1. BUILDF-NHF-0002(516), LAUDERDALE 4. HSIP-0013(620), ETC., CLARKE
8. BR-I059(428), TUSCALOOSA 11. HRRR-6122(250), TALLADEGA
14. NH-0008(606), ETC., LOWNDES 18. IM-I065(524), CHILTON
19. IM-I065(528), LIMESTONE 20. IM-I459(321), JEFFERSON
24. NH-0001(628), MADISON 25. NH-0003(650), ESCAMBIA
27. NH-FMGR-HSIP-0152(500), MONTGOMERY 29. NH-HSIP-0001(626), CALHOUN
*33. RACRNH-0006(587), AUTAUGA 37. RP-STPAA-HSIP-0010(558), HENRY
40. STPAA-0040(504), DEKALB 41. STPAA-0136(501), ETC., MONROE
44. STPNU-HSIP-0018(513), FAYETTE 45. STPNU-HSIP-0086(503), PICKENS
48. STPMN-0120(252), AUTAUGA 51. STPNU-0006(595), BARBOUR
52. STPNU-0051(521), BARBOUR 53. STPNU-1623(250), COFFEE
55. STPNU-HSIP-0021(580), ETC., MONROE 58. TAPBH-CRPBH-CMAQ-3715(262), JEFFERSON
61. ATRP2-05-2021-005, BLOUNT 62. ATRP2-28-2020-223, ETOWAH
* - WITHDRAWN FROM THE LETTING

The Bracket Ranges shown herein are to provide general financial information to Contractors and Bonding Companies concerning a Project's complexity and size. THESE BRACKETS SHOULD NOT BE USED IN PREPARING A BID, NOR WILL THESE BRACKETS HAVE ANY BEARING ON THE DECISION TO AWARD ANY CONTRACT.


1.BUILDF-NHF-0002(516) ,LAUDERDALE COUNTY

Contract Time: 375 Working Days

DBE Goal Percent:2.00

for constructing the Additional Lanes (Grading, Drainage, Pavement, Traffic Signals, and Traffic Stripe) on SR-2 (US-72/Florence Boulevard) from the junction of CR-30 (Indian Springs Drive) to the junction of Sky Park Road east of Florence. Length 2.106 mi.

The Bracket Estimate on this project is from $22,624,729 to $27,652,446 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $104.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


4.HSIP-0013(620) & ATRP2-13-2021-013 ,CLARKE COUNTY

Contract Time: 55 Working Days

DBE Goal Percent:3.00

for constructing the Roadway Improvements (Center Turn Lane Addition) on SR-13 (US-43) from the junction of Gail Drive to the junction of Toddtown Road southwest of Grove Hill. Length 0.733 mi.

The Bracket Estimate on this project is from $1,470,570 to $1,797,363 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $36.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


8.BR-I059(428) ,TUSCALOOSA COUNTY

Contract Time: 165 Working Days

DBE Goal Percent:1.00

for constructing the Bridge Deck Repair (Hydroblasting, Deck Rehabilitation, Bridge Rail Retrofit) and Guardrail Installation on I-20/I-59 (Northbound Roadway) from MP 63.721 to MP 72.064 in the West Central Region (Tuscaloosa Area) at various locations as indicated in the plans. Length 6.342 mi.

The Bracket Estimate on this project is from $4,918,069 to $6,010,973 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $18.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


11.HRRR-6122(250) ,TALLADEGA COUNTY

Contract Time: 45 Working Days

for constructing the Roadway Safety Improvements (Raised Pavement Marker Installation, Traffic Markings, and Rumble Strips) on CR-207, Grist Mill Road, Stockdale Road, Logan Martin Dam Road, Berney Station Road, Priebes Mill Road, Old Sylacauga Highway, Odens Mill Road, Goodwater Highway, and Ironaton Road at various locations as indicated in the plans. Length 62.837 mi.

The Bracket Estimate on this project is from $138,772 to $169,610 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $6.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


14.NH-0008(606) & HSIP-0008(605) ,LOWNDES COUNTY

Contract Time: 75 Working Days

DBE Goal Percent:1.00

for constructing the Planing, Resurfacing, Intersection Modifications (Grading, Drainage, and Pavement) and Traffic Stripe on SR-8 (US-80) from 0.700 mile west of the junction of Streety Road to 0.500 mile east the junction of SR-97. Length 4.319 mi.

The Bracket Estimate on this project is from $3,497,195 to $4,274,350 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $18.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


18.IM-I065(524) ,CHILTON COUNTY

Contract Time: 65 Working Days

DBE Goal Percent:2.00

for constructing the Micro-Milling, OGFC Surface Treatment, and Traffic Stripe on I-65 (Mainline) and Micro-Surfacing (Shoulders) from the SR-3 (US-31) Overpass to the SR-145 Overpass in Clanton. Length 6.236 mi.

The Bracket Estimate on this project is from $3,087,470 to $3,773,575 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $9.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


19.IM-I065(528) ,LIMESTONE COUNTY

Contract Time: May 24, 2024 Completion Date

for constructing the Welcome Center Replacement (Building Only) on I-65 north of Athens.

The Bracket Estimate on this project is from $4,851,000 to $5,929,000 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $28.00 per set.

A MANDATORY pre-bid conference is scheduled for 10:00 a.m. on Thursday, February 9, 2023, at the Alabama Department of Transportation, North Region Office; 1525 Perimeter Parkway; Suite 400; Huntsville, AL 35806 Any qualified bidder wishing to bid this proposal is required to have a company representative present at this MANDATORY pre-bid conference. Proposals issued to bidders who fail to attend the MANDATORY pre-bid conference and/or register their attendance will be voided and their bids will not be received nor considered.

View Items

Return To: Proposal Letting List (Top of web page)


20.IM-I459(321) ,JEFFERSON COUNTY

Contract Time: 70 Working Days

DBE Goal Percent:5.00

for the constructing the Micro-Milling, OGFC Safety Treatment, and Traffic Stripe on I-459 from the Grants Mill Road Overpass to a point 0.270 mile south of the SR-7 (US-11) Interchange southwest of Trussville. Length 5.408 mi.

The Bracket Estimate on this project is from $4,635,491 to $5,665,600 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $10.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


24.NH-0001(628) ,MADISON COUNTY

Contract Time: 90 Working Days

DBE Goal Percent:4.00

for constructing the Micro-Milling, Resurfacing, and Traffic Stripe on SR-1 (US-231/US-431) from the junction of Cedarama Drive Northwest to the junction of Grimwood Road/Walker Lane north of Meridianville. Length 5.759 mi.

The Bracket Estimate on this project is from $4,549,113 to $5,560,027 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $9.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


25.NH-0003(650) ,ESCAMBIA COUNTY

Contract Time: December 31, 2023 Completion Date

DBE Goal Percent:4.00

for constructing the Planing, Resurfacing, Guardrail Replacement, and Traffic Stripe on SR-3 (US-31) from a point 0.300 mile south of the Railroad Overpass (MP 57.181) in Flomaton to the south end of the Little Escambia Creek Bridge (MP 59.317). Length 2.080 mi.

The Bracket Estimate on this project is from $1,268,402 to $1,550,269 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $8.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


27.NH-FMGR-HSIP-0152(500) ,MONTGOMERY COUNTY

Contract Time: 110 Working Days

DBE Goal Percent:5.00

for constructing the Planing, Resurfacing, Safety Improvements (Bridge Rail Retrofit and Guardrail Installation), and Traffic Stripe on SR-152 from the I-65 Interchange to the SR-9 (US-231) Interchange. Length 6.402 mi.

The Bracket Estimate on this project is from $4,218,249 to $5,155,638 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $17.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


29.NH-HSIP-0001(626) ,CALHOUN COUNTY

Contract Time: 95 Working Days

DBE Goal Percent:3.00

for constructing the Micro-Milling, Resurfacing (Scrub Seal), Bridge Guardrail Retrofit, Guardrail Installation, and Traffic Stripe on SR-1 (US-431) from the junction of SR-144 northwest of Alexandria to a point 0.280 mile south of the junction of SR-204 (MP 246.800). Length 4.583 mi.

The Bracket Estimate on this project is from $4,455,990 to $5,446,210 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $5.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


33.RACRNH-0006(587) ,AUTAUGA COUNTY

Contract Time: 150 Working Days

DBE Goal Percent:4.00

for constructing the Planing, Resurfacing, and Traffic Stripe on SR-6 (US-82) Westbound Lanes and the Widening (Grading, Drainage, and Pavement), Planing, Resurfacing, and Traffic Stripe on SR-6 (US-82) Eastbound Lanes from the intersection of SR-14 to the intersection of SR-3 (US-31) to include Bridge Replacements over Autauga Creek and the Autauga Northern Railroad in Prattville. Length 2.350 mi.

The Bracket Estimate on this project is from $9,432,757 to $11,528,925 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $91.00 per set.

***WITHDRAWN FROM THE LETTING***

Return To: Proposal Letting List (Top of web page)


37.RP-STPAA-HSIP-0010(558) ,HENRY COUNTY

Contract Time: 120 Working Days

DBE Goal Percent:3.00

for constructing the Safety Widening, Micro-Milling, Resurfacing, and Traffic Stripe on SR-10 from a point east of Vann Mill Creek (MP 218.583) in Abbeville to the Georgia State Line. Length 11.568 mi.

The Bracket Estimate on this project is from $4,399,347 to $5,376,980 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $16.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


40.STPAA-0040(504) ,DEKALB AND JACKSON COUNTIES

Contract Time: 115 Working Days

DBE Goal Percent:4.00

for constructing the Micro-Milling, Resurfacing, Bridge Guardrail Retrofit, and Traffic Stripe on SR-40 from the intersection of SR-71 northeast of Dutton to the junction of SR-117 in Hammondville. Length 14.199 mi.

The Bracket Estimate on this project is from $6,988,097 to $8,541,007 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $5.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


41.STPAA-0136(501) & ATRP2-50-2022-202 ,MONROE COUNTY

Contract Time: 55 Working Days

DBE Goal Percent:1.00

for constructing the Resurfacing (Scrub Seal) and Traffic Stripe on SR-136 from the junction of SR-21 southwest of Monroeville to the junction of SR-12 (US-84) to include constructing Roadway Improvements (Right Turn Lane Addition) at the entrance to Excel High School. Length 6.081 mi.

The Bracket Estimate on this project is from $1,701,709 to $2,079,866 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $13.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


44.STPNU-HSIP-0018(513) ,FAYETTE COUNTY

Contract Time: 90 Working Days

DBE Goal Percent:2.00

for constructing the Safety Widening, Micro-Milling, Resurfacing, Bridge Guardrail Retrofit, and Traffic Stripe on SR-18 (US-43) from 0.260 mile east of the junction of 6th Avenue Southeast in Fayette to the junction of CR-91. Length 6.159 mi.

The Bracket Estimate on this project is from $4,092,446 to $5,001,878 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $13.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


45.STPNU-HSIP-0086(503) ,PICKENS COUNTY

Contract Time: 50 Working Days

DBE Goal Percent:1.00

for constructing the Safety Widening, Micro-Milling, Resurfacing (Scrub Seal), Guardrail Replacement, and Traffic Stripe on SR-86 from 0.320 mile east of the junction of Old Carrollton Road (MP 4.422) in Pickensville to the junction of Ladow Center Circle (MP 9.250) in Carrollton. Length 4.827 mi.

The Bracket Estimate on this project is from $2,567,287 to $3,137,796 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $11.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


48.STPMN-0120(252) ,AUTAUGA COUNTY

Contract Time: 30 Working Days

DBE Goal Percent:1.00

for constructing the Widening, Resurfacing, and Traffic Stripe on CR-27 from the junction of SR-14 to the junction of CR-29 and on CR-29 from the junction of CR-27 to the junction of SR-14 southwest of Prattville. Length 5.631 mi.

The Bracket Estimate on this project is from $1,077,389 to $1,316,809 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $3.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


51.STPNU-0006(595) ,BARBOUR COUNTY

Contract Time: 55 Working Days

DBE Goal Percent:2.00

for constructing the Micro-Milling, Resurfacing, and Traffic Stripe on SR-6 (US-82) from the Bullock County Line to the junction of Poplar Springs Road northwest of Eufaula. Length 8.140 mi.

The Bracket Estimate on this project is from $3,025,429 to $3,697,747 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $5.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


52.STPNU-0051(521) ,BARBOUR COUNTY

Contract Time: 65 Working Days

DBE Goal Percent:1.00

for constructing the Resurfacing and Traffic Stripe on SR-51 from the junction of SR-239 to the Bullock County Line. Length 10.031 mi

The Bracket Estimate on this project is from $2,977,106 to $3,638,685 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $5.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


53.STPNU-1623(250) ,COFFEE COUNTY

Contract Time: 40 Working Days

DBE Goal Percent:2.00

for constructing the Planing, Resurfacing, and Traffic Stripe on CR-636 from the junction of SR-87 to the junction of SR-27 south of Enterprise. Length 8.985 mi.

The Bracket Estimate on this project is from $1,491,127 to $1,822,489 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $5.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


55.STPNU-HSIP-0021(580) & STPNU-0047(507) ,MONROE COUNTY

Contract Time: 65 Working Days

DBE Goal Percent:1.00

for constructing the Micro-Milling, Resurfacing, and Traffic Stripe on SR-21 from the junction of SR-41 to the junction of SR-47 to include Traffic Signal Upgrades at CR-20 (Drewry Road) in Monroeville (Site 1) and on SR-47 from the junction of SR-41 to the junction of SR-21 in Monroeville (Site 2). Length 2.971 mi.

The Bracket Estimate on this project is from $1,399,746 to $1,710,801 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $14.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


58.TAPBH-CRPBH-CMAQ-3715(262) ,JEFFERSON COUNTY

Contract Time: 190 Working Days

DBE Goal Percent:4.00

for constructing the Streetscape Improvements on 2nd Avenue South from the intersection of 24th Street South to the intersection of 32nd Street South; on 27th Street South from the intersection of 2nd Avenue South to the intersection of 3rd Avenue South; and on 29th Street South from the junction of 2nd Avenue South to the intersection of 3rd Avenue South in Birmingham. Length 0.850 mi.

The Bracket Estimate on this project is from $2,476,024 to $3,026,252 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $55.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


61.ATRP2-05-2021-005 ,BLOUNT COUNTY

Contract Time: 45 Working Days

DBE Goal Percent:2.00

for constructing the Roadway Improvements (Left Turn Lane Addition) on SR-75 North at CR-26 southwest of Susan Moore. Length 0.227 mi.

The Bracket Estimate on this project is from $432,047 to $528,057 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $14.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)


62.ATRP2-28-2020-223 ,ETOWAH COUNTY

Contract Time: 45 Working Days

DBE Goal Percent:6.00

for constructing the Intersection Improvements (Grading, Drainage, Pavement, and Traffic Stripe) and Roadway Improvements (Lane Reconfiguration) on SR-1 (US-278/US-431) at SR-291 (Hood Avenue) in Gadsden. Length 0.392 mi.

The Bracket Estimate on this project is from $783,079 to $957,097 .

A Bidding Proposal may be purchased for $5.00. Plans may be purchased for $16.00 per set.

View Items

Return To: Proposal Letting List (Top of web page)