Office Engineer

Proposal Letting List
December 03, 2021, Transportation Letting

Welcome to the Proposal Letting List Page. You may view the approximate items of work with each proposal as a "printer friendly" page by clicking on the View Items hyperlink. Adobe Acrobat Reader will now be required to view the "View Items" pages. Please e-mail us with your comments.

Note: Adobe Acrobat Reader is now required to view the Proposal Item Summary pages.

1. ERPR-9070(932), WILCOX 4. HRRR-0521(250), BLOUNT
5. HRRR-2221(250), CULLMAN 6. HRRR-4521(250), MADISON
9. HSIP-0008(600), RUSSELL 11. HSIP-I085(375), MONTGOMERY
14. IM-I059(409), ETOWAH 17. NH-0008(602), SUMTER
23. RP-NH-FMGR-0005(562), ETC., DALLAS 24. RP-STPAA-HSIP-0172(505), MARION
28. STPAA-0019(507), FRANKLIN 29. STPAA-0022(533), RANDOLPH
30. STPAA-0069(570), CULLMAN 31. STPAA-0093(503), PIKE
32. STPAA-0205(511), MARSHALL 35. STPAA-FMGR-0006(582), BULLOCK
42. STPAA-HSIP-FMGR-0049(515), TALLAPOOSA 44. STPAA-HSIP-MR22(900), MOBILE
51. STPOA-4116(250), LEE 55. ATRP2-46-2021-046, MARENGO
56. ATRP2-59-2020-059, SHELBY *57. ATRP2-HSIP-0002(587), ETC., JACKSON
*60. ST-002-000-015, BALDWIN
-*WITHDRAWN FROM THE LETTING

The Bracket Ranges shown herein are to provide general financial information to Contractors and Bonding Companies concerning a Project's complexity and size. THESE BRACKETS SHOULD NOT BE USED IN PREPARING A BID, NOR WILL THESE BRACKETS HAVE ANY BEARING ON THE DECISION TO AWARD ANY CONTRACT.


1.ERPR-9070(932) ,WILCOX COUNTY

Contract Time: 30 Working Days

for constructing the Slide Repair on CR-37 at various sites between the intersection of CR-31 and the junction of CR-43 northeast of Camden. Length 0.084 mi.

The Bracket Estimate on this project is from $543,537 to $664,323 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $11.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


4.HRRR-0521(250) ,BLOUNT COUNTY

Contract Time: 35 Working Days

DBE Goal Percent:3.00

for constructing the Widening, Resurfacing, and Traffic Stripe on CR-8 (Skyline Drive) from the junction of Rickwood Caverns Road to a point easterly at MP 4.355 west of Smoke Rise. Length 2.140 mi.

The Bracket Estimate on this project is from $234,292 to $286,357 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $5.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


5.HRRR-2221(250) ,CULLMAN COUNTY

Contract Time: 30 Working Days

for constructing the Safety Improvements (Guardrail Installation and Traffic Stripe) on CR-1301 from the intersection of CR-1435 in Cullman to the intersection of SR-3 (US-31). Length 1.857 mi.

The Bracket Estimate on this project is from $62,669 to $76,595 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $4.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


6.HRRR-4521(250) ,MADISON COUNTY

Contract Time: 30 Working Days

for constructing the Safety Improvements (Shoulder Widening, Guardrail Installation, Pavement Markers, and Traffic Stripe) on Dug Hill Road from a point 1500 feet north of the junction of King Drake Road to the junction of Raintree Road in Huntsville. Length 0.109 mi.

The Bracket Estimate on this project is from $92,950 to $113,606 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $6.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


9.HSIP-0008(600) ,RUSSELL COUNTY

Contract Time: 35 Working Days

for constructing the Roadway Improvements (High Friction Surface Treatment) on the SR-8 (US-80) Eastbound Ramp from the SR-1 (US-280) Interchange to the intersection of South Railroad Street in Phenix City. Length 0.227 mi.

The Bracket Estimate on this project is from $140,473 to $171,689 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


11.HSIP-I085(375) ,MONTGOMERY COUNTY

Contract Time: 35 Working Days

for constructing the Roadway Improvements (High Friction Surface Treatment) on the I-85 Southbound Ramp to I-65 (Southbound) in Montgomery. Length 0.222 mi.

The Bracket Estimate on this project is from $420,888 to $514,419 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $2.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


14.IM-I059(409) ,ETOWAH AND DEKALB COUNTIES

Contract Time: May 17, 2024 Completion Date

DBE Goal Percent:1.00

for constructing the Reconstruction (Grading, Drainage, Pavement, and Pavement Removal) on I-59 (Northbound Roadway and the Southbound Outside Shoulder) from 0.390 mile south of the CR-276 (Stephens Gap Road) Overpass northeast of Reece City to approximately 0.500 mile south of the SR-68 (Exit 205) Interchange in Collinsville. Length 10.896 mi.

The Bracket Estimate on this project is from $32,775,224 to $40,058,607 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $131.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


17.NH-0008(602) ,SUMTER COUNTY

Contract Time: 100 Working Days

DBE Goal Percent:3.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-8 (US-80) from west of the junction of Pine Street (MP 14.322) in Bellamy to west of the junction of SR-28 (MP 20.00). Length 5.677 mi.

The Bracket Estimate on this project is from $4,087,508 to $4,995,844 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $9.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


23.RP-NH-FMGR-0005(562) & NH-0005(564) ,DALLAS COUNTY

Contract Time: 70 Working Days

DBE Goal Percent:4.00

for constructing the Planing, Resurfacing, Guardrail Installation, Steel Blockout Replacement, and Traffic Stripe on SR-5 from the intersection of CR-21 to the Perry County Line. Length 7.822 mi.

The Bracket Estimate on this project is from $2,567,491 to $3,138,044 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $9.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


24.RP-STPAA-HSIP-0172(505) ,MARION COUNTY

Contract Time: 60 Working Days

DBE Goal Percent:1.00

for constructing the Safety Widening, Micro-Milling, Resurfacing, and Traffic Stripe on SR-172 from the Franklin County Line to the Intersection of SR-17 in Hackleburg. Length 6.013 mi.

The Bracket Estimate on this project is from $2,518,984 to $3,078,759 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $15.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


28.STPAA-0019(507) ,FRANKLIN COUNTY

Contract Time: 35 Working Days

DBE Goal Percent:5.00

for constructing the Micro-Milling, Resurfacing, and Traffic Stripe on SR-19 from the Marion County Line to the junction of SR-172 southeast of Vina. Length 3.600 mi.

The Bracket Estimate on this project is from $745,810 to $911,545 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


29.STPAA-0022(533) ,RANDOLPH COUNTY

Contract Time: 30 Working Days

for constructing the Micro-Milling, Resurfacing, and Traffic Stripe on SR-22 from a point 0.610 mile east of the junction of CR-855 (MP 157.835) to the intersection of SR-1 (US-431) in Roanoke. Length 2.234 mi.

The Bracket Estimate on this project is from $728,871 to $890,842 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


30.STPAA-0069(570) ,CULLMAN AND MARSHALL COUNTIES

Contract Time: 55 Working Days

DBE Goal Percent:5.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-69 from 0.171 mile south of the Intersection of SR-67 to 0.134 mile south of the SR-53 (US-231) Overpass in Arab. Length 5.510 mi.

The Bracket Estimate on this project is from $2,278,991 to $2,785,433 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $7.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


31.STPAA-0093(503) ,PIKE COUNTY

Contract Time: 35 Working Days

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-93 from the junction of SR-53 (US-231) to the junction of Lakeview Drive in Brundidge. Length 2.429 mi.

The Bracket Estimate on this project is from $1,083,561 to $1,324,352 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $10.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


32.STPAA-0205(511) ,MARSHALL COUNTY

Contract Time: 30 Working Days

DBE Goal Percent:5.00

for constructing the Micro-Milling, Resurfacing, and Traffic Stripe on SR-205 from the Etowah County Line to the junction of Henderson Avenue in Albertville. Length 2.280 mi.

The Bracket Estimate on this project is from $1,064,786 to $1,301,405 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $10.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


35.STPAA-FMGR-0006(582) ,BULLOCK COUNTY

Contract Time: 45 Working Days

DBE Goal Percent:10.00

for constructing the Micro-Milling, Resurfacing, Steel Blockout Replacement, and Traffic Stripe on SR-6 (US-82) from a point 0.450 mile east of the Bowlin Creek Bridge to the junction of Conecuh Avenue West in Union Springs. Length 5.276 mi.

The Bracket Estimate on this project is from $1,133,269 to $1,385,106 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $4.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


42.STPAA-HSIP-FMGR-0049(515) ,TALLAPOOSA COUNTY

Contract Time: 70 Working Days

DBE Goal Percent:1.00

for constructing the Safety Widening, Micro-Milling, Resurfacing, Bridge Guardrail Retrofit, and Traffic Stripe on SR-49 from the junction of SR-38 (US-280) in Dadeville to a point 0.084 mile south of the junction of CR-57 (MP 39.710). Length 8.311 mi.

The Bracket Estimate on this project is from $2,343,120 to $2,863,813 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $4.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


44.STPAA-HSIP-MR22(900) ,MOBILE COUNTY

Contract Time: 110 Working Days

DBE Goal Percent:1.00

for constructing the Safety Widening, Planing, Resurfacing, Steel Blockout Replacement, and Traffic Stripe on I-65 (Service Roads) from the SR-16 (US-90) Interchange in Mobile to the SR-17 (US-45) Interchange in Prichard. Length 12.997 mi.

The Bracket Estimate on this project is from $2,940,239 to $3,593,625 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $14.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


51.STPOA-4116(250) ,LEE COUNTY

Contract Time: 250 Working Days

DBE Goal Percent:3.00

for constructing the Drainage Improvements, Widening, Planing, Resurfacing, and Traffic Stripe on South College Street, Samford Avenue, Gay Street, and Reese Avenue in Auburn. Length 0.429 mi.

The Bracket Estimate on this project is from $4,095,325 to $5,005,397 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $39.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


55.ATRP2-46-2021-046 ,MARENGO COUNTY

Contract Time: 90 Working Days

for constructing the Safety Improvements (Roadway Lighting Installation) on SR-8 (US-80) at the Westrock Paper Mill Entrances. Length 1.912 mi.

The Bracket Estimate on this project is from $612,765 to $748,935 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $9.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


56.ATRP2-59-2020-059 ,SHELBY COUNTY

Contract Time: 110 Working Days

DBE Goal Percent:2.00

for constructing the Bridge Replacement and Approaches on SR-25 over Waxahatchee Creek southwest of Columbiana. Length 0.245 mi.

The Bracket Estimate on this project is from $1,659,365 to $2,028,113 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $24.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


57.ATRP2-HSIP-0002(587) & ATRP2-36-2021-445 ,JACKSON COUNTY

Contract Time: 125 Working Days

DBE Goal Percent:5.00

for constructing the Operational and Intersection Improvements on SR-2 (US-72) at County Park Road to include Service Road Extensions in Scottsboro. Length 0.539 mi.

The Bracket Estimate on this project is from $2,005,956 to $2,451,724 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $51.00 per set.

WITHDRAWN FROM THE LETTING

Return To: Proposal Letting List (Top of web page)


60.ST-002-000-015 ,BALDWIN COUNTY

Contract Time: June 28, 2024 Completion Date

for constructing the Connector Road (Grading, Drainage, Pavement, Bridge, Fence Installation, Traffic Lighting, and Traffic Stripe) on SR-161 from the junction SR-180 to a point north of the junction of CR-4 (Cotton Creek Drive) in Gulf Shores. Length 1.078 mi.

The Bracket Estimate on this project is from $35,636,838 to $43,556,135 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $97.00 per set.

WITHDRAWN FROM THE LETTING

Return To: Proposal Letting List (Top of web page)