavement Preservation [Resurfacing (Scrub Seal) and Traffic Stripe] on SR-229 from the junction of SR-14 in Burlington to the junction of SR-63. Length 10.818 mi.

The Bracket Estimate on this project is from $1,016,588 to $1,242,496 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $2.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


39.STPAA-0263(503) ,BUTLER AND LOWNDES COUNTIES

Contract Time: 30 Working Days

for constructing the Resurfacing (Seal Coat) and Traffic Stripe on SR-263 from the junction of SR-185 to the junction of SR-21 northwest of Greenville. Length 15.131 mi.

The Bracket Estimate on this project is from $1,433,850 to $1,752,484 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $7.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


40.RASTPAA-2619(255) & STPAA-2619(254) ,ELMORE COUNTY

Contract Time: 30 Working Days

DBE Goal Percent:2.00

for constructing the Resurfacing and Traffic Stripe on CR-7 (Deatsville Highway) from the North City Limits of Millbrook to the junction of Alpha Lane in Deatsville (Site 1) and on Foxwood Road from the Autauga County Line to the junction of Deatsville Highway in Deatsville (Site 2). Length 5.624 mi.

The Bracket Estimate on this project is from $831,775 to $1,016,613 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $8.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


41.RASTPAA-3019(251) ,FRANKLIN COUNTY

Contract Time: 30 Working Days

DBE Goal Percent:1.00

for constructing the Resurfacing and Traffic Stripe on CR-60 from the junction of Badgett Road to the junction of CR-56 (Site 1); on CR-56 from the junction of CR-60 to the junction of CR-77 (Site 2); and on CR-77 from the junction of CR-56 to the Colbert County Line (Site 3). Length 4.152 mi.

The Bracket Estimate on this project is from $502,360 to $613,995 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


44.STPAA-HSIP-0014(546) ,MACON AND TALLAPOOSA COUNTIES

Contract Time: 50 Working Days

DBE Goal Percent:3.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-14 from the Tallapoosa County Line to the Lee County Line. Length 9.305 mi.

The Bracket Estimate on this project is from $2,325,445 to $2,842,211 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $9.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


45.STPAA-HSIP-0050(506) ,TALLAPOOSA COUNTY

Contract Time: 40 Working Days

DBE Goal Percent:2.00

for constructing the Safety Widening, Micro-Milling, Resurfacing, and Traffic Stripe on SR-50 from the junction of SR-38 (US-280) in Camp Hill to the Chambers County Line. Length 5.412 mi.

The Bracket Estimate on this project is from $1,397,179 to $1,707,663 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $4.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


46.STPAA-HSIP-0052(517) ,GENEVA, COFFEE, AND COVINGTON COUNTIES

Contract Time: 95 Working Days

DBE Goal Percent:6.00

for constructing the Safety Widening, Micro-Milling, Resurfacing, and Traffic Stripe on SR-52 from the junction of SR-9 (US-331) in Opp to the junction of Harvest Time Road west of Samson. Length 14.533 mi.

The Bracket Estimate on this project is from $3,774,673 to $4,613,489 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $9.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


47.STPAA-HSIP-0134(508) ,COFFEE COUNTY

Contract Time: 70 Working Days

DBE Goal Percent:6.00

for constructing the Safety Widening, Planing, Resurfacing, and Traffic Stripe on SR-134 from the junction of SR-87 to the junction of SR-88 in Enterprise. Length 10.769 mi.

The Bracket Estimate on this project is from $3,254,387 to $3,977,584 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $8.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


48.STPAA-HSIP-0265(502) ,WILCOX COUNTY

Contract Time: 40 Working Days

DBE Goal Percent:2.00

for constructing the Safety Widening, Resurfacing, and Traffic Stripe on SR-265 from the Monroe County Line to 0.970 mile north the junction of CR-51. Length 6.037 mi.

The Bracket Estimate on this project is from $958,325 to $1,171,286 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $6.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


51.STPBH-3715(269) ,JEFFERSON COUNTY

Contract Time: 30 Working Days

for constructing the Pavement Rehabilitation (Micro-Milling, Resurfacing, and Traffic Stripe) on Lakeshore Parkway from the junction of Leaf Drive to the junction of Venice Road southeast of Wenonah. Length 1.987 mi.

The Bracket Estimate on this project is from $920,233 to $1,124,729 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $12.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


52.STPBH-3716(253) ,JEFFERSON COUNTY

Contract Time: 135 Working Days

for constructing the Interstate Lighting Upgrades and Replacements on I-20/59 from a point east of the EB Stephens Expressway Interchange to a point east of the I-20/59 Split in Birmingham. Length 3.522 mi.

The Bracket Estimate on this project is from $1,072,955 to $1,311,390 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $17.00 per set.

****ALL BIDS REJECTED****

Return To: Proposal Letting List (Top of web page)


55.99-407-234-053-901 ,DALE COUNTY

Contract Time: 75 Working Days

for constructing the Bridge Culvert Extension on SR-53 (US-231) at MP 32.996 (Northbound Lane) in Pinckard. Length 0.046 mi.

The Bracket Estimate on this project is from $437,707 to $534,976 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $9.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)