3. ACBRZ59621-ATRP(007), TUSCALOOSA 7. BR-0021(554), TALLADEGA
15. HRRR-0920(250), CHAMBERS *16. HRRR-0720(251), BUTLER
17. HRRR-6020(250), SUMTER 20. HSIP-0251(501), LIMESTONE
21. HSIP-I459(312), JEFFERSON 24. IM-HSIP-I022(310), MARION
27. NH-0002(590), LAUDERDALE 28. NH-0005(560), WILCOX
29. NH-0012(573), ETC., MONROE *30. NH-0053(589), MONTGOMERY
31. NH-0182(507), BALDWIN 33. NH-HSIP-0016(527), MOBILE
37. RABRZ-6014(258), SUMTER 40. RASTPAA-3720(250), JEFFERSON
43. RP-NH-0052(518), HOUSTON 45. RP-STPAA-0015(538), MACON
46. RP-STPAA-0027(516), COFFEE 49. STPAA-0010(549), PIKE
50. STPAA-0010(552), CRENSHAW 51. STPAA-0019(506), FRANKLIN
52. STPAA-0028(515), WILCOX 53. STPAA-0051(517), COFFEE
54. STPAA-0055(515), BUTLER 55. STPAA-0180(506), BALDWIN
56. STPAA-0188(505), MOBILE 59. STPAA-HSIP-0008(598), MACON
60. STPAA-HSIP-0068(510), CHEROKEE 61. STPAA-HSIP-0075(537), ETC., MARSHALL
62. STPAA-HSIP-0075(538), BLOUNT 64. STPAA-HSIP-0241(502), MARION
68. STPBH-7073(602), JEFFERSON 71. STPMN-2620(252), ELMORE
74. STPOA-0815(261), CALHOUN **75. STPOA-0815(263), CALHOUN
76. STPOA-1720(250), COLBERT 81. ATRP2-26-2020-026-3, ELMORE
* - WITHDRAWN FROM THE LETTING
** - ALL BIDS REJECTED

The Bracket Ranges shown herein are to provide general financial information to Contractors and Bonding Companies concerning a Project's complexity and size. THESE BRACKETS SHOULD NOT BE USED IN PREPARING A BID, NOR WILL THESE BRACKETS HAVE ANY BEARING ON THE DECISION TO AWARD ANY CONTRACT.


3.ACBRZ59621-ATRP(007) ,TUSCALOOSA COUNTY

Contract Time: 95 Working Days

DBE Goal Percent:3.00

for constructing the Bridge Replacement on CR-1358 (Holman Church Road) over the Kansas City Southern Railroad southeast of Gordo. Length 0.033 mi.

The Bracket Estimate on this project is from $1,293,837 to $1,581,356 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $16.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


7.BR-0021(554) ,TALLADEGA COUNTY

Contract Time: 260 Working Days

DBE Goal Percent:5.00

for constructing the Bridge Replacement (Grading, Drainage, Pavement, and Bridge) on SR-21 over Cheaha Creek southwest of Munford. Length 0.757 mi.

The Bracket Estimate on this project is from $6,344,952 to $7,754,941 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $51.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


15.HRRR-0920(250) ,CHAMBERS COUNTY

Contract Time: 30 Working Days

for constructing the Widening, Leveling, Resurfacing, and Traffic Stripe on CR-289 from a point north of the junction of CR-216 northwest for 770 feet. Length 0.145 mi.

The Bracket Estimate on this project is from $111,552 to $136,341 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


16.HRRR-0720(251) ,BUTLER COUNTY

Contract Time: 15 Working Days

for constructing the Guardrail and Guardrail End Anchor Installations on CR-11 over Cedar Creek Relief. Length 0.077 mi.

The Bracket Estimate on this project is from $62,861 to $76,830 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $4.00 per set.

****WITHDRAWN FROM THE LETTING****

Return To: Proposal Letting List (Top of web page)


17.HRRR-6020(250) ,SUMTER COUNTY

Contract Time: 15 Working Days

for constructing the Intersection Improvements (Traffic Control Devices) on CR-34 at CR-83 in Panola. Length 1.000 mi.

The Bracket Estimate on this project is from $46,704 to $57,082 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


20.HSIP-0251(501) ,LIMESTONE COUNTY

Contract Time: 140 Working Days

DBE Goal Percent:7.00

for constructing the Intersection Modifications to include the Roundabout Installation (Grading, Drainage, Pavement, and Lighting) on SR-251 at CR-83 (Lindsay Lane) in Athens. Length 0.378 mi.

The Bracket Estimate on this project is from $3,515,223 to $4,296,384 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $45.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


21.HSIP-I459(312) ,JEFFERSON COUNTY

Contract Time: 65 Working Days

DBE Goal Percent:4.00

for constructing the Median Crossover Protection (Cable Guiderail Installation) on the I-20/I-59 Interchange to a point south of the SR-150 Underpass (MP 10.700) in Hoover. Length 10.699 mi.

The Bracket Estimate on this project is from $857,325 to $1,047,841 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $9.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


24.IM-HSIP-I022(310) ,MARION COUNTY

Contract Time: 150 Working Days

DBE Goal Percent:7.00

for constructing the Planing, Resurfacing, Guardrail Steel Blockout Replacement, and Traffic Stripe on I-22 from the Mississippi State Line to just west of the Reese Road Overpass (MP 6.000). Length 5.987 mi.

The Bracket Estimate on this project is from $8,229,190 to $10,057,898 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $15.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


27.NH-0002(590) ,LAUDERDALE COUNTY

Contract Time: 50 Working Days

DBE Goal Percent:10.00

for constructing the Micro-Milling, Resurfacing, and Traffic Stripe on SR-2 (US-72) from the north end of the O'Neal Bridge (MP 31.185) to the junction of Glendale Street in Florence. Length 2.064 mi.

The Bracket Estimate on this project is from $1,179,873 to $1,442,067 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $5.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


28.NH-0005(560) ,WILCOX COUNTY

Contract Time: 30 Working Days

DBE Goal Percent:1.00

for constructing the Micro-Milling, Resurfacing (Scrub Seal), and Traffic Stripe on SR-5 from the Clarke County Line to south of the Moccasin Creek Bridge in Pine Hill. Length 3.915 mi.

The Bracket Estimate on this project is from $912,874 to $1,115,735 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $6.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


29.NH-0012(573) & NH-0012(535) ,MONROE COUNTY

Contract Time: 65 Working Days

DBE Goal Percent:3.00

for constructing the Planing, Resurfacing, Bridge Rail Retrofit, Guardrail Replacement, and Traffic Stripe on SR-12 (US-84) from the Clarke County Line to a point east of the junction of CR-1 (MP 66.580) southeast of Purdue Hill. Length 8.418 mi.

The Bracket Estimate on this project is from $1,632,241 to $1,994,961 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $11.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


30.NH-0053(589) ,MONTGOMERY COUNTY

Contract Time: 95 Working Days

DBE Goal Percent:5.00

for constructing the Planing, Resurfacing, Guardrail Installation, and Traffic Stripe on SR-53 (US-231) from the junction of CR-89 in Pine Level to the junction of Athey Road. Length 4.656 mi.

The Bracket Estimate on this project is from $4,214,116 to $5,150,586 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $15.00 per set.

****WITHDRAWN FROM THE LETTING****

Return To: Proposal Letting List (Top of web page)


31.NH-0182(507) ,BALDWIN COUNTY

Contract Time: 40 Working Days

DBE Goal Percent:1.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-182 from the West City Limits of Orange Beach to the Perdido Pass Bridge. Length 3.283 mi.

The Bracket Estimate on this project is from $1,476,709 to $1,804,866 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $9.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


33.NH-HSIP-0016(527) ,MOBILE COUNTY

Contract Time: 40 Working Days

DBE Goal Percent:3.00

for constructing the Planing, Resurfacing, Guardrail Steel Blockout Replacement, and Traffic Stripe on SR-16 (US-90) from 0.340 mile east of the Cochrane Bridge to 0.360 mile west of the Tensaw River Bridge in Mobile. Length 2.935 mi.

The Bracket Estimate on this project is from $2,051,743 to $2,507,686 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $10.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


37.RABRZ-6014(258) ,SUMTER COUNTY

Contract Time: 75 Working Days

DBE Goal Percent:4.00

for constructing the Bridge Replacement on Bunkum Road over an unnamed creek 1.500 miles east of the junction CR-9. Length 0.051 mi.

The Bracket Estimate on this project is from $365,626 to $446,876 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $18.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


40.RASTPAA-3720(250) ,JEFFERSON COUNTY

Contract Time: 40 Working Days

DBE Goal Percent:7.00

for constructing the Planing, Resurfacing, and Traffic Stripe on CR-65 (Minor Parkway) from the junction of SR-269 (Birmingport Road) in Sherman Heights to 0.260 mile south of the junction of CR-67 (Crumly Chapel Road) in Adamsville. Length 2.819 mi.

The Bracket Estimate on this project is from $1,788,550 to $2,186,005 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $8.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


43.RP-NH-0052(518) ,HOUSTON COUNTY

Contract Time: 45 Working Days

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-52 from the intersection of SR-605 to the junction of SR-210 (US-231/Ross Clark Circle) in Dothan. Length 3.023 mi.

The Bracket Estimate on this project is from $2,214,676 to $2,706,826 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $9.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


45.RP-STPAA-0015(538) ,MACON COUNTY

Contract Time: 190 Working Days

DBE Goal Percent:6.00

for constructing the Micro-Milling, Resurfacing, and Traffic Stripe on SR-15 (US-29) from the Bullock County Line to the junction of SR-8 (US-80) in Tuskegee. Length 14.689 mi.

The Bracket Estimate on this project is from $3,067,357 to $3,748,992 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $4.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


46.RP-STPAA-0027(516) ,COFFEE COUNTY

Contract Time: 65 Working Days

DBE Goal Percent:2.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-27 from the junction of SR-12 in Enterprise to the Dale County Line. Length 7.484 mi.

The Bracket Estimate on this project is from $2,601,440 to $3,179,537 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $9.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


49.STPAA-0010(549) ,PIKE COUNTY

Contract Time: 55 Working Days

DBE Goal Percent:8.00

for constructing the Micro-Milling, Resurfacing, Guardrail Installation, and Traffic Stripe on SR-10 (US-29) from the Crenshaw County Line to the SR-53 (US-231) Overpass in Troy. Length 11.394 mi.

The Bracket Estimate on this project is from $2,560,869 to $3,129,951 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $9.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


50.STPAA-0010(552) ,CRENSHAW COUNTY

Contract Time: 30 Working Days

DBE Goal Percent:2.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-10 from the intersection of Glenwood Avenue in Luverne to the end of the four-lane section near the junction of Martin Road (MP 150.135). Length 1.969 mi.

The Bracket Estimate on this project is from $688,978 to $842,084 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $7.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


51.STPAA-0019(506) ,FRANKLIN COUNTY

Contract Time: 40 Working Days

DBE Goal Percent:7.00

for constructing the Micro-Milling, Resurfacing, and Traffic Stripe on SR-19 from the junction of 11th Street in Red Bay to the Mississippi State Line. Length 1.812 mi.

The Bracket Estimate on this project is from $582,891 to $712,422 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


52.STPAA-0028(515) ,WILCOX COUNTY

Contract Time: 45 Working Days

DBE Goal Percent:2.00

for constructing the Micro-Milling, Resurfacing (Scrub Seal), and Traffic Stripe on SR-28 from 0.450 mile west of the intersection of SR-5 to 0.120 mile west of the junction of SR-162. Length 6.149 mi.

The Bracket Estimate on this project is from $1,533,076 to $1,873,760 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $6.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


53.STPAA-0051(517) ,COFFEE COUNTY

Contract Time: 30 Working Days

for constructing the Preventative Maintenance (Micro-Milling, Resurfacing, and Traffic Stripe) on SR-51 from the junction of SR-12 (US-84) to the junction of SR-167 northeast of New Brockton. Length 5.654 mi.

The Bracket Estimate on this project is from $758,503 to $927,060 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $7.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


54.STPAA-0055(515) ,BUTLER COUNTY

Contract Time: 90 Working Days

DBE Goal Percent:3.00

for constructing the Micro-Milling, Resurfacing, and Traffic Stripe on SR-55 from a point south of the junction of SR-3 (US-31) MP 52.690 to a point north of the junction of SR-106 (MP 57.541) to include the Right Turn Lane Addition on SR-55 at SR-3 (US-31) in Georgiana. Length 4.850 mi.

The Bracket Estimate on this project is from $3,478,434 to $4,251,420 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


55.STPAA-0180(506) ,BALDWIN COUNTY

Contract Time: 50 Working Days

DBE Goal Percent:2.00

for constructing the Micro-Milling, Resurfacing, and Traffic Stripe on SR-180 from a point near the Fort Morgan Historical Site (MP 0.000) to the junction of SR-59 in Gulf Shores. Length 20.779 mi.

The Bracket Estimate on this project is from $2,197,622 to $2,685,982 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $10.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


56.STPAA-0188(505) ,MOBILE COUNTY

Contract Time: 30 Working Days

DBE Goal Percent:4.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-188 from MP 4.640 to the junction of the Bayou La Batre - Irvington Highway in Bayou La Batre. Length 3.845 mi.

The Bracket Estimate on this project is from $738,956 to $903,169 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $7.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


59.STPAA-HSIP-0008(598) ,MACON COUNTY

Contract Time: 35 Working Days

DBE Goal Percent:1.00

for constructing the Safety Widening, Resurfacing, and Traffic Stripe on SR-8 (US-80) from the beginning of the divided 4-Lane Section (MP 167.290) to the end of the divided 4-Lane Section (MP 171.160) in Tuskegee. Length 3.870 mi.

The Bracket Estimate on this project is from $1,486,872 to $1,817,288 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


60.STPAA-HSIP-0068(510) ,CHEROKEE COUNTY

Contract Time: 35 Working Days

DBE Goal Percent:6.00

for constructing the Micro-Milling, Resurfacing, Guardrail Reset, and Traffic Stripe on SR-68 from the junction of SR-9 in Cedar Bluff to the junction of SR-35 in Gaylesville. Length 4.799 mi.

The Bracket Estimate on this project is from $1,596,557 to $1,951,348 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $8.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


61.STPAA-HSIP-0075(537) & STPAA-0205(510) ,MARSHALL COUNTY

Contract Time: 60 Working Days

DBE Goal Percent:5.00

for constructing the Intersection Safety Improvements, Micro-Milling, Resurfacing, and Traffic Stripe on SR-75 from the junction of Strickland Street to the intersection of SR-1 (US-431) (Site 1) and on SR-205 from a point south of the junction of Guinivere Drive (MP 6.670) to the intersection of SR-75 in Albertville (Site 2). Length 4.350 mi.

The Bracket Estimate on this project is from $2,612,866 to $3,193,503 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $11.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


62.STPAA-HSIP-0075(538) ,BLOUNT COUNTY

Contract Time: 60 Working Days

DBE Goal Percent:4.00

for constructing the Safety Widening, Micro-Milling, Resurfacing, Safety Improvements, and Traffic Stripe on SR-75 from a point north of the junction of CR-39 to a point south of the junction of Kornegay Road south of Snead. Length 4.409 mi.

The Bracket Estimate on this project is from $1,533,029 to $1,873,702 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


64.STPAA-HSIP-0241(502) ,MARION COUNTY

Contract Time: 55 Working Days

DBE Goal Percent:3.00

for constructing the Safety Widening, Micro-Milling, Resurfacing, and Traffic Stripe on SR-241 from the junction of CR-143 to MP 11.086 south of the junction of SR-172 in Bear Creek. Length 4.542 mi.

The Bracket Estimate on this project is from $2,325,764 to $2,842,600 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $11.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


68.STPBH-7073(602) ,JEFFERSON COUNTY

Contract Time: 150 Working Days

DBE Goal Percent:10.00

for constructing the Roadway Widening (Grading, Drainage, Pavement, Traffic Signals, and Traffic Stripe) on SR-7 (US-11) from the intersection of Chalkville Road to the Cahaba River Bridge in Trussville. Length 0.492 mi.

The Bracket Estimate on this project is from $2,724,184 to $3,329,558 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $42.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


71.STPMN-2620(252) ,ELMORE COUNTY

Contract Time: 175 Working Days

DBE Goal Percent:11.00

for constructing the Intersection Improvements with Roundabout on Orline Street at Company Street to include constructing the Sidewalk Installation, Pedestrian Lighting, and Landscape Improvements on Company Street from the junction of East Bridge Street to the junction of Orline Street; on Orline Street from the junction of Company Street to the junction of Hill Street; and on Hill Street from the junction of Orline Street to the junction of East Bridge Street in Wetumpka. Length 0.116 mi.

The Bracket Estimate on this project is from $1,082,487 to $1,323,040 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $16.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


74.STPOA-0815(261) ,CALHOUN COUNTY

Contract Time: 75 Working Days

DBE Goal Percent:3.00

for constructing the Planing, Resurfacing, and Traffic Stripe on Church Avenue from the junction of SR-21 to the junction of 11th Street in Jacksonville. Length 3.324 mi.

The Bracket Estimate on this project is from $1,135,555 to $1,387,900 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $20.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


75.STPOA-0815(263) ,CALHOUN COUNTY

Contract Time: 60 Working Days

DBE Goal Percent:9.00

for constructing the Roundabout Installation on CR-109 (Bynum Leatherwood Road) at the intersection of Old Gadsden Highway in Blue Mountain. Length 0.178 mi.

The Bracket Estimate on this project is from $769,174 to $940,102 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $24.00 per set.

****ALL BIDS REJECTED****

Return To: Proposal Letting List (Top of web page)


76.STPOA-1720(250) ,COLBERT COUNTY

Contract Time: 30 Working Days

DBE Goal Percent:4.00

for constructing the Resurfacing and Traffic Stripe on CR-55 (Woodmont Drive) from the junction of Ponderosa Drive to the South City Limits of Tuscumbia. Length 5.475 mi.

The Bracket Estimate on this project is from $889,965 to $1,087,735 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $5.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


81.ATRP2-26-2020-026-3 ,ELMORE COUNTY

Contract Time: 35 Working Days

DBE Goal Percent:3.00

for constructing the Left Turn Lane Installation (Planing, Resurfacing, Traffic Signals, and Traffic Stripe) on SR-143 at Cobbs Ford Road in Millbrook. Length 0.224 mi.

The Bracket Estimate on this project is from $356,594 to $435,838 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $14.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


999.BP-NHF-0042(517) & ST-049-I10-006 ,MOBILE COUNTY

Contract Time: 30 Working Days

for the Maintenance Demolition of Building Structures on Glenwood Road over the SR-42 (US-98 ) Overpass and on I-10 at the Mobile River Bridge and the Bayway Corridor.

The Bracket Estimate on this project is from $76,061 to $92,964 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $4.00 per set.

View Items